Chapter 3 - Fees paid to managing contractors
Background
3.1
In its Interim Report the committee noted that it had not received
sufficient evidence to form conclusions about the concerns arising in relation
to fees paid to managing contractors and therefore the true costs of buildings
under the Primary Schools for the 21st Century (P21) Program. The committee
therefore indicated that, in continuing its inquiry, it would further
investigate the issues surrounding managing contractors and the fees paid to
them by state and territory governments. It also indicated that it would
continue to pursue the release of accurate costings data.
Response from contractors
3.2
In June 2010 the committee wrote to over 100 builders and contractors
identifiable from public information as having some involvement in P21 program
delivery. The committee invited these building professionals to contribute to
its inquiry by providing information on the following:
- the tender/selection process undertaken for their company;
-
the fees/fee structure agreed with the state education
authorities;
- any additional fees agreed, such as a performance incentive fees;
-
protocols regarding communication with the school community;
- whether requests for detailed project costings had been received
from any schools and how these had been dealt with;
- the average costs per square metre being achieved and how these
figures related to costs listed in the current Rawlinson's Construction
Handbook/Guide; and
- reporting requirements to state education authorities.
3.3
Disappointingly, the committee received only eight responses to this
request, making comparisons difficult and conclusions almost impossible. For
the most part, submissions were supportive of the P21 program and contained
brief commentary on each of the relevant terms of reference outlined above. The
submissions indicate that:
- Contractors were usually engaged through state or territory
procurement or building infrastructure agencies, following tender selection
processes. In many cases, tenders were invited from 'prequalified' firms known
or accredited by the relevant agency.[1]
- A key distinction between jurisdictions was whether managing
contractors carried out construction themselves, or subcontracted it to another
entity. New South Wales (NSW) and Victoria were noted as jurisdictions
which employed a 'number of large construction companies' which were then
responsible for subcontracting work within a designated region of the state.[2]
The Australian Capital Territory engaged project managers who also fulfilled
the role of construction manager.[3]
It was often difficult to ascertain which submitters managed projects, which
undertook construction, and which did both.
-
Consistent with the findings in each BER Implementation Report
delivered to date, project management, design and other costs were difficult to
compare between contractors and jurisdictions because of different tender and
reporting formats. Bovis Lend Lease submitted that its total fee, including any
applicable incentive, ran between 9.76 per cent and 10.26 per cent.[4]
Another submitter, Project Coordination, listed its project management fee at
less than 3 per cent but estimated indirect costs at 9 per cent and design
costs at a further 8 per cent, suggesting that total cost could run to 20 per
cent of construction cost.[5]
The only other relevant submitter listed a 10 per cent 'fee structure'.[6]
- Savings on design costs were sometimes achieved through the use
of generic designs for school buildings.
-
Performance incentives, where they were reported upon, varied
from nil to 1.5 per cent.[7]
-
Price per square metre was disclosed in only two cases, and
ranged from $1,454 to $3,200, but were described by other submitters as being
meaningless because of the costs of different types of building depending on
their purpose.[8]
3.4
Overall, there was little to learn from the contractor's submissions,
due in equal part to their number and their content.
3.5
However, the committee is concerned that the differences in reporting
and tender formats make it difficult to compare project management, design and
other costs between contractors and jurisdictions. To ensure proper
accountability in the future, the committee believes that National Partnership
Agreements should require states and territories to report on managing
contractor fees by referring to a standardised charging structure.
3.6
The government advised in its response to the committee's Interim Report
that it had established a nationally common reporting structure with consistent
definitions in January 2011.[9]
This form is located in Appendix 3. The committee notes with approval that this
structure includes a detailed definition of 'project management fees'. To
ensure that states and territories report properly, and publicly, the committee
believes that reporting should be a mandatory clause in future National
Partnership Agreements.
Recommendation 5
The committee recommends that all future National Partnership Agreements explicitly require states and territories to report publicly, using a standardised charging structure, on fees paid to managing contractors.
3.8
The committee is of the view that if the fees paid to managing
contractors are recorded in a standardised charging structure, then Parliament
and the Australian people will be able to better assess the true costs of
building under future programs. Education authorities will also be able to
better assess value for money at the tender/selection phase.
Concerns about the collapse of building companies sub-contracted under P21 projects
3.9
The committee notes with concern the collapse of a number of building
companies who were subcontracted to deliver BER projects in NSW. Two practical
outcomes are that some workers are not being paid and some P21 projects might
not be completed. These issues were raised with the Department of Education,
Employment and Workplace Relations (DEEWR) during Additional Estimates on
24 February 2011.[10]
3.10
The Secretary for DEEWR, Ms Lisa Paul, advised that all the BER projects
affected were near completion and that the responsibility for delivering the
project (and paying the subcontractors) rested with the managing contractor. The
committee was advised that while DEEWR had a limited role to play, it was
meeting with the schools, managing contractors and the NSW Government with a
view to obtaining a satisfactory resolution.[11]
Minister Evans advised the committee:
[M]y view is that we have two priorities. One is that the
work is completed and the schools are brought to finalisation. We are very
confident, as I understand it, that that has occurred or occurring, so there is
no concern about that. I mean, things have to be followed through, but we are
confident they will occur. The second, of course, is that the blokes ought to
get their wages.[12]
3.11
No formal announcement has been made at the time of writing as to
whether any satisfactory outcome for subcontractors has been achieved.
3.12
The committee now turns to consider the sanctions available to the
Commonwealth Government in the event that P21 projects do not comply with the
BER Guidelines.
Navigation: Previous Page | Contents | Next Page