Chapter 10 - The comparative economic costs of maintaining, repairing and refitting large Naval vessels throughout their useful lives when constructed in Australia vice overseas
Background
10.1
When considering the costs of an acquisition, many witnesses emphasised
the need to take account of the through-life expenses which are many times
greater than the initial cost of acquisition. Most accepted that the rule of
thumb applying to large constructions, including a typical warship, is 30 per
cent in initial acquisition costs compared with 70 per cent through-life
support (TLS) costs.[1]
This chapter examines the comparative economic costs of maintaining, repairing
and refitting large naval vessels throughout their working lives when
constructed in Australia against an overseas build.
Through-life costs
10.2
The 2006 ACIL Tasman report noted that the Navy requires an in-country
capability to undertake repair and maintenance. It noted further that this
requirement is not only because of strategic and operational issues but also a
result of personnel policies for crew leave and training.[2]
It came to the conclusion:
Because ship and submarine repair and maintenance must for the
most part be performed in Australia and are constrained by home porting and
capability sustainment in the repair and maintenance sector international
comparisons would provide minimum insights into productivity in the Australian
repair and maintenance context.[3]
10.3
Defence confirmed unequivocally that Navy requires major support for its
warship to be conducted in or near the ship's home port.[4]
It identified two important considerations that Navy requires:
- the advantages and reduced impact on ship's company of conducting
ship support and crew rest and recreation in parallel; and
- proximity to support infrastructure such as ammunitioning point,
ranges and fleet assets, necessary to work up the crew and platform after
maintenance.
10.4
It explained:
Navy's requirement does not prevent maintenance being conducted
at repair facilities that are not in the proximity of the ship's operational
base. It is sometimes necessary to conduct maintenance at other locations. For
example,
- Collins class
Full Cycle Docking maintenance is conducted at Osborne in South Australia as a
consequence of a Federal Government decision to retain the relevant skills
developed during the build program...;
- because warships
can be deployed anywhere in the world, Navy has successfully conducted major
repair activates at many facilities remote from the ships' home port.[5]
10.5
Defence made clear that while it is not essential to have a repair
facility close to a ship's home port it is 'desirable' to meet Navy's
requirements'. Given that Defence requires its naval fleet to be repaired and
maintained in Australia, the extent to which an in-country build influences these
through-life costs is a significant consideration.
The lack of data
10.6
The lack of sufficient data prevented the committee from obtaining any
sensible or reliable statistics on the comparative economic productivity of
building a naval vessel in-country compared with overseas. The same difficulty confronts
the committee in endeavouring to determine the comparative costs of TLS for
large naval vessels when constructed in Australia vice overseas. As ASC's
submission noted:
In nearly every case Australia has built significantly different
ships to those built elsewhere and coupled with the fact that comparative
pricing data rarely exists, assumptions about life-cycle costing and the
relative costs of through-life support differ.[6]
10.7
Despite this lack of data, many witnesses took the view that there was a
strong connection between savings that could be made repairing and maintaining
a ship in Australia if that ship were built in-country.
10.8
As noted in the previous chapter, the Allen Consulting Group report
queried the cost savings that would accrue to the AWDs and the LHDs because of
the small production run. It nevertheless accepted that if the ships were not
built in Australia the capability to maintain and provide TLS may be
compromised. The 2006 ACIL Tasman report suggested that linkages between
shipbuilding and TLS can be very important to the productivity and cost of ship
repair and maintenance.[7]
10.9
It cited findings from its 2002 study which showed that the in-service
support benefits associated with the arrangements established for the
Minehunters included:
- cost savings for Defence in money and resources for in-service
support;
- shorter turn around times than out of country support,
particularly in times of international crisis;
- increased effectiveness during operations with a 24 hour
technical enquiry service;
- opportunities for value adding such as the multi-functional
system team approach used by ADI and Thales Underwater Systems to support the
Minehunter Coastal Vessels;
- development of related and supporting industries that create
alliances between systems suppliers and contractors which improve local
capability to deliver repair and maintenance services; and
- ability to provide more consistent employment for specialist
skills in systems, systems integration and application.[8]
10.10
These findings are consistent with the general view of a number of
submitters who suggested that savings are made on TLS if the ship is produced
in-country. They highlighted the importance of taking account of the advantages
gained for TLS by building in-country.[9]
10.11
Rear Admiral (Ret'd) W. J. Rourke argued that the costs of
maintaining, repairing and refitting ships that have been constructed in
Australia will be significantly less than the costs of maintaining ships
constructed overseas.[10]
Drawing on past performance, the Submarine Institute of Australia noted that construction
in Australia of naval vessels (including the Collins class submarines)
generated significant economic and other benefits including the prospect of
ensuring adequate through-life support of the vessels.[11]
10.12
Saab Systems Pty Ltd also asserted that 'the long term economic outcome
is that Australian based support for the life of a ship is much cheaper than
foreign based support or introduction of a new development or support facility
into Australia'.[12]
Mr Mark Proctor, Business Development Manager, Saab Systems Pty Ltd, added:
The greatest cost of a warship is the cost of support and
upgrade provided during its working life. This is most economically provided
from Australian based organisations whose origins need to be during the
construction and initial delivery phase.[13]
10.13
ASC concurred with the view that generally it would cost more to
maintain, repair and refit a foreign-built vessel than one produced
domestically.[14]
More specifically, Thiess Pty Ltd argued:
Repairing ships built overseas can cost 2 to 3 times as much as
maintaining in country. The offshore scenario does not provide repairs or parts
at short notice and does not provide or retain the adequate expertise to
diagnose problems in very complex ships. Repairs of battle damaged ships or
major change of use of ships cannot be accommodated if industry is not building
the ships in country.[15]
10.14
The Australian Industry Defence Network Inc submitted that the 'ability
of Defence to rely on local sources for repairs, maintenance and spares will
lead to substantial reductions in repair turnaround times...which will have an
impact on the quality and overall costs of stock holdings'. It also stated that
'beyond repair and maintenance, involvement in the construction phase will
position many Australian companies to play an active role in subsequent
upgrades'.[16]
10.15
The Victorian government also pointed to the cost savings gained during
the working life of a vessel if it is constructed in country. It argued that
familiarity and experience with the warships results in more efficient through
life support.[17]
The Government of Western Australia agreed with this view. The Hon. Mr Francis Logan,
the Western Australian Minister for Energy, Science and Innovation, explained:
There is no doubt that the through-life costs will go up if the
corporate memory, the knowledge, the skills and the intellectual property is
not contained in the place where the ship will eventually undertake its
service.[18]
10.16
While many submitters maintained that the economic costs of maintaining,
repairing and refitting large naval vessels throughout their useful lives is
greatly lessened by constructing those vessels in Australia, they did not
produce statistics to substantiate this assumption.
The ACIL Tasman estimate
10.17
In broad quantitative terms, the main guide for the committee on this
issue is the modelling by ACIL Tasman. The February 2000 report, A Case
Study of the ANZAC Ship Project, found that:
- local or overseas supply is determined on a case by case basis:
items that are part of pools through which components are rotated may be most
economic to acquire from overseas; items that are uniquely developed or depend
on timeliness of supply are often sourced locally;
-
the cost of repairs, maintenance and spares is cheaper if the
original source of supply is local because of shorter repair turn around times
for locally produced items. Shorter repair turn around times mean a lesser
quantity and overall cost of spares that need to be held;[19]
and
- the ANZACs' annual repair costs of $45 million could be higher by
a factor of two if the original source of supply had been overseas. Assuming a
long term bond rate of 7.12 per cent over a repair period of 25 years, the estimated
repair cost saving is A$518 million.[20]
10.18
It should be noted that Ms Denise Ironfield, the author of the reports
on the Minehunters and the ANZACs, informed the committee that despite her
efforts to obtain information from Defence, she had no government data but was
given 'very comprehensive information by Tenix and ADI', the respective primes.[21]
She explained that she spoke to Defence:
...I was trying to get some information from them on through-life
support issues. Both reports were very interested in the through-life aspects
of Australian industry involvement. However, in both instances it was extremely
difficult to get very much information from the Department of Defence on the
implications of the Australian build on through-life support.[22]
The Department of Industry response
10.19
The Department of Industry, Tourism and Resources' (DITR) submission to
this inquiry questioned some of the findings from the ANZAC study and made the
following points regarding comparative costs of TLS:
- Domestic equipment can be installed in Australia for an overseas
build. So, even with an overseas build, the costs and problems with maintaining
overseas sourced equipment can be avoided.
- ACIL Tasman's repair savings figure of A$518 million for the
ANZAC project must be discounted by the proportion of Australian produced
equipment that would be sent overseas to support an offshore build of the same
vessel or fitted when the ship arrives in Australia. If this proportion is
half, then the repair cost saving from the in-country build is A$259 million
(half of A$518 million).
- The ACIL Tasman long-term government bond rate of 7.12 per cent
underestimates the risk—a 10 per cent rate is more appropriate which reduces
the savings estimate to $408 million.
- Australian built ships will still depend on some overseas sourced
equipment.
- Factors other than the source of initial construction supplies
are significant in minimising repair costs. These include automated processes
in the vessel design to reduce the whole of life crew costs and access to intellectual
property (IP) for repair.
- Developing the in-country skills and knowledge for repair and
maintenance does not depend on the location of the build—personnel can be
posted offshore to participate in the build. However, 'there are greater
benefits (and risks) from conducting an onshore build of complex vessels than
simple vessels'.[23]
10.20
The committee accepts that some proportion of foreign-built RAN vessels
will be sourced from Australian supplies and generic supplies that can be
readily replaced in Australia. To this extent, it notes DITR's claim that ACIL
Tasman's estimate is inflated. The committee also understands that Australian-built
ships will look to overseas sources for some products or services. According to
Defence, however, a local build is far more likely to have higher Australian
industry content than a foreign-built vessel, and is therefore more likely to
have original parts in stock for repair.[24]
It was of the view that:
...the economic costs of maintaining, repairing and refitting
large naval vessels throughout their useful lives is greatly lessened by
constructing those vessels in Australia.
10.21
Ms Ironfield, in response to a question about the criticism of using the
government bond rate of 7.12 per cent, noted that this figure was equal to the
long-term rate in December 1999. She noted, however, advice from Defence
contained in the report that:
...experience with other major defence projects constructed in Australia
is that sourcing locally, rather than overseas, achieves substantial savings in
repair turn around times and spare stock savings for a comparable operational
availability. These savings can flow through to cost and productivity savings
for Defence which in turn translates into improved welfare for the economy as a
whole...[25]
10.22
She explained that given the ANZAC ships have a twenty-five to thirty
year service life, savings of sourcing repairs and maintenance would be
substantial. Furthermore, referring to the ACIL Tasman report, she told the
committee:
...assuming overseas sourcing doubled annual costs for repairs,
and maintenance, and spare holdings for the ANZAC ships, the saving to the
Australian economy...would be the one quoted—that is, the $515 million.[26]
10.23
In answer to a written question on notice from the committee, however,
Defence stated that 'for a low to moderate technology basic platform like the
Amphibious-LHD there is only a low correlation between build capability and
sustain/upgrade capability'.[27]
It considered that there could be relatively few savings in whole-of-life cost
from choosing to build the LHDs locally. It expected that the greatest savings
over the life of the ship would come from full access to and use of ship design
and intellectual property across the entire capability. ASC also understood
that while generally it would cost more to maintain, repair and upgrade a
foreign-built vessel than one produced in-country, the savings would depend on circumstances
of the specific case and in particular the complexity of the ship.[28]
Skills, knowledge and intellectual
property
10.24
The availability of equipment is only part of the explanation for
potential TLS cost savings from a local build. A broader reason is that an
in-country build develops the skills and knowledge base needed for subsequent through
life support.[29]
ASC's submission stated that the challenges of repairing and maintaining a
foreign-built vessel in-country depend on: the level of familiarity with key
systems and original equipment manufacturers; access to the foreign shipbuilder
and the ship's original drawings; and access to the parent navy's technical
staff.[30]
For example, it is more expensive to train labour to repair and upgrade a
vessel that was built offshore than it is to employ the skills used in the
construction phase for through-life support.
10.25
Several witnesses also argued that the greater the complexity of the
warship, the greater the need to build in-country to develop the domain
knowledge and skills for through-life support.[31]
The committee notes that this is the rationale for Defence's support for
building the complex AWDs in-country: it is much less enthusiastic to build the
less complex LHDs in-country.
10.26
DITR, among others, suggested that these skills can be developed by
posting local designers offshore during the construction phase. This
arrangement would need to ensure that access is allowed to the offshore
builder's resources.
10.27
An in-country build may not be without its own challenges for through-life
support. Engineers Australia argued that there is often a challenge in
sustaining in-country skills once the ship transitions from the construction phase
into naval service.[32]
10.28
Contractual arrangements guaranteeing access to IP and design rights are
important to cost-effective through-life support.[33]
Gibbs & Cox Australia's submission noted that in-country design of warships
will mean that the Commonwealth will have control over the amount of life cycle
cost savings. Difficulties can arise with TLS costs when the IP is not
Australian-owned. Most notably, ASC's resolution of a contractual issue with IP
owner Kockums was crucial to enable it to secure the Collins class refit
contract. As ASC's Managing Director Mr Greg Tunny told the committee, without
the IP and the repair and refit contract 'ASC would not exist'.[34]
Conclusion
10.29
The previous chapter concluded that given that overseas countries are
unlikely to remove the various forms of assistance and protection given to
their local naval shipbuilding industry, Australia's builders of large naval
ships must compete on an 'unlevel playing field' to some extent. Evidence
suggests, however, that the comparative costs of producing a ship in Australia would
improve when the total amount of the acquisition, including the ship's through-life
support, is considered.
10.30
Indeed, many submitters produced strong and credible arguments that savings
accrue to the repair and maintenance costs if the ship is constructed
in-country. They include savings generated by the substantial reductions in
repair turnaround times and the more efficient through-life support that
results from familiarity and experience with the warships.[35]
10.31
Intuitively, these assumptions appear logical and sensible. However, the
lack of data on this issue makes any reliable or accurate assessment difficult.
ACIL Tasman has produced some figures which provided the basis for discussion. But
even in these cases, the author of the studies noted that little government
data was made available.
10.32
ACIL Tasman estimated that annual TLS costs could be twice as high if
foreign supplies had sourced the ANZAC Ship Project. This is due to shorter
repair turn around times and lower stocks of spares from local sources of
supply. However, DITR noted that local equipment can be used for an overseas
build, thereby avoiding the higher costs associated with repairing overseas-built
ships in Australia. It argued that the ACIL Tasman TLS estimate must be
discounted by the proportion of equipment that could be sent overseas to
support an offshore build of the same vessel.
10.33
The committee also accepts that through life support productivity savings
from an in-country build derive in large measure from developing the skills and
knowledge during the construction phase needed for this support. It notes that
measures can be taken to compensate for the skills and knowledge deficiency
should the ship be built overseas. For example, personnel can be posted
offshore to participate in the build in order to develop the in-country skills
and knowledge for repair and maintenance.[36]
10.34
Even so, the committee's evidence was unanimous in the view that
building warships in-country would deliver greater TLS savings than an offshore
build. Defence also agreed with this view but added the qualification that the
savings from an in-country build depends on the complexity of the ship. It used
the example of the less complex LHDs, stating 'there could be relatively few
savings in whole-of-life cost from choosing to build locally'.[37]
10.35
To this stage, the committee has considered the costs of building and
repairing a naval ship in Australia vice overseas within a narrow economic
framework. The following chapter takes a broader approach and examines the
wider benefits that accrue to building large naval ships in Australia.
Navigation: Previous Page | Contents | Next Page