Navigation: Previous Page | Contents | Next Page
Chapter 4 - Mechanisms for improving compliance and transparency
4.1
The previous chapters have identified a number of areas for improving the
operation of the order. These were largely concerned with strengthening internal
processes and enhancing guidance and training to improve compliance.
4.2
This chapter examines a number of external mechanisms which might improve
the order's operation and strengthen parliamentary scrutiny of government
contracts. The chapter also discusses the arguments for shifting to a single reporting
mechanism for procurement contracting.
Verification of compliance
4.3
In 2003 the Senate passed a resolution which prescribed that the Senate
and its committees would not entertain any claim to withhold information on the
grounds of commercial-in-confidence, unless the claim is made by a minister and
accompanied by a statement setting out the reason for the claim including any
commercial harm which might result from disclosure. In practice, however, this
resolution is not always observed or enforced. Nor does it overcome the problem
of testing whether the reason for treating information as confidential is
appropriate.
4.4
Members of the Committee were interested in developing possible
mechanisms senators could use in response to claims of commercial confidentiality
during committee inquiries and the estimates process. Senator Murray suggested
senators could be provided with a checklist to verify the legitimacy of
commercial confidentiality claims.[1]
4.5
ANAO suggested the process chart included in DOFA's Guidance on
Confidentiality of Contractors' Commercial Information would form a
suitable guide for this purpose.[2]
A copy of this process chart is provided in Appendix 7.
4.6
ANAO also suggested that DOFA's guidance be amended, to inform
departments that should officers withhold contractual information from a
committee, senators may use the process outlined in the guidance to verify
their claims of commercial confidentiality.[3]
4.7
The Committee considers this could be a useful reference aid to assist
senators with the scrutiny of contracts during inquiries undertaken by Senate
committees and estimates hearings.
Referral to the Auditor-General
4.8
Senator Murray sought witnesses' views on another mechanism to increase
compliance with the accountability principles of the order, through the Senate
Estimates process. Senator Murray proposed that:
...where a public officer declined to give evidence on the basis
that something is commercial-in-confidence, the committee would be entitled to
automatically refer that contract to the Auditor-General for specific inclusion
in the department's next review, so it would be reported on.[4]
4.9
Witnesses for the ANAO were concerned that resource constraints may not
allow the ANAO to audit every such contract. Instead, the ANAO proposed an
alternative arrangement which it thought might be more workable:
Senators could write to the Auditor-General asking him to
examine the contract in question in the next audit of the Senate Order. While,
this may not produce an immediate answer, as the next audit may be conducted
some months after the question was asked, it might have an impact on how
witnesses consider responding to the Committee's questions.[5]
4.10
Again the ANAO suggested that DOFA's guidance be amended, to advise
departments that this course of action may be taken.
Annual reports
4.11
The Committee revisited the recommendation made in its September 2001
report regarding changes to annual reporting requirements. The recommendation
was:
The Committee recommends that annual reports of Financial
Management and Accountability Act agencies provide the following information:
- the web address of lists of
contracts of $100 000 or more;
- a report on compliance with the
Senate order;
- a report on training completed by
officers undertaking procurement functions;
- a report on the inclusion in
requests for tender and contracts of advice about public and parliamentary
accountability responsibilities; and
- a report on the agency's
compliance with mandatory reporting requirements and steps taken to improve the
integrity of its data in GaPS.[6]
4.12
The Government disagreed with this recommendation, largely on the basis
that the required information was reported elsewhere.[7]
ANAO tended to concur with the Government view, saying 'the present mechanism
for listing contracts with confidential information is a suitable one'.[8]
However, ANAO suggested that some information relevant to the order could
usefully be provided in agencies' annual reports. ANAO suggested that:
A solution might be for agencies to include a note in the annual
report referring readers to the Internet site where ... all contracts over $100
000, as required by the Senate Order, are shown.[9]
4.13
The Committee considers the ANAO suggestion a simple, easy, economic solution
which would increase the transparency of agency contracts and reporting.
Rationalising reporting regimes – a single reporting mechanism?
4.14
As mentioned in chapter 1, the Committee's preparation of this report
coincided with a DOFA proposal to overhaul reporting arrangements for
procurement contracts with the introduction of a single reporting mechanism.
The proposal has radical implications for the current reporting framework for
contracts. If it were to go ahead the single reporting mechanism, based on the
AusTender database, would supersede both the order and the existing requirement
for consultancies to be reported in annual reports. Both the order and annual
reporting requirements would be revoked.
4.15
It is necessary to understand the background to the proposal before
examining the arguments for and against its adoption.
Origin of the DOFA proposal
4.16
DOFA's proposal originated in an ANAO audit on the reporting of
expenditure for consultancies.[10]
The audit examined the three reporting regimes which cover government
procurement:
- AusTender – for reporting of contractual commitments $10 000 and
over;
- Senate order – for reporting of contracts valued at $100 000 and
over and their use of confidentiality provisions; and
- Annual reporting – for total aggregate expenditure on
consultancies for the financial year and contract details including price for
consultancies let in the reporting year valued at $10 000 or more.
4.17
For all three regimes the audit found a high incidence of
under-reporting and non-compliance. It also detected problems with data
integrity and the accuracy of the information reported. ANAO concluded that the
three regimes appeared to be working at cross-purposes. The operation of three
separate systems with different reporting requirements for different timeframes
had caused, the audit found, inconsistency, inefficiency and confusion.[11]
4.18
Mr Boyd who led the audit explained to the Committee how current
reporting arrangements militate against accurate reporting:
A lot of the difficulties we found with the accuracy and
completeness of reporting of consultancies both in the Senate order and in
annual reports were essentially around the fact that this is a separate
exercise performed at different points in time when the reporting is required.
It is not something which is in-built and part of the ongoing management of the
organisations. Therefore it is treated as being in large part an extra exercise
on top of our existing responsibilities.[12]
4.19
To remedy the problem, ANAO recommended:
...that the Department of Finance and Administration and the
Department of Prime Minister and Cabinet, in consultation with key
Parliamentary Committees, affected agencies and other relevant stakeholders,
examine options for improving the accuracy and completeness of reporting of
Government procurement, including the merits of rationalising the number of
reporting regimes.[13]
4.20
ANAO told the Committee that the key to improving the accuracy of
reporting was to use the same data agencies rely upon for their own decision
making and management. Mr Boyd explained to the Committee:
Our aim when we examined across the three regimes was to find
which data they [agencies] use and what they use it for. Human nature in these
things being what it is, if you are relying upon the data yourself for a
purpose that you find useful, you will put far more effort into actually making
that data complete and accurate so that you can rely upon it yourself in your
own decision making. In that sense the agencies do not use the Senate order for
their own management decision making. The information that is used out of the
three regimes to extend any of it is what is in GaPS-AusTender. ... Our interest
was that, if we could actually build this into their ongoing management
operations, it would presumably increase the chances of the data being complete
and accurate.[14]
4.21
The outcome of ANAO's recommendation is DOFA's proposal for a single
reporting mechanism, which is discussed below.
DOFA's proposal
4.22
DOFA's proposal to rationalise reporting for procurement contracts
involves three elements.[15]
The first is for all procurement reporting to be shifted to a single system
based on AusTender, currently the central point for all Commonwealth
procurement, which will have enhanced data, search and reporting capacity. DOFA
outlined to the Committee how it expects the new AusTender system would
operate:
The redeveloped system will provide a range of new fields that
will supply procurement information that is currently in the Senate order and in
annual reports. ... The system will improve the support that agencies get to
upload data into AusTender, and this is very important in helping them provide
high-quality information about their procurements. ... It also expands the
reporting and searching tools that are available to assist agencies and the
public to use AusTender information. This means that there will be a variety of
more comprehensive views of procurement information available that will make it
much easier for senators, for the public and for suppliers to understand the
way government is letting its contracts and that will help them to make best
use of that.
The new information that we are planning to require agencies to
put into AusTender relates to all contracts over $10,000. Agencies will be
required to supply, for all their consultancies, a justification for why the
contract is a consultancy, and this is the major field that is currently in the
annual report listing for contracts. Agencies will also have to flag any
confidentiality clauses in contracts and the reasons for those clauses.
Additionally, they will have to provide the reasons for any confidentiality in
materials obtained or generated in carrying out the contract. These are the
central elements—but not the only elements—of the Senate order.[16]
4.23
DOFA is aiming for the new AusTender system to be operating by 1 July 2007, although it concedes some larger departments and agencies (eg. Defence,
Centrelink) may take longer to implement the new system.
4.24
The second and third elements of the proposed rationalisation entail
revoking the order for contracts and discontinuing the requirement for
consultancy reporting in annual reports. DOFA contends that abolishing the
order and annual reporting requirements would not only address fragmentation
under current reporting arrangements but would also remove duplication and
reduce inefficiency.[17]
Moving to a single reporting mechanism would, it claims, streamline
arrangements.
4.25
However, in response to Committee questioning DOFA modified its position
to suggest the order might only need to be partially revoked. Since the new
AusTender system will only capture procurement contracts, DOFA indicated the
order would only need to be amended to remove that category of contract. DOFA
admitted it was feasible that the order could continue to apply to
non-procurement matters such as revenue and grant contracts.[18]
The case for a single reporting
mechanism
4.26
The potential advantages of adopting a single reporting mechanism
include:
- Streamlining reporting requirements;
- Providing a central point of reference based on the AusTender
system;
- Reducing the reporting and administrative burden on departments
and agencies;
- Increasing the transparency of procurement to cover contracts
valued at $10 000 and more;
- Improving data integrity by reducing inconsistency, providing stronger
data entry protocols[19]
and, as ANAO argued above, drawing on data used routinely in daily business and
management operations. DOFA also intends to offer training and assistance to
agencies under the new system;
- Automated checking for confidentiality provisions and the reason
for such provisions for each contract. These checks are intended to remind
staff inputting data of the need to check if a contract contains confidential
information. While agency staff could circumvent these checks, to do so would
leave an audit trail and indicate 'the agency made a conscious choice to do something
that they were warned was not in line with the policy';[20]
- Improved timeliness. According to DOFA, contract data would be
available on line in 'real time', that is, 42 days after the award of a
contract as opposed to the lag of up to six months for contracts reported under
the order and as much as eighteen months in annual reports.[21]
Changes to contracts, such as their value, would also be readily available;[22]
and
-
Enhanced search and reporting capacity with the ability for users
to tailor reports to their own needs, eg. searching across agencies or
categories of contracts and extracting groups of contracts and more detail on
individual contracts.[23]
4.27
In setting out the proposal for a single system, DOFA also pointed to
the 'significantly different environment now to that which existed during the
early development of the Senate order'.[24]
The Commonwealth procurement guidelines, referred to in chapter 2, provide
greater guidance on the importance of transparency and accountability with
procurement. DOFA also mentioned the 'large amount of goodwill amongst agencies
to comply with the spirit of the order'.[25]
4.28
ANAO supported this view, adding that the principle of limiting the use of
confidentiality clauses only to cases where a sound reason exists (and
documenting it) was embedded in government policy. ANAO also noted agencies had
invested significantly in complying with the order and there would be little
incentive for them to revert to inappropriate practices.[26]
4.29
While ANAO would not have the regular compliance role under the proposed
system which it does under the order, the auditor-general has agreed to ANAO
conducting a post-implementation audit of the single reporting system and
further audits if required.[27]
Concerns about a single reporting
mechanism
4.30
A number of factors need to be taken into account in considering a shift
to a single reporting mechanism and revoking the order, either fully or
partially.
- The proposed AusTender model has yet to be implemented and
remains untested. The history of the implementation of new information systems
suggests there is often a gap between expected capacity and the challenges and
delays which emerge in practice. DOFA noted the new system would require
changes to the information technology systems agencies use to register contracts
and the business practices they use to extract data.[28]
It also conceded larger agencies such as the Department of Defence and
Centrelink may take longer than most agencies to implement the new system.[29]
- Training of staff for the new system may take longer to show
results than DOFA expects. As discussed in chapter 3, inadequate agency
training for implementing the order has been a persistent problem. Although
support from agencies for the new system is encouraging, it should be
remembered DOFA reported to the Committee in the past that acceptance of the
order was stronger in agencies at senior levels than line areas responsible for
procurement. This may not be such an issue with the new system, since staff
would be using automated core data and not have to input data manually into a
different system as occurs currently under the order.
- The promised improvements in data integrity cannot be assumed as
given. When the Committee reported on the operation of the order in 2002 a similar
model for adopting a single system based on GaPS was mooted but it suffered
from data integrity issues.[30]
Data integrity has continued to be a challenge under the GaPS-AusTender system.
As ANAO reports have shown, problems with the accuracy and completeness of data
extend beyond the reporting framework and encompass issues ranging from
internal business processes to staff training.[31]
Despite the promised enhancements, data quality under the proposed model will
remain unknown until tested.
- The increased visibility of procurement contracts under the new
system (which will capture contracts valued at $10 000 or more as opposed to
the order's reporting of contracts valued at $100 000 or more) needs to be offset
by the potential reduction in transparency for non-procurement contracts if the
order were to be revoked fully. DOFA's discussion paper on the proposed
rationalisation noted this potential gap but was silent on how it might be
addressed.
- While DOFA appeared to accept that the order could remain in
place under the new system if it applied only to non-procurement contracts,
this would in effect create a dual reporting system: there would be one system
for procurement contracts and another for non-procurement contracts. This would
amount to a departure from the single reporting system DOFA advocates. It is
unclear whether a dual system might recreate for agencies some of the
fragmentation and confusion which the new system is intended to address.
However, it would almost certainly fragment the transparency of contract
reporting for the purpose of parliamentary and public scrutiny.
- Although the ANAO has agreed to audit the new system once its
implemented, this is not the same as the mandatory regular compliance auditing
required under the order. Those compliance audits have been instrumental in
detecting problems, providing remedies and educating and inculcating agency
staff in the principles the order embodies. Ad hoc auditing of the new system
may not carry the same weight.
4.31
The Clerk of the Senate also drew the Committee's attention to an
element missing under DOFA's proposal but which is central to the function of
the order: it would not possess the authority which is invested in the order because
it is an accountability mechanism ordered by a house of the Parliament. The
Clerk told the Committee:
...by keeping the order in place completely consistent with the
AusTender system, you signal to departments and agencies that this is a matter
in which the Senate maintains a continuing interest. It is not as though the
Senate has vacated the field, and that attaches a certain greater authority and
importance to the question of disclosure of contracts... .[32]
4.32
The Clerk also cautioned against revoking the order in favour of an
unproven new system 'until it is clearly demonstrated that the AusTender system
actually provides for public disclosure to the same extent of all the
information required by the order'.[33]
He also advised the Committee the question of reporting for non-procurement
contracts would need to be resolved before any change to current arrangements
could be accepted.
4.33
In the next section, the Committee discusses a modification to the DOFA
proposal involving the AusTender system as a reporting source for the order.
An alternative model
4.34
The Clerk recommended retaining the order, at least in the interim,
until the AusTender system is fully operational and the Senate is in a better
position to assess whether the order should be amended. He advised the enhanced
AusTender system could be used by agencies to meet the requirements of the
order as it currently stands:
As departments and agencies move into the AusTender system, they
could continue to comply with the Senate order by tabling statements, under
paragraph (1) of the order, to the effect that they have fulfilled their
obligations under the order by placing the required information in the
AusTender system. No further action by the departments and agencies would then
be required, not even the downloading of the information on the AusTender
system to a different site.[34]
4.35
Under this model, AusTender's online system would supersede departmental
and agency homepages as the source where required contract information can be
accessed. It would not lead to the duplication DOFA officials appear to be
concerned might arise if the new system were to proceed with the order still in
place. Apart from that concern, DOFA agreed that the new AusTender system and
the order's current requirements would be compatible.[35]
4.36
Once AusTender was fully operational, the Senate could then consider
amending the order to reflect the enhanced reporting capacity of the new
system, particularly in relation to the $10 000 reporting threshold.
4.37
As for the question of reporting of non-procurement contracts, the Clerk
suggested DOFA develop a system comparable to the proposed AusTender mechanism
to list those contracts. In his view this would be preferable to truncating the
order to apply only to non-procurement contracts.[36]
Committee conclusion
4.38
The alternative model of adopting AusTender as the mechanism for
reporting against the current order has the attraction of being straightforward
and in line with the thrust of DOFA's proposal for enhanced reporting under
AusTender. It would avoid the possible risks of moving immediately to an
untested system and allow time for departments and agencies to adjust to
AusTender and for any teething problems to be resolved. It would not entail any
changes to either the order or the new AusTender system, but adjustments could
be made if necessary once the new framework had been trialled successfully.
4.39
Retaining the order while a new system for reporting non-procurement
contracts is developed would also overcome the accountability gap that would
emerge under the current DOFA proposal.
4.40
Under this alternative model reporting would be rationalised and the projected
improvements would proceed, while the current transparency for procurement and
non-procurement contracts would be maintained and possibly expanded, with its accuracy
and completeness improved.
Navigation: Previous Page | Contents | Next Page
Top
|