Chapter 6 - Infrastructure
6.1
The shipbuilding industry is capital intensive requiring substantial
equipment and installations that are expensive to build and maintain. A
shipyard itself is a major industrial facility that occupies large tracts of
land with access to water.[1]
Docks, slipways, piers, cranes, large covered workshops as well as supporting
administrative buildings and amenities are needed. The age, condition and
suitability of its facilities clearly influence a shipyard's capacity to build modern
naval vessels.
6.2
As noted in the previous chapter, much of ship building activity takes
place in sites scattered around the country. Activities, such as steel
fabrication, may also be capital intensive and require substantial
infrastructure. This chapter evaluates the infrastructure in Australian
shipyards and associated sites to determine its capability to sustain a viable
naval shipbuilding industry and its capacity to meet the likely demands of Australia's
navy.
6.3
There are a number of phases in shipbuilding—design, production,
outfitting, testing, commissioning and trials.[2]
The UK's naval shipbuilding report spelt out the facilities required in the
construction of warships which it asserted, 'cannot be developed or expanded without
significant resources, planning effort, and a long lead time'.[3]
It divided ship construction into three main phases together with the main
facilities required in each phase.[4]
Pre-Final Assembly
|
|
|
|
|
|
|
Final Assembly
|
|
|
- Dry docks
- Floating docks
- Slipways
- Land-level areas
- Ship assembly
|
|
|
|
Afloat Outfitting
|
|
|
- Piers
- Quays
- Locks
- Any location specified as such
|
6.4
There is some overlap in the use of different facilities throughout each
phase. For example, the cranes, shops or fabrication facilities associated with
the final assembly are used throughout the other phases.
Investment in infrastructure
6.5
Modern facilities are a precondition for success in naval shipbuilding.[5]
The recent First Marine International study of major shipyards graded shipyards
according to their level of technology. It identified five categories of
shipyards ranging from the most basic to the highest state-of-the-art
shipbuilding technology.[6]
6.6
Modularisation fits into the highest levels of technology as determined
by the First Marine International study. Some shipyards in Australia have
actively embraced this technology. Indeed, a number of witnesses believed that Australia
has gained a comparative advantage from modularisation and assembly in Australia.[7]
6.7
Keeping infrastructure up-to-date with the latest advances in
shipbuilding is costly. ASC noted that it and other Australian shipbuilders
have invested heavily in new up-to-date facilities to satisfy the requirements
of success. These include 'undercover construction and land level transfer to
allow highly efficient outfitting on the hard stand' and access to key warship
intellectual property.[8]
6.8
The Government of Western Australia recognised, however, the
difficulties companies have in investing in major capital works:
Provision of these facilities involves high fixed costs which
can only be recouped over the long term and which even the largest companies
have difficulty absorbing. This constitutes a form of market failure in which investments
that would enhance aggregate state and national welfare are not forthcoming
because individual firms selling into specific markets (like resources projects
or repair/maintenance of naval ships) cannot obtain sufficient individual
benefit to warrant making the investment by themselves.[9]
6.9
The South Australian government also noted that a major challenge for
the industry concerns investment in sustainable, modern, competitive
infrastructure.[10]
6.10
Over and above the investment by Australian shipbuilders in their own
infrastructure, governments have played a significant role in developing
necessary facilities to support large construction projects. Thiess Pty Ltd remarked
on the recent practice involving state investment in infrastructure which is
then rented to the shipyards 'at prices which could vary depending on the
willingness of the respective government to help the industry set up in their
State'. It elaborated on the advantages that accrue to industry from this type
of assistance:
The main attraction is that they are leased for the duration of
the project and therefore do not need to be fully amortized on the project.
Because they remain the property of the State, if they are sufficiently
generic, they can be reused by other industries such as the resource industry.[11]
6.11
A notable development based on this model of state involvement is the
construction of a Common User Facility (CUF) to attract shipbuilding and other manufacturing
industries. It is a new concept embraced by sectors of the Australian
shipbuilding industry and supported by a number of state governments.
6.12
The CUF is designed to form part of a broader industrial complex. Its
use is not limited to shipbuilding. A number of witnesses underlined the
advantages of having a CUF which can be used by different companies from a
number of industries, particularly the resources sector. The Australian
Shipbuilders Association Ltd noted:
Broadly, State Governments provide a site with state of the art
infrastructure; wharfage and ship lift capacity on a lease basis. The
availability of such infrastructure allows shipbuilders/repairers to undertake
major projects without the barrier to entry of capital infrastructure costs,
which might otherwise be incurred. The site can be leased for the duration of
the project, reducing cost. A CUF can and is also used by other industries, in
particular the resource industry.[12]
6.13
Mr David Miller, Tenix, regarded the availability of the CUF as one of the
great advantages that shipbuilders have in Australia.[13]
He stated:
We do not have first-hand experience in South Australia but,
certainly, our Tenix site is immediately adjacent to the common user facility
in Henderson. Over the past year we have undertaken a number of naval repairs
on Anzac frigates using that facility. We are currently converting the civilian
oil tanker Delos into an underway replenishment ship for the Australian
Navy. It is soon to be the HMAS Sirius. The availability of that
infrastructure allows us to take on major projects without the barrier to entry
that we might otherwise experience if we had to go out and capitalise all of
that ourselves.[14]
6.14
There are three CUFs in place or planned in Australia: WA, SA and Queensland.
The Australian Shipbuilders Association Ltd stated that they are on a scale
'suitable for the fabrication and fit-out of large ship-section modules'.[15]
They are designed to accommodate not only the major shipbuilders in Australia
but also regional engineering and fabrication firms with their own labour and
resources.[16]
It suggested that this wider accessibility 'significantly augments Australia’s
overall “shipbuilding” capability through access to an extensive, much broader
and geographically spread pool of resources with relevant skills'.[17]
Overview of shipyards in Australia
6.15
There are numerous naval shipyards located around the Australian
coastline. Some, such as Henderson in Western Australia, are green field sites
that have attracted significant investment. Others, however, are well
established with a long tradition of naval shipbuilding (see paragraphs
3.2–3.7).
6.16
In 2002, after examining the physical infrastructure of Australian
shipyards, the Naval Shipbuilding and Repair Sector Strategic Plan concluded that:
It is important to note that no Australian shipbuilding facility
can currently accommodate the consolidation/final assembly of Navy’s major
surface ships planned under SEA4000, JP2048/2027 and SEA1654. This assumes the
following physical characteristics of these major ships:
- a future Air Warfare Destroyer (AWD) will probably be in the
order of 6,000-9,000 tonnes displacement and a length of 130m to 150m; and
- future Amphibious and Afloat Support ships that will be somewhat
larger and considerably wider than the AWD and also of considerably greater
laden tonnage.[18]
6.17
It suggested the following two alternatives if vessels were to be
constructed in-country:
- varying degrees of infrastructure investment in an existing
facility; or
- the development of a new green-field site.[19]
6.18
Significant developments have taken place since the publication of the
strategic plan in 2002 including additional investment in infrastructure at a
number of shipyards. It should be noted that the plan was not adopted by the
government. Also, in May 2005, the government selected ASC as the preferred
tenderer for the AWD project.
6.19
Before continuing a general appraisal of the current and future
infrastructure requirements to meet Navy's future acquisition program, the
committee considers the infrastructure at Australia's major shipyards.
Infrastructure and the lead naval shipyards in Australia
6.20
There are eight shipbuilding sites of particular relevance to the
committee—Henderson in Western Australia, Osborne in South Australia;
Williamstown in Victoria; Newcastle (ADI), Newcastle (Forgacs) and Garden Island
in New South Wales; and Cairncross and Cairns in Queensland.[20]
Some of these shipyards date back to the 19th century; others,
however, have developed or are developing to accommodate the newest
developments in technology particularly the construction of larger and more
sophisticated modules. The following section looks at recent developments in
these shipyards and the level of government support for infrastructure
development.
The Australian Marine Complex at Henderson
in Western Australia
6.21
The Australian Marine Complex (AMC) is at Cockburn Sound, south of Perth.
It is situated next to a 'massive technology park', including an industrial
estate, where companies can position themselves next to the AMC. The complex is
divided into four specialist precincts and takes advantage of the advances in
technology and the benefits that derive from catering for diversification in
products and markets. It recognises the cost savings to be gained from
integrating Australia's naval shipbuilding and ship repair capacity into a
broader marine complex that also provides for the needs of the oil and gas
sector. According to the Hon. Mr Francis Logan, Minister for Science and
Innovation in the Western Australia government, this heavy engineering/marine
industry cluster is 'unique in Australia as a matrix for a sustainable naval
shipbuilding capability'.[21]
The AMC is not intended for shipbuilding alone but is a facility that can provide
for the needs of a wide range of companies and industries.[22]
6.22
The Western Australian government has demonstrated its preparedness to invest
in important infrastructure to support industry including naval shipbuilding. It
informed the committee that it and the Commonwealth government initially
invested a total of $180 million ($100 million from the State government and
$80 million from the Commonwealth) in the Australian Marine Complex Common User
Facility (CUF). This initial investment, which was completed in mid-2003, is
owned by the State government and operated by AMC Management (WA) Pty Ltd.
Common User Facility (CUF)
6.23
The CUF is a state-of-the-art commercial heavy engineering facility
located in the AMC. The facility is substantial and sufficiently large to
accommodate a number of projects being carried out concurrently. It is not
dedicated to one user or even one industry and will have applications other
than for naval shipbuilding.[23]
In particular, it is expected to service the oil and gas, resources, marine and
defence industries.[24]
The CUF comprises:
- a protected deepwater harbour—10 metres water depth;
- a 15,000 tonne service and heavy lift wharf;
- a 3,000 tonne load out wharf;
- a 4,800 square metre mobile assembly hall with a 200 tonne mobile
portal crane;
- 39 hectares of paved laydown area; and
- offices, workshops and other amenities.[25]
6.24
It is leased out by the government on the basis of whoever wishes to use
it under the following arrangements:
Parties using the facility provide their own management and
workforce and accept normal project accountabilities. They use only the facilities
as and when their projects so require: for example, a company may require the
use of the mobile assembly hall and a project office for some months and then
use the load out wharf for two weeks. The CUF only charges the company for its
use of those specific facilities for that particular period. This arrangement
greatly reduces set up costs for the project and overheads for the company,
thereby enhancing their ability to win such contracts.[26]
6.25
The Hon. Mr Francis Logan also referred to the incentive that this large
modern facility offers to Australian industry:
Not one of those companies could afford that type of facility
themselves... and they would not want to hold onto it because of the ongoing
costs of running those types of facilities. But they can get access to it at
any point in time, and that is the paradigm shift—and it is in keeping with the
way in which the rest of the corporate world is going.[27]
6.26
Mr Michael Deeks, Chairman, Nautronix Ltd, envisaged that companies like
Austal and Tenix would use the floating dock for other commercial ship
construction work. He also expected other, non-naval businesses, such as heavy
fabrication, to use it and noted that 'One company in particular wants to use
the floating dock basically for testing purposes—to submerse fixtures that go
on seabeds for the oil and gas industry'.[28]
Clearly, the infrastructure will be used for purposes other than just naval
ship construction.

The committee visited the Common User Facility
(CUF) at Henderson south of Perth.
Recent developments at the AMC
6.27
Over the last three years, the AMC has attracted greater business. In
December 2003, ASC was awarded the $3.5 billion 25 year contract for the repair
and maintenance of the Collins class submarines. The Federal government and
State government, in conjunction with the West Australian marine industry have
established the home port of the submarines in Western Australia.[29]
Other developments have encouraged further investment. These include Tenix
Western Australia securing a $60 million contract to convert the Korean oil tanker
Delos as a replacement for HMAS Westralia and the ANZAC Alliance
needing berthing in order to undertake ship upgrades worth $500 million.
6.28
The Western Australian government responded to this growing demand by
committing a further $81.1 million toward additional infrastructure at the CUF
including:
- a floating dock to launch and dock large ships and a rail transfer
system to allow construction and repair within the CUF’s undercover facilities;
- an extension and upgrade of the existing wharves to accommodate
all types of naval and commercial vessels; and
- the installation of marine services such as power, seawater fire
main, wharf communications and sewerage off-take.[30]
6.29
According to the Western Australian Chamber of Commerce, the current upgrade
means that the CUF:
...could have five ships tied up at dock at the same time and they
could have two platforms being built, two amphibious ships and a submarine
being refitted—and this is just in the common-use facility. At the same time,
you have not even called on Austal’s or Tenix’s premises. This is a very
significant development that has occurred down there and you could have a lot
of work in there. At the moment, there is a little bit of work in there
compared to how much work you could put in there.[31]
6.30
The Australian Manufacturing Workers' Union (Western Australia Branch) singled
out this massive and expanding manufacturing precinct at Henderson to
demonstrate the extent of government commitment to developing infrastructure
and the benefits flowing from it:
The AMC accounts for approximately 55% of national shipbuilding
production, and has produced vessels in excess of $2 billion dollars in the
last decade. 25% of the world's demand for high-speed ferries is met by
businesses at the AMC. The AMC is an internationally competitive manufacturing
precinct with a proven record of large-project shipbuilding.[32]
6.31
The Government of Western Australia expected that other long term
stakeholders such as the Australian Navy and the ANZAC Alliance would also make
contributions to the operation and upgrade of the CUF commensurate with their
respective usage of the facility.[33]
Indeed, ASC intends to:
- build its own new purpose built submarine support facilities
(worth an estimated $20 million) in the Australian Marine Complex, adjacent to
the CUF; and
- contribute a further $5 million in capital towards the common user
transfer system connecting the floating dock to the ASC submarine support
facility.[34]
6.32
To April 2006, the CUF had achieved a million man-hours and $100 million
worth of work.[35]
The Western Australian government believes that the success of the CUF to date
demonstrates its existing capability to undertake naval maintenance work and
establishes its claim for consideration for future naval shipbuilding.[36]
Additional investment
6.33
The Australian Manufacturing Workers' Union (Western Australia Branch)
noted the planned upgrade of AMC including the floating dock and rail transfer
system and was of the view that:
Unlike other Australian locations, the AMC would not need
significant additional infrastructure to cope with a major RAN shipbuilding
contract. Such a project would, for the most part, merely require an expansion
of current capacity rather than the construction of new facilities. [37]
6.34
Even so, the Government of Western Australia is considering further
developments, over and above the current commitment.[38]
It has stated that it would invest further should the site be included in the
construction of the LHDs. According to the Hon. Mr Francis Logan, his government
is 'prepared to build the second half of the floating dock should the AMC be
selected as the site for integration and consolidation of the amphibious
support ships'.[39]
6.35
Although naval shipbuilding is a highly specialised industry there are
strong parallels with the infrastructure needs of the oil and gas sector and
more generally the resources sector. The developments taking place in Western
Australia demonstrate the growing synergy in technologies that is occurring
and allowing other industries to use the same facilities. The Western Australia
Chamber of Commerce and Industry observed that the risk profile for an oil and
gas platform or an LPG plant is similar to the defence industry which
encourages the technologies used in these sectors to merge.[40]
It saw a unique opportunity for both industries to take advantage of the
growing complementarity between the two sectors.[41]
Osborne in South Australia
6.36
In 2002, the Australian Naval Shipbuilding and Repair Sector Strategic
Plan reported on the infrastructure at Osborne in South Australia. It recorded
that the 20 acre site had a shiplift (5048 dwt capacity, 80m x 20m), side
transfer rails, manufacturing halls, adjacent hull and outfitting workshops,
various workshops and alongside berthing of 160 metres. The strategic plan
found that the site had the capacity to be developed to cater for a
considerably greater level of demand, including consolidation and upgrade of
vessels proposed under SEA 4000, JP2048/JP2027 and SEA 1654.[42]
6.37
At the same time, a report from the Australian Strategic Policy Institute
(ASPI) noted that significant facility development was required at the site for
participation in major surface ship module construction or ship assembly.[43]
6.38
Since 2002, the South Australian government has actively promoted the
naval shipbuilding industry in that state by committing to develop further the
site at Osborne. It has developed a plan that builds on the presence of ASC at
Port Adelaide to 'provide the critical mass of naval shipbuilding
infrastructure and a skilled work force that can deliver the next generation'. It
informed the committee that planning is well advanced to 'transform industrial
land at Port Adelaide into a modern internationally competitive shipbuilding
site that can become the future hub of naval warship construction in Australia'.[44]
The Allen Consulting Group noted that:
...the ASC at Osborne has a capability in conventional submarine
construction and support that is probably unrivalled outside Europe.[45]
6.39
The facility at Osborne has been designed around common user facilities
to enable any shipbuilder to come onto the site to use the infrastructure.[46]
The centrepiece of the infrastructure aspect of the plan comprises a 10 000
ton ship lift, wharf and transfer system representing a current budget of
approximately $130 million.[47]
6.40
The configuration of the complex enables a builder from the back block,
where the infrastructure will be developed, to gain access to the water through
the ship lift.[48]
Thirty hectares of land has been set aside where the government hopes to see a
'fully integrated submarine and shipbuilding supplier and subcontractor
precinct'.[49]
Adjacent to the shipbuilding infrastructure, the government intends to make
available more than 100 hectares at Port Adelaide as a 'high technology defence
industrial hub'.[50]

This
is an impression of ASC's site at Osborne when current developments are completed. The
Collins-class submarines were constructed at the facility to the centre-right
of picture, while some of the AWD modules will be constructed in the new
facilities to the left of picture. The committee thanks ASC for their permission
to reproduce this picture.
6.41
Mr Andrew Fletcher, CEO, Port Adelaide Maritime Corporation, noted
progress in achieving the state government's objective to develop a long-term
sustainable defence base at Osborne:
There are the common user facilities...There is the suppliers
precinct at the rear. That was initially 30 hectares; we now control 500 hectares
of land on the peninsula and in the adjacent area for future development. There
is also the development of the air warfare destroyer system centre and the
skills centre in a hub that we are building.[51]
6.42
The base itself is in the heart of South Australia's busiest
international port. It is 18 kilometres from the central business
district and 16 kilometres from the international airport. According to Mr Fletcher:
...on completion of the road and rail bridges across the Port
River, which are anticipated by the end of next year, it will be connected
directly by rail and road to the rest of Australia. So it is a unique piece of
real estate that is attractive not just to the defence industry and the SMEs
supporting the defence industry but to industry as a whole in South Australia...[52]
6.43
While the AWDs are to be assembled at Osbourne, 70 per cent of the
module construction is expected to be outsourced. It should be noted that
Defence informed the committee that the Commonwealth is not funding the
development of any infrastructure for this project. It stated that the
government of South Australia is funding the development of a Common User
Facility (approximately $115 million) while ASC is funding about $69 million of
infrastructure development. Defence informed the committee that the
Commonwealth is to reimburse ASC 'for the depreciation costs of the new
infrastructure, which was taken into consideration in the comparative and value
for money evaluation of ASC's offer against other tenders'.[53]
Older shipyards
6.44
Up to this stage, the committee has focused on the newer shipyards. Australia
also has shipyards that have a long history of shipbuilding. Williamstown, Garden
Island and Cockatoo Island were designed in the 1880s to look after old
seafarers. According to Mr Peter Croser, Gibbs & Cox Australia Pty Ltd, the
cost of changing their infrastructure would be reflected in the cost of the
program. He does not argue that such sites do not have the capability but that
it depends on where they are in their infrastructure development. He stated:
What I would say is that once the infrastructure on a greenfield
site is in place it obviously will be to a higher standard and more tailored to
currently and to the future than the existing ones, and therefore will be a
standout in that regard. But, with investment, you can improve old
infrastructure to meet demand.[54]
6.45
Even so, he queried whether the older sites have sufficient space.[55]
Williamstown in Victoria
6.46
The Victorian government noted that its state holds most of the residual
value of the considerable investment made in naval shipbuilding in Australia
over recent decades. It made the point that Williamstown has benefited from
over 100 years of public investment in its infrastructure.[56]
Indeed, the Allen Consulting Group noted:
Tenix's shipyard at Williamstown has a record in significant
surface warship construction that would be envied by many competitors around
the world.[57]
6.47
Williamstown is situated on the western shore of Port Phillip Bay and
dates back to 1865. Tenix owns the site, which they bought in 1987 from the
Commonwealth 'as a going concern to build ships'.[58]
It has 2 x 6000dwt building berths (150m length x 36.5m total width), travelling
cranes: 3 x 59t, 3 x 10t, graving dock (limited to 145m x 29.6m; gate 23.3m),
cranage of 250t capacity, transporters with capacity 400t, halls for module
construction, assembly, blast and paint and outfit, and wharfage in excess of
600m with 300m fully serviced.[59]
Mr David Miller, Executive General Manager, Tenix Defence Pty Ltd, believed
that, despite its age, Williamstown is a very modern, very clean and very
advanced shipyard. He explained that, in the mid-1990s, the shipyard had four
and five ships under consolidation simultaneously. He noted further that 'in
terms of modularity and how it fits into our infrastructure, modularity allows
us, more than anything, to simply...spread the work around so that we can have
the higher, more complex, work of the system and physical integration of the
ship ongoing'.[60]
Investment in infrastructure
6.48
The 2002 strategic plan noted that the infrastructure at Williamstown
had been developed to enable consolidation of the ANZAC frigates. It observed
that some aspects of the infrastructure could be modified 'relatively easily',
whereas others would require 'considerable investment or are effectively
permanent'.[61]
The plan reflected advice it had received that 'for future construction of
large major surface combatants such as proposed under SEA 4000, the site would
need significant redevelopment'. It stated further 'Considerable investment,
possibly including a floating dock to supplement land docking, might also be
necessary should concurrent build and/or upgrade activities be planned'.[62]
At this time, ASPI concurred that the site could be used to construct large
ship modules but that major infrastructure changes would be necessary for the
consolidation of large ships.[63]
A study, conducted by the Allen Consulting Group in 2005, before the AWD
project was awarded to ASC, found:
While much of the existing shipyard would not require
refurbishing in order to accommodate the AWDs, some facilities would need to be
upgraded or replaced. For example, the present slipways and docks are too small,
and in any case there is now a view that slipway launches are undesirable for
substantial vessels because of the strain they supposedly exert on the hull. [64]

The Tenix Williamstown 64 tonne slipway crane
6.49
The report indicated that the capital cost of the work would be
approximately $80 million and would include: a floating dock for launch;
cranes, including a heavy lift mobile crane; a construction hall; a steel
fabrication shop; panel manufacturing facilities, including a robot cutting
machine; pier demolition; and dredging.[65]
The report noted that the Victorian government had offered a support package
for the AWD project that would have provided 'funding for a share of this
upgrade cost'.[66]
6.50
According to Mr Miller, Tenix commissioned a benchmarking study of its
performance as a shipbuilder against companies through Asia, Europe and the U.S.
According to Tenix, the study indicated that Tenix is 'above the midpoint of
where many of the best yards in the worlds are in'. Although the study showed
the company's strength in planning systems and organising work, it had specific
suggestions to improve its modular assembly. Mr Miller stated:
An area where it was suggested we should go back and begin to
put in plans for improvement was the layout of our yard. So we would look at
ways to have a better flow of material coming through in the way that modules
are constructed, so that we do more work in the module phase before we begin
the large assembly of a hull. A lot of that just gets into time use management
to ensure that you get as much into that module as you can and that you get it as
densely packed as you can before you begin moving that on and assembling it as
part of the hull. Simply, it takes more labour once you get it as part of the hull—then
the workers have to begin crawling down into more confined spaces and so forth.[67]
Investment for the construction of
very large ships
6.51
Looking to the immediate future, the committee asked whether additional
significant investment would be required in Williamstown to make those yards
competitive for the modular assembly of both the AWDs and the LHDs. Mr Miller
informed the committee that a substantial upgrade would be needed if Tenix were
to take on the construction of a very large vessel such as an LHD at
Williamstown. The company, however, has other options that would accommodate
such a project, such as using its Western Australian site which is immediately
adjacent to the common user facility in Henderson. According to Mr Miller, the
common user facility in Western Australia is now part of Tenix's business plan:
that when bidding for major jobs it tends to do so through the CUF.[68]
He noted:
Over the past year we have undertaken a number of naval repairs
on Anzac frigates using that facility. We are currently converting the civilian
oil tanker Delos into an underway replenishment ship for the Australian
Navy. It is soon to be the HMAS Sirius. The availability of that
infrastructure allows us to take on major projects without the barrier to entry
that we might otherwise experience if we had to go out and capitalise all of
that ourselves.[69]
6.52
It should be noted, however, that Mr Miller did not want to imply that
because Tenix consolidates in one place, work cannot be done in other areas
such as Williamstown.[70]
Garden Island in New South Wales
6.53
The New South Wales government noted that there are two existing
facilities with the capacity 'to host work on large naval vessels'—Captain Cook
Dry Dock in Garden Island and the Cairncross shipyard in Brisbane.[71]
Mr Warwick Glenn, New South Wales Department of State and Regional Development,
told the committee that the Captain Cook Dry Dock is 'ideally positioned at the
fleet base—near naval personnel, accessible to Canberra and close to Defence
ICT systems hub of North Ryde, which offers support for electronics components
of modern ships'.[72]
6.54
Although in Commonwealth hands, the Garden Island Dockyard in Sydney is
operated under lease by ADI Ltd (now Thales, see paragraph 4.48).[73]
The yard is used mainly for repair and maintenance of major surface ships and
upgrade of the FFGs.[74]
The site has a dry dock 100 000 dwt capacity, 345 metre x 41.6 metre and a
floating dock 800 dwt capacity, 63 metre x 12.9 metre. According to the
2002 Australian naval shipbuilding strategic plan, the dry dock is the largest
in the Southern Hemisphere and capable of servicing very large ships of foreign
navies. It was of the view that the site 'as a whole would require significant
investment to convert to consolidation of vessels planned under SEA4000,
JP2048/2027 or SEA1654'.[75]
6.55
The 2002 ASPI report was of the view that, although its key capabilities
relate to the repair sector, it could be used for the construction of large
ship modules. It noted, however, that while the Captain Cook Dry Dock could be
used to assemble modules, this activity would disrupt its repair and
maintenance dockings.[76]

The Captain Cook Dry Dock at Garden Island
Investment for the construction of
large naval vessels
6.56
Mr Smith, ADI, advised the committee about the existing facilities on
the eastern sea board which have been in place for many years. In his view they
are 'fully capable right now of commencing this LHD program with only very
small infrastructure investment—and I mean really small'.[77]
He explained:
The history of Garden Island as a facility before ADI was a
privatised company is that it was a heavy engineering facility where anything
was possible. You could do any work there. That has changed for obvious
reasons. There are environmental pressures on the site. Having said that,
however, what we can do are essentially...major cutting, major refabrication
within the ship, putting in new capabilities and so forth. As I said before, if
there is some aspect of that work that is noisier, dirtier or whatever than
what is possible under our licence regime then we get that done somewhere else
and bring the finished product into the facility where we then install it in
the ship.[78]
6.57
He noted that ADI have partners in the bid for the LHDs including Forgacs,
an engineering company based in Newcastle that has facilities in Newcastle and Brisbane.[79]
He indicated that between ADI; Forgacs; the French designer-shipbuilder partner,
Amaris; and other strategic subcontractors, ADI does not envisage any
constraints in undertaking the LHD program.[80]
The Cairncross Dry Dock in Queensland
6.58
The Queensland government also believed that Australia has the existing
infrastructure needed to sustain a viable naval shipbuilding industry. It
identified two sites in Queensland that could provide the necessary
infrastructure for the proposed LHDs.
6.59
The Cairncross Dry-dock Facility is situated in a mixed
industrial-residential area on the Brisbane River and has access to the local
workforce, existing steel fabrication sites and transportation nodes. In 2002,
the Naval Shipbuilding and Repair Sector Strategic Plan noted that the site
covered 16 hectares and had a graving dock (85 000 dwt capacity, 263 metre
x 33.5 metre), a fitting out wharf of 307 metre and travelling cranes: 4 x 5 tonnes,
1 x 50 tonnes, 1 x 30 tonnes. The 2002 Strategic Plan commented on the capacity
for infrastructure expansion on this 'relatively spacious' site. It was of the
view that 'some investment would be needed to adapt it to module fabrication,
but full vessel assembly was not considered 'practical'.[81]
Investment for the construction of
large naval vessels
6.60
According to the Government of Queensland, the site is amongst the
largest in the Southern Hemisphere and could facilitate the assembly of either
of the LHD designs. It is considering developing a CUF, particularly in support
of building modules to be consolidated in the Cairncross Dock in Brisbane and
is working on the plan for the development of a common user facility with
leaseholder Viking Industries.[82]
The development would provide the necessary facilities for the complete
assembly of large ship modules up to 500 tonnes which could then be transported
six kilometres to the Cairncross Dry Dock or another shipyard in Australia.
6.61
Cairncross is highly suited to the assembly of super-blocks, such as the
forward or aft section of a large vessel and the site requires minimal upgrade
to support the project 'given the symbiotic relationship between the dry dock
and the fabrication facility (Common User Facility) immediately down river'.
The Queensland government noted that the site would be suitable for the
fabrication of modules for the AWD that would then be transported to South
Australia.[83]
Additional requirements, however, would be needed to cater fully for the
consolidation of the LHDs at this site.
6.62
Brisbane Slipways wrote to the committee drawing attention to its
facilities and suitability to be part of the naval shipbuilding projects. It
noted that it is a 2500 tonne repair facility based in Brisbane on over
30 000 square metres. It listed its existing infrastructure and concluded:
Brisbane Slipways has existing physical and staff infrastructure
to make a serious contribution to Australia's shipbuilding capabilities. We are
enthusiastic about the future and look forward to working with Government and
other industry players to develop our joint capabilities.[84]
6.63
Having looked at individual shipyards, the committee now considers the
state of Australia's shipbuilding infrastructure as a whole. It looks at the
efficiencies or inefficiencies created by the pattern of investment in
Australian shipyards.
Overall infrastructure development in Australia
6.64
Australian shipyards are not without problems. Rear Admiral (retired)
Kevin Scarce from the Port Adelaide Maritime Authority and the South Australian
government informed the committee that their analysis of data revealed 'a
fragmented industry characterised by an oversupply of dated, uneconomic and
competitive infrastructure...'[85]
The South Australian government stated that Australian shipbuilding
infrastructure has 'evolved on a project-by-project basis rather than in
response to a national plan'. It maintained that 'the myriads of facilities
that are left are old, underutilised and not cost competitive'. In its view, further
infrastructure investment beyond that already planned, can 'only add to the
underutilisation of costly assets'.[86]
Thiess also gave its assessment of the current state of infrastructure in Australia.
It found:
In past naval shipbuilding programs, most infrastructures were
built as part of the project. For instance, ASC built up the site in Osborne,
SA from a green field. ADI did the same in Newcastle for the Mine Hunter. In
most cases, the investment represented around 3% of the total value of the
project. The ultimate use of the site after the end of the program was never
fully optimized. The Newcastle site was returned to the landlord who is leasing
it to a super yacht builder from New Zealand. The site in Williamstown used to
build the ANZAC ships is probably underutilised at the present time.[87]
6.65
An Allen Consulting Group study, commissioned by Tenix, published before
the successful tender for the AWD project was announced touched on the
development of new sites while, it noted, the older sites offered a viable
option. It stated:
On the basis of the criterion of minimising capital expenditure
on set-up costs, Tenix at Williamstown is a clear winner. If the AWD project
went to Osborne (under the auspices of either Tenix or ASC), the investment
required would be at least twice that needed at Williamstown, which is a
working naval shipyard successfully building major surface combatants. Other
things being equal, since the two sites would be equally capable, this does not
stand up as an investment, irrespective of whether or not the South Australian
government would fund it. It seems unlikely that a private investor such as
Holden, for example, would scrap a successful existing facility when it
introduced its next model and build a new plant 800km away at double the cost.[88]
6.66
Mr David Miller, Tenix Defence Pty Ltd, drew attention to the legacy of
this practice of building up infrastructure to meet the needs of a specific project
resulting in the underutilisation of sites. He told the committee:
My comment would be that there may be value in having more focus
on industry policy so that we do not end up with the situation...of having
various sites all around the nation that have been developed to a certain level
and then left for the grass to grow over. Our site in Williamstown is operating
well below capacity, and I suspect that that is the situation at many sites
around Australia right now.[89]
6.67
Defence also noted the influence that specific projects have had on the
pattern of infrastructure development in Australia:
ASC was created to meet the needs of the Collins project. Tenix
grew from the Anzac ship project, which used Williamstown facilities previously
owned by government, and they created a whole new workforce to undertake the
build program. ADI created a completely new greenfield workforce for the MHC
project.[90]
6.68
Mr Kim Gillis, DMO, noted further that the Osborne facility in South
Australia is designed around the AWD program. Mr Warren King, DMO, reinforced
the view that the Osborne site is being purposely designed and built to
accommodate the AWDs.[91]
6.69
Mr Andrew Fletcher, CEO of the Port Adelaide Maritime Corporation,
wanted to make clear that the fundamental premise behind South Australia
investing in a Common User Facility at Osborne was 'to provide internationally
competitive and flexible infrastructure for users'. The additional investment
in the CUF is 'to ensure the development of world-class infrastructure that can
support multiple users (beyond that required to service the AWD program)'.[92]
6.70
The Government of Victoria surmised that fragmented single project based
decisions had given rise to a situation where there was an oversupply in the
naval shipbuilding and repair sector at the same time that Australian industry
does not have the capability to undertake the AWD and LHD projects concurrently.[93]
It observed:
It is interesting to note that, over the last 20 years, each new
major shipbuilding contract awarded by Defence has involved building up new
capability at a different shipyard.[94]
6.71
The New South Wales government also referred to what it believed could
be a better use of established facilities rather than putting in place a new
facility:
Use of existing facilities rather than the building of new
infrastructure for individual projects is clearly a better use of resources for
the taxpayer. Creating new infrastructure is likely to result in a national
overcapacity and risk the viability of both existing and new dockyards.
Equally, purchasing the amphibious ships from overseas creates risk to the
survival of infrastructure for Australia’s future needs by reducing the
critical mass of work available in Australia. An overseas purchase also
relocates to other nations rather than captures for Australia positive impacts
such as technology and skills enhancement.[95]
6.72
To a degree, major engineering centres such as the AMC, which are
intended to service more than one industry, are looking to address the problem
of underutilisation. They are designed to make more and effective use of major
infrastructure. Difficulties arise however, if the demands of the respective
sectors run out of kilter and the demand for the facilities peak
simultaneously, placing heavy demands on the facilities, which may drive prices
up.[96]
6.73
Clearly, while individual shipyards and state governments develop their
infrastructure to cater for a specific project, there is the potential for inefficiencies
and underutilisation of infrastructure. The Commonwealth government, as the
major buyer of naval ships in Australia and the custodian of taxpayer money, together
with state governments have an important role in ensuring that the pattern of
infrastructure development benefits the industry as a whole and not just particular
sites. This is especially important considering the two major naval ship
projects that are underway. The role of the Australian government in planning
and shaping Australia's shipbuilding is discussed in Part IV.
Infrastructure needs for the AWDs and LHDs
6.74
Each of the shipyards discussed in this chapter would require further
investment in infrastructure if it were to meet the requirements for the
construction of the AWDs and LHDs. The state governments, ASC, ADI and Tenix
were confident that their particular shipyard, with some infrastructure
development or use of additional sites, could accommodate the build of large
naval vessels such as the LHD. Their public optimism is understandable. The
amount of investment needed to bring Australian shipyards up to standard,
however, is unclear and their capacity to meet the demand created by an LHD build
is uncertain. For example, in assessing the overall capability for Australian
industry to meet Defence's demands with regard to the AWD program, the Allen
Consulting Group suggested in 2005 that:
No existing shipyard would be able to accommodate their [AWDs] construction
without modification. Of the three competing tenders, only Tenix at
Williamstown offers an existing shipyard that, with a significant outlay but
one that is relatively modest in terms of the overall value of the contract,
would be capable of accommodating the AWD project.[97]
6.75
On the other hand, Mr Warren King, Program Manager, AWD, said with
regard to the AWD project:
For the air warfare destroyer, both sites that came under
serious consideration—that is, Tenix at Williamstown and the Osborne
site—required very similar levels of investment in facilities to make them AWD
ready, which is probably not understood by all. There was no facility that was
ready and waiting to be used and then was not used. Of course, if there were such
a place, that might have made that particular proposal more attractive. The
fact is that both sites needed an investment, and it was not an entirely
dissimilar level of investment—and in both cases, of course, it was the state
governments which made the investment behind the companies. So I do not think
we actually had a site that was AWD ready and we ignored it. That was not the case.[98]
In summary, he advised the committee:
My team's bottom line was that they found significant capability
around Australia to do the AWD modules in a variety of formats—not just in the
shipbuilding industry, interestingly enough.[99]
6.76
He noted, however, that their underpinning concern at the moment was
'capacity'.[100]
The committee asked Defence to explain the distinction between industry
'capability' and 'capacity'. Defence uses capability to refer to industry's
'shipbuilding related skills and the necessary infrastructure to construct the
AWD modules'. On the other hand, Defence understood 'capacity' to mean 'the
measure of the available labour to carry out the work'.[101]
It explained further:
At a number of locations Australian industry has the experience
and facilities required to build AWD modules (capability). The capacity of
Australian industry to build the AWD modules depends upon the availability of
skilled people during the desired build period.[102]
Along with meeting the demands of broader Australian industry,
the potential impact of building LHD’s concurrently with AWDs will need to be
evaluated.[103]
6.77
Chapter 7 examines workforce issues in terms of Australia's capacity to
meet the demand for the construction of large naval vessels in Australia. The
following section looks in greater detail at the capability of Australian
shipyards to construct the LHD given that the AWDs are to be built in Australia.
Capacity to meet the challenges of
an AWD and LHD program
6.78
Although most witnesses agreed that Australia does have, or could
develop if required, the infrastructure needed to undertake the construction of
large naval vessels, the project to build LHDs would require additional
infrastructure. Estimates differed, however, on the amount of infrastructure
investment needed to accommodate the LHDs. Thiess concluded:
In addition to existing facilities in existing yards and at
fabrication shops across Australia, it is now clear that very limited further
investment will be necessary to build the new AWD and Amphibious ships (LHD).
That should improve the competitiveness of the build by the 3% or 4% that
previously was invested in infrastructure during earlier programs and that is
not necessary for foreign yards if the ships are built overseas.[104]
6.79
Aerospace, Industrial and Marine Technology (AIMTEL) Pty Ltd had some
reservations about the capacity of Australian shipyards to build the LHDs. It
was of the view that Australia has limited capacity to construct ships in
excess of 100 metres from existing facilities.[105]
It stated:
Australian industry is substantially behind the leading 'Large'
shipbuilding yards in Japan and Korea which benefit from massive investment in
automated process for construction of 'large' steel ships. However, Australia
still leads the productivity race in respect of Aluminium construction.[106]
6.80
Even so, it concluded that large ships could reasonably be constructed
from improved facilities at Brisbane, Sydney, Melbourne, Adelaide or Perth/Fremantle.[107]
6.81
Austal, however, was certain that Australia does not have the
infrastructure and production personnel on a scale that would enable the
construction of very large naval (or commercial) steel vessels, which are
greater than 10 000 tonnes. It noted that traditional steel shipyards have
a lot of automated equipment—'a lot of large panel lines; equipment is welded,
coated and so forth'. It stated that 'Were this capacity to be developed for a
specific naval program then its long-term sustainability would, in the absence
of significant ongoing Australian government support, rely on the ability of
industry to secure additional contracts for very large, steel vessels'.[108]
Mr Rothwell, Executive Chairman, Austal, had no doubt that large ships could
be built in Australia but added:
I have often said that, if you need a hole in the ground, you
can use a pick and shovel or you can use an excavator—and I do not think we
have an excavator, if I can use that as an analogy, in Australia; it is not
here. Moving on from that, it could be set up in Australia, but the question
is: would that be sustainable or, at least, would there be a workload for it?[109]
6.82
It should be noted that the Western Australian and South Australian
governments have clearly indicated their preparedness to invest in the lead
shipyards in their respective states as a positive indication of their
confidence in their industrial infrastructure to meet the demands of building a
large naval vessel. The Western Australian government concedes that the investment
to date, including the new floating dock, is not large enough to accommodate
amphibious support ships which could weigh some 27 000 tonnes. As noted
earlier, it has put on the public record its plan to provide the needed
infrastructure should it be required. It stated:
The...CUF floating dock is being designed so that it can be
extended to accommodate the amphibious support ships, if the Commonwealth
chooses to build the amphibious support ships in Australia and if the
shipbuilder selected for the job chooses to build or assemble them at the CUF.
The estimated cost of any such extension of the CUF floating dock is $50 million,
equivalent to about 2.5 per cent of the estimated cost of constructing the two
amphibious support ships.[110]
It has made clear, however, that if the amphibious ships do
not come to Western Australia, the government would not invest in this second stage.[111]
6.83
Mr Kim Gillis, Deputy CEO of the DMO, referred to the plans for further
investment in Western Australia. He noted a recent study undertaken by
Appledore that assessed all the independent and individual sites in the country
and their ability to build the LHDs and any upgrades or specifics.[112]
It noted the Western Australian government's two-stage plan to upgrade its
facilities at the AMC and the intention in the second stage to investment in a
second phase lift so that an LHD could be lifted out of the water.[113]
6.84
With regard to the other major sites, Mr Gillis told the committee that:
The Osborne facility in South Australia, from what I have seen
of the plans, is designed very much around the air warfare destroyer program;
it does not have the facility to lift an LHD. The original plans were that,
before ASC withdrew from the LHD program, they could have expanded into that
facility but, at this stage, the plans indicate that they cannot lift an LHD.
The Williamstown facility does not have the facilities to lift an LHD out of
the water. Garden Island in Sydney and Cairncross in Brisbane have the
facilities to dock a vessel of that size.[114]
6.85
According to Mr Gillis, the Appledore report looked not only at those particular
facilities but also a whole range of other areas, including blast, the capacity
to move large modules and infrastructure issues.[115]
6.86
In response to a direct question about whether suitable and capable
infrastructure and plant existed in Australia to accommodate the AWD and LHD
projects, Mr Gillis said with regard to the LHD:
The limiting factors are not necessarily the lifting facilities;
a whole range of other infrastructure issues are affecting the ability of any
company to build in Australia. The amount of steel that we would need to
process would require significant investment in infrastructure in respect of
blasting, painting and the ability to move these large modules. Yes, there is a
lot of work. We have had estimates from all four original tenderers in the risk
reduction and design study phase, which was a funded study that DMO undertook
with Austal, ASC, Tenix and ADI. The outcome of that was that a significant
investment was required in-country. The dollar figures varied from somewhere
between $100 million to $300 million worth of investment just in infrastructure
in-country to build the LHDs in-country.[116]
6.87
He indicated that the tenderers have been negotiating with state
governments about state government investment.[117]
6.88
There can be no doubt that if the LHDs are to be built in Australia, infrastructure
development would have to take place to supplement existing facilities which
could amount to between $100 and $300 million.
Through-life costs
6.89
The investment in infrastructure, however, does have long-term benefits
for the costs in maintaining and upgrading the vessels. Many noted that by
constructing vessels in Australia the economic costs of maintaining, repairing
and refitting large naval vessels throughout their useful lives is reduced.[118]
The savings generated by having the infrastructure available for the
maintenance of the Navy's fleet is a major consideration.
Infrastructure outside the shipyard
6.90
It is clear that the importance of adequate infrastructure extends
beyond the shipyard. The shift in production to modularisation creates demands
for improved infrastructure not only in the shipyards but, as noted above, in
areas such as steel fabrication. Modern ship construction also requires the
effective and efficient transportation of large modules from their place of
production to the assembly site.
6.91
The following section looks at the need for improved methods of
transporting large modules from their place of construction to the assembly site.
High wide load corridors
6.92
Modular construction techniques allow the bulk of steelwork fabrication
and equipment installation to be performed in controlled workshop environments,
in a number of locations simultaneously. This modular approach to shipbuilding
significantly shortens project schedules and reduces manpower requirements. The
use of modular techniques, however, also leads to an increasing need for high
wide loads up to and exceeding 200 tonnes in weight to be transported from
place of production to final assembly.[119]
Thus the move to larger modular construction creates new infrastructure demands
such as improved transport routes. Although it does not necessarily matter
where the modules are built they need to be moved to the lead shipyard. The Chamber
of Commerce and Industry, Western Australia, noted that the metropolitan areas
are growing throughout Australia but 'without thought to our ability to move
huge loads as we have moved to integration across the world'.[120]
6.93
While confident that the industrial capacity exists in Australia, Tenix
saw an urgent requirement for the Federal government and State governments 'to
seek out and implement innovative means for transporting large steel modules'.[121]
It cited the example of modules fabricated in Brisbane, Newcastle or Melbourne
for the AWD or LHD programs which may need to be transported efficiently and
economically to Osborne or Henderson for final consolidation. Referring to the
difficulty transporting modules by truck or train to the one location for consolidation,
Mr Miller of Tenix, suggested that consideration be given to heavy sealift.[122]
6.94
Noting that the growing trend toward modularisation in the shipbuilding
industry created specific infrastructure needs, the Chamber of Commerce and
Industry of Western Australia stated that:
...principal workshops in the Kwinana and the Kewdale-Welshpool
industrial areas were previously hamstrung from bidding for many large
contracts because the road network out of those areas contained power line and
road furniture obstructions preventing the outward movement of high and wide
loads.[123]
6.95
It cited the construction of very high wide load corridors in Western
Australia to accommodate the new trend toward large engineering centres.[124]
This development of high wide corridors has enabled the modules to be
transported to the site for assembly. Mr Alan Windram, AGC Industries Pty Ltd,
told the committee that with the high wide load corridor, his company can move
an 11 metre by 11 metre module of probably 200 tonnes through the arteries of Western
Australia.[125]
6.96
As noted earlier, the initial outlay in building the necessary
infrastructure for constructing a vessel will then be available for the
vessel's through-life support. Investment in infrastructure will also benefit
the larger economy, especially improvements in facilities such as the common
user facility, which is designed with other users in mind, and the nation's
transportation network.
6.97
ASC submitted that national governments are not disinterested bystanders
of national shipbuilding and repair industries, that they should have 'a strong
and enduring interest in the industry's success'.[126]
This chapter has identified a number of problems in the industry such as the
underutilisation of facilities that could be addressed by better planning.
Committee view
6.98
Over many years governments and private enterprise have invested in
infrastructure for the naval shipbuilding industry. The governments of New
South Wales, Victoria, South Australia, Queensland and Western Australia
together with ASC, ADI and Tenix were confident that Australian shipyards, with
some infrastructure development could accommodate the build of large vessels
such as the LHD. Recent studies acknowledge that infrastructure improvements
are needed to supplement existing facilities and that undoubtedly some
investment would be required. A study commissioned by DMO suggested that the cost
estimates for improvements to satisfy an LHD build range from $100 million to
$300 million.
6.99
Some lead yards are looking to their respective state government to help
fund infrastructure improvements. For example, Western Australia has committed
to further investment in its CUF should Henderson be selected as the assembly
site for the LHDs. As noted in this chapter, the government would charge for the
use of such facilities which would be reflected in the overall cost of building
the ships in Australia. The committee has no doubt that should the decision be
taken to build the LHDs in Australia, there is the commitment by state
governments and the major primes to ensure that the infrastructure needed to
support the project would be available.
6.100
This chapter picked up on a number of themes emerging from previous
chapters. One of the main themes is the important role that Defence, as the
sole purchaser of navy vessels, has on shaping the industry. The committee is
concerned about how Defence encourages or fosters local business and the
influence it exerts on the extent and nature of investment in large
infrastructure. The role of governments in planning for, and investing in, the
industry is particularly significant in light of the observations about the
fragmented state of the industry where specific projects have dictated the
infrastructure requirements for that site. Part IV of the report considers
these issues in greater depth.
6.101
Although Australia may possess the infrastructure or the potential to
develop the necessary facilities to support the Navy's shipbuilding program,
this capability alone does not mean that Australia has the wherewithal to meet
the challenge created by the AWD and LHD projects. A highly skilled workforce
is essential to sustain the industry. The following chapter considers the skill
base in Australia.
Navigation: Previous Page | Contents | Next Page