Chapter 2 - Themes and issues

  1. Themes and issues
    1. The Committee, during the course of its inquiry, examined a number of issues as it considered how to ensure the continuing value of the MPR as a mechanism to improve the accountability and transparency of the Department of Defence’s (Defence) acquisitions. A number of matters were raised in the Auditor-General’s Independent Assurance Report, which the Committee examined in further detail. The Committee sought to understand the rationale for a growing amount of data being classified as not for publication (NFP), which was the subject of an emphasis of matter by the Auditor-General, and how transparency might be maintained in a more complex strategic environment. It also addressed the bases for the Auditor-General’s qualified conclusion: the removal of lessons learned from the project data summary sheets (PDSSs) and the applicability to the MPR of internal Defence policy changes; and the accuracy of the PDSS for the Battlefield Command System (BCS).
    2. The Committee also returned to issues that have been of interest over past MPRs, including the requirement for, and publication of, Australian Industry Capability (AIC) plans, considered a key means to grow the sovereign industrial base; the implementation and administration of a risk management system; contingency statements and management of contingency budgets, including the continuing misalignment of contingency allocation and identified risks; and the use of non-specific terminology to describe milestones that have been achieved in principle but have outstanding actions to be rectified or mitigated.
    3. More generally with regard to Defence acquisitions, the Committee was interested to understand the interface between capability and delivery managers in the context of scope creep; compliance with Commonwealth Procurement Rules; and the inclusion of military-off-the-shelf options in all procurements so as to provide a baseline for timeliness and value for money considerations.
    4. Given the importance of the MPR as a tool for accountability, the Committee, as it has done previously, considered views on how the MPR might evolve so as to fulfil its primary purpose, which as discussed in chapter 1, is to provide the Parliament and the Australian public with accessible, transparent and accurate information about the state of Defence’s major acquisitions projects while these projects are still in train.

Creeping secrecy through ‘not for publication’

2.5As it has previously, the Committee examined again the impact of the classification of data as NFP, noting the ANAO’s view NFP classifications were producing a reduced level of transparency and accountability.[1] Given the purpose of the MPR is to provide transparency and accountability to the Parliament and other stakeholders, the Committee considered whether it was sufficient for the ANAO to provide assurance on classified data, and whether this was appropriately the role of the Auditor-General.

2.6The growing classification of information as NFP was the subject of an ‘emphasis of matter’ in both the 2021–22 and 2022–23 Independent Assurance Reports. The purpose of an emphasis of matter is to draw attention to a matter where the Auditor-General is of the view awareness of the disclosure is fundamental to the reader’s understanding of the PDSSs and the Statement by the Secretary of Defence.[2]

2.7In the 2021–22 MPR, schedule information for four (19 per cent) of the 21 projects was affected by NFP classifications.[3] While this information was provided to the ANAO for review and the ANAO obtained assurance over the information, the Auditor-General noted it was the first time forecast dates and variance information were not available to users of the MPR. As a consequence, the ANAO stated that year it ‘was not in a position to publish a complete analysis of schedule performance for the suite of MPR projects, as in the past’. The extent of the NFP information was such that the ANAO judged the 2021–22 MPR provided a ’reduced level of transparency and accountability to Parliament and other stakeholders’.[4]

2.8In the 2022–23 MPR, Defence advised the ANAO it had decided certain information relating to forecast dates, capability delivery information and variance information was classified NFP and would not be included in the PDSSs for 12 of the 20 projects—or 60 per cent of the PDSSs. The affected projects account for almost 64 percent of the aggregate budget of projects contained in the MPR.[5]

2.9Specifically, eight projects in 2022–23 (three in 2021–22) did not disclose a Final Operational Capability (FOC) forecast date—affecting 40 per cent of PDSSs.[6] Final operational capability is the key milestone that forms the basis for the majority of the ANAO’s schedule analysis, including aggregate analysis of total schedule slippage across projects, average schedule slippage across projects, and in-year schedule slippage across projects.[7]

2.10The ANAO judged the extent of the NFP information meant the MPR, again, provided a ‘reduced level of transparency and accountability to Parliament and other stakeholders’.[8] While it was possible for the ANAO to provide greater aggregate performance information than previously—with the large number of projects subject to classification, it was not possible to derive NFP information for individual projects from the aggregate analysis—the MPR did not provide the same level of information on individual project performance compared to 2020–21 and previous years.[9]

2.11The ANAO stated with regard to the trend:

There has been a reduction in the level of transparency and accountability, to the Parliament and other stakeholders, over the MPR projects since the 2020–21 MPR.[10]

2.12The table below, reproduced from the report, identifies the projects and respective sections of the PDSSs affected by NFP decisions. It is reproduced in its entirety to provide an accurate picture of the classification Defence is assigning to PDSS information.

Table 2.1Project Data Summary Sheets affected by not for publication decisions

NFP in section 3.3 of PDSS
(material release/operational capability)

NFP in other sections of PDSS

AIR6000 Phase 2A/2B Joint Strike Fighter

Final Materiel Release (FMR)

Final Operational Capability (FOC)

Post-Final Operational Capability

Milestone dates and variance information

Sections 1.3, 2.1, 3.2, 5.1 and 5.2 – Information relating to capability, weapons delivery and delays of acceptance of final air vehicles

Section 4.2 – Post-Final Operational Capability details

LAND400 Phase 2 Combat Reconnaissance Vehicles

N/A

Sections 1.3, 5.1 and 5.2 – Information relating to Issue 4 and air transport dates

AIR5349 Phase 6 Advanced Growler

Initial Materiel Release (IMR)

Initial Operational Capability (IOC)

Final Materiel Release (FMR)

Final Operational Capability (FOC)

Milestone dates and variance information

Section 1.1 – Jammer type information

Section 2.3B – Information relating to weapons quantities

Section 4.2 – IMR, IOC, FMR and FOC forecast dates

AIR7000 Phase 1B MQ-4C Triton

N/A

Section 3.2 – Information relating to the delivery date for Test and Evaluation–Acceptance

Section 1.2 and 4.1 – Delays in delivery of the initial Misson Control System

AIR555 Phase 1 Peregrine

Initial Materiel Release (IMR)

Initial Operational Capability (IOC)

Final Materiel Release (FMR)

Final Operational Capability (FOC)

Milestone dates and variance information

Section 1.2 – Information relating to schedule dates

Section 3.2 – Information relating to delivery dates for test and evaluation

Section 4.2 – IMR, IOC, FMR and FOC forecast dates

LAND907 Phase 2/LAND8160 Phase 1 Heavy Armoured Capability

Initial Materiel Release (IMR)

Initial Operational Capability (IOC)

Final Materiel Release (FMR)

Final Operational Capability (FOC)

Milestone dates and variance information

Section 3.1 – Information relating to achievement of Major System/Platform Variants

Section 3.2 – Information relating to delivery dates for test and evaluation

Section 4.2 – IMR, IOC, FMR and FOC forecast dates

AIR2025 Phase 6 JORN Mid-Life Upgrade

Initial Materiel Release (IMR)

Initial Operational Capability (IOC)

Final Materiel Release (FMR)

Final Operational Capability (FOC)

Milestone dates and variance information

Section 1.2 – Schedule performance modified

Section 3.1– Information relating to delivery dates for Design Review Progress

Section 3.2 – Information relating to delays in delivery, including variance

Section 4.2 – IMR, IOC, FMR and FOC forecast dates

LAND19 Phase 7B SRGB Air Defence

Initial Materiel Release (IMR) and Initial Operational Capability (IOC) reported as ‘delayed’

Milestone dates and variance information not for publication

Section 1.2 – Scheduleperformance modified

Section 2.3B – Information relating to quantities of equipment purchased from the US government.

Section 3.2 – Information relating to delivery date for test and evaluation, delays in delivery of Fire Units, and CEA Radars

Section 4.2 – IMR and IOC forecast dates

LAND 200 Tranche 2 Battlefield Command System

Initial Materiel Release (IMR)

Initial Operational Capability (IOC)

Final Materiel Release (FMR)

Final Operational Capability (FOC)

Milestone dates and variance information

Section 3.1 – Information relating to delivery dates for design review including delivery and variance

Section 3.2 – Information relating to delivery dates for test and evaluation, and delays in delivery, including variance

Section 4.2 – IMR, IOC, FMR and FOC forecast dates

SEA1439 Phase 5B2 Collins Comms and EW

Initial Operational Capability (IOC) (Stage 1, 2 and MWES)

Final Materiel Release (Stage 1)

Milestone dates and variance information

Reasons for delays not for publication

Section 1.2 – Delays in delivery, including variance

Section 4.2 – IOC forecast date

SEA1442 Phase 4 Maritime Comms

Initial Operational Capability (IOC)

Materiel Releases (Ships 6 and 7)

Final Materiel Release (FMR)

Final Operational Capability (FOC)

Milestone dates and variance information

Section 1.2 and 2.2A – Milestone dates and variance

Section 3.2 – information relating to: delivery dates for test and evaluation; delays in delivery of ships 6, 7 and 8; and variance

Section 4.2 – IOC, FMR and FOC forecast dates

SEA1448 Phase 4B ANZAC Air Search Radar Replacement

Final Materiel Release (FMR)

Final Operational Capability (FOC)

Milestone dates and variance information

Section 1.2 – schedule performance modified in relation to FMR and FOC delays

Section 3.2 – information relating to delivery dates for test and evaluation, system integration and acceptance, and variance

Section 4.2 – FMR and FOC forecast dates

Source: ANAO, 2022-23 Major Projects Report, pages 8-11.

2.13Defence explains its NFP classifications as responsible decision making in the context of changing strategic circumstances over the past 16 years:

Defence is responsible for ensuring that the information in the MPR is suitable for unclassified publication … Defence has assessed that some details, both in respect of individual projects and in aggregate, would or could reasonably be expected to cause damage to the security, defence or international relations of the Commonwealth without sanitisation of the data.[11]

2.14Nevertheless, the Committee was told the NFP assessment was a ‘subjective assessment’:

There is no empirical data. It's on the basis of us looking at what the capability implications might be. Certain components of the information will come to light, but certain things like scope changes, inventory changes, when a capability comes online, what it can and it can't do—these become very important from an operational security perspective.[12]

2.15Defence acknowledged the amount of information on the public record changed over time. However, Defence’s reliance on a ‘geostrategic circumstances’ rationale means given the current geostrategic context the direction is towards greater secrecy not transparency. For instance, Defence stated where certain types of information were previously approved for publication, it may be decided if that information remains on the public record, ‘it could do us egregious damage in terms of our operational security’.[13] Problematically, if the information was in the public domain already it would remain public. The implication is classifying information as NFP is considered prudent.

2.16Defence stated it understood the requirement for transparency as to capabilities, delays and scope changes. However, it stated:

As you start to work your way down through the MPR, there comes an assessment as to which elements of them in the changing geostrategic circumstance would potentially confer an advantage to those who will either coerce or bring to play capabilities against us.[14]

Committee comment

2.17The Committee has previously considered the tension between the need for transparency and accountability through the MPR process and the fact there may be legitimate national security grounds upon which some information might be classified. The Committee does not dispute, as a matter of principle, that the classification of some information is reasonable. Accountability runs two ways: to the Parliament, and for the information that is put in the public domain.

2.18However, the ANAO has previously raised justified concerns about its duty to provide adequate transparency to the Parliament, and about continuing to provide assurance over information that is not published.

2.19Defence acquisitions involve the expenditure of significant sums of public money and transparency and accountability, provided through such mechanisms as the MPR, are important for fostering public confidence in the activities of government.

2.20The Committee previously recommended in Report 503 that the ANAO provides a confidential submission dealing with information required to be withheld from publication in the PDSSs due to national security considerations; and that Defence organises a confidential briefing with regard to that information.[15] The Committee awaits a response from the ANAO and Defence on this recommendation.

2.21In the interim, the Committee notes with further concern the continuing decline in transparency since 2020–21, with NFP decisions now affecting 60 percent of PDSSs for projects accounting for almost 64 per cent of the aggregate budget of projects in the MPR. The acceleration in classification, from affecting 19 per cent of PDSSs in 2021–22 to 60 percent in 2022–23, has occurred without an assurance the increased redactions are reasonable.

2.22The Committee will review with interest the 2023–24 MPR—an ongoing reduction in transparency to the extent observed between 2020–21 and 2022–23 raises fundamental questions about the value and purpose of the MPR, and legitimate questions as to how the Committee receives assurance that Defence’s redactions or judgements, which it admits are based on subjective assessments, are reasonable.

2.23Should it become necessary, the Committee may need to seek more detailed briefings on an item by item basis to satisfy its scrutiny function.

Lessons learned

2.24In its interim report to the 2020–21 and 2021–22 MPRs, Report 496, the Committee emphasised the importance of capturing centrally, lessons learned for new projects in a broader strategic context where Defence is required to accelerate its capability acquisitions processes. The Committee also noted consistent issues with lessons across previous MPRs, for instance, compliance with requirements for lessons learned logs.[16] In combination with the trend towards increasingly technical and complex acquisitions, Defence cannot successfully accelerate its acquisition process unless it has the ability to learn from past challenges.

2.25In May 2020, Defence’s Capability Acquisition and Sustainment Group (CASG), released version 2.0 of its Lessons Program Policy. Full compliance with the policy was expected by May 2021.[17] In the 2020–21 MPR, it was reported Defence was yet to fully implement a lessons learned framework and compliance monitoring process; full implementation was expected to enable projects to review and apply lessons learned to enable more consistent and improved project outcomes.[18]

2.26In February 2022, CASG released version 3.0 of its Lessons Program Policy, and in the 2021–22 MPR, the ANAO observed again that Defence was yet to fully implement the lessons learned framework and compliance monitoring process. In particular, lessons from nine projects were not available in the Defence Lessons Repository, and seven projects did not maintain a lessons learned log at all.[19]

2.27In the 2022–23 MPR, the ANAO again observed the major projects were yet to fully implement the lessons learned framework and compliance monitoring process.[20] Five projects have not established a lessons learned log or lessons collection and management plan, which is a mandatory requirement under the lessons policy.[21] The lessons collection and management plan draws on information in the Defence Lessons Repository (DLR), which is relevant for the particular project. Projects are also required to record their own observations, insights and lessons so as to support the planning of future projects.[22]

2.28Of the five projects that have not established a lessons learned log or lessons collection and management plan, three have nevertheless had lessons accepted into the DLR, suggesting there is some lessons learned process. Two projects did not maintain a lessons learned log or lessons collection management plan, or have lessons accepted into the DLR in 2022–23—the MHR90 Helicopters and Battlefield Command system.[23]

2.29The following table summarises data on lessons learned on projects in the 2022–23 MPR, across the 2021–22 and 2022–23 MPR. Of the twenty projects in the MPR, none of the lessons have been categorized as applicable to the ‘whole-of-defence’ in the 2022–23 MPR.

Table 2.22022–23 MPR Projects Lessons Learned - 2021–22 MPR and 2022–23 MPR

Project 
(2nd pass approval) 
[slippage - months]

 Established Log/Plan

 Accepted into CASG/DLR 

 Lessons in PDSS* 

Lessons
Captured
#
(*)

21-22

22-23

21-22

22-23

21-22

22-23

Joint Strike Fighter (Nov 09; Apr 14) [NFP][24]

Yes

Yes

No

Yes

8

3

8(0)

MHR90 Helicopters (Aug 04; Apr 06) [110]

No

No

No

No

4

3

4 (0)

Hunter Class Frigate (Jun 18) [N/A]

Yes

Yes

No

No

3

3

5 (0)

Combat Recon Vehicle (Mar18) [0]

Yes

Yes

Yes

No

8

3

8(0)

Offshore Patrol Vessel (Nov07) [0]

No

Yes

No

No

0

3

15(0)

Overlander Medium/Heavy (Phase 3B: Jul 13) [36]

Yes

Yes

Yes

No

17

3

17(0)

Advanced Growler (Dec 16; Dec 22) [0]

-

DLR

-

No

-

3

3 (0)

MQ-4C Triton (Tranche 1: Jun 18) [66]

No

No

No

Yes

0

3

3 (0)

Peregrine (Sep 17) [NFP][25]

Yes

Yes

No

Yes

4

3

4 (0)

Heavy Armoured Capability (Dec 21) [NFP]

-

Yes

-

No

-

1

(0)

Hawkei (Aug 15) [12]

Yes

DLR

Yes

No

6

3

6 (0)

JORN Mid-Life Upgrade (Dec 17) [NFP][26]

Yes

DLR

Yes

No

6

3

6 (0)

SRGB Air Defence (Feb 19) [0]

No

No

Yes

Yes

4

2

(0)

CMATS (Dec 14) [57]

Yes

DLR

Yes

No

6

3

(0)

Battlefield Command System (Sept 17) [NFP][27]

No

No

Yes

No

4

3

(0)

Battle Comm. Sys. (Land) 2B (May 15) [36]

No

No

Yes

No

3

3

3 (0)

Collins Comms and EW (June 15; Mar 17) [30]

Yes

Yes

Yes

No

7

3

(0)

Pacific Patrol Boat Repl (Apr16) [12]

Yes

Yes

No

No

4

3

(0)

Maritime Comms (Jul 13) [NFP][28]

Yes

Yes

Yes

No

10

3

10 (0)

ANZAC Air Search Radar Repl (Jun 17) [(1)][29]

No

Yes

No

No

5

3

5 (0)

# Number of lessons captured taken from statement in 2022-23 PDSSs. (*) Lessons categorized as whole-of-defence lessons learned. Source: ANAO, 2022–23 MPR, p. 44, and project PDSSs; ANAO, 2021–22 MPR, p. 40, and project PDSSs.

Removal of lessons learned from PDSSs

Defence policy approach

2.30The Guidelines require Defence to describe project lessons (at the strategic or systemic level) that have been learned.[30] Rather than dealing with each lesson individually, lessons are grouped under systemic category headings. These categories were intended to reflect the strategies adopted at the enterprise level to address organisational level lessons, and in the early years of the MPR many of the lessons identified were generic across projects and had enterprise-wide applicability.[31] There are presently seven categories of systemic lessons: requirements management; first of type equipment; off-the-shelf equipment; contract management; schedule management; resourcing; and governance.[32]

2.31In the 2022–23 MPR, Defence reassessed its approach to reporting on lessons learned in its PDSSs and made the unilateral decision to remove content previously reported in the PDSSs on the grounds no project identified ‘”systemic” or “strategic” “lessons learned”, as defined by the [Defence 2022 CASG Lessons Policy] policy’.[33] In the MPR, 18 projects identify three key project-level lessons; one project identifies two lessons; and one project identifies one lesson. These lessons are said to have ‘potential “systemic” or “strategic” relevance’, have been entered in the DLR, and will be formally assessed to be validated as ‘lessons learned’, though the timeframe for this is not specified.[34]

2.32The PDSS for each project, at the lessons learned section, now provides a statement that specifies a number of lessons that have been captured for each project (which may not be the total number of lessons captured) and Defence’s approach to lessons learned. The following example is taken from the Battlefield Command System, which with only minor variations, is the same for the other major projects in the report:

In line with Defence Instructions and CASG Lessons policy, the project conducts scheduled reviews of its captured lessons information (including any observations, insights and/or lessons identified) as well as lessons Information contained within the Defence Lessons Repository. The project has captured four lessons related to Commercial and Schedule Management. Three project lessons are provided below (note this does not include all project lessons) …[35]

Three lessons are then published—two identified as ‘commercial’ and one as ‘schedule management’. One of the ‘commercial’ lessons appears to be an evolution from a previously published ‘resourcing’ lesson; the other two lessons do not appear to have been published since LAND 200 entered the MPR.[36] Though the statement identifies that four lessons have been captured related to commercial and schedule management, since the 2019–20 MPR, six lessons with regard to the Battlefield Command System have been published encompassing resourcing, schedule management, contract management, and commercial.[37]

2.33The basis for the lesson count in the PDSS is not clear. In addition to the situation noted above for the Battlefield Command System, the Joint Strike Fighter PDSS specifies eight lessons have been captured; since 2019–20, nine have been published in the MPRs.[38] It is also not clear why 18 of the major projects coincidentally have only three potential systemic or strategic lessons.

2.34Defence made several statements to the ANAO explaining its internal policy change and how it applied this to the MPR Guidelines, including:

  • Many of the lessons previously included in PDSSs were at a project level and would not be considered strategic lessons of the sort that must be captured under Defence’s revised policy.
  • For a ‘lesson’ to be considered a strategic/systemic lesson learned, Defence policy requires that it undergoes a lessons assessment and review process.
  • Defence considered that under its lessons assessment and review process, none of the 20 major projects had ‘learned’ any strategic/systemic lessons.
  • Defence removed all but three previously reported lessons from its PDSSs.[39]
    1. It is worth reiterating the ANAO’s observation, noted above, that the major projects are yet to fully implement the lessons learned framework and compliance monitoring process.[40]
    2. Defence told the Committee it was not seeking to reduce transparency by reducing the number of lessons contained in the PDSSs:

I think the approach is to make sure that, in aggregate, as we're looking at these projects, we are talking about strategic and systemic issues rather than what might be captured at a low project level. So, by default, when you start to aggregate a lot of those lessons learnt within individual project activity, there is a degree to which, if you try to capture all of those, they can be quite repetitive and not necessarily joined at the hip. What we're doing through our change in policy in the early 2022 time frame is trying to make sure that we are bringing those to that strategic level and looking at systemic issues, which often requires an interpretation.[41]

2.37Defence suggested it was ‘trying to focus the reader and provide a better understanding of what those systemic issues are that we’re confronting and how we’re going after and resolving those across all of our projects’.[42] This explanation, in and of itself, is difficult to understand, given Defence maintains there were no validated strategic/systemic lessons learned through any of the 20 major projects in the 2022–23 MPR.

2.38Some lessons that have been removed from the MPR would potentially seem to have broader systemic and strategic applicability. For instance, the following lessons, published in the 2021–22 MPR, were removed from the 2022–23 MPR:

  • Battlefield Command System

The integration of complex ICT systems onto platforms, especially complex, developmental platforms, should not be the responsibility of the ICT acquisition project. This is because coordination and alignment of outcomes between both complex projects becomes increasingly difficult and unmanageable. Instead, the scope of the ICT acquisition project should be limited to delivery of the ICT mission system (hardware and software) to the platform acquisition project. The platform acquisition project should then assume responsibility for integrating the ICT mission system onto the platform.[43]

  • Hawkei

First-of-type projects contain significant levels of complexity and require substantial effort to fulfil the right balance of technical, performance, risk, cost and schedule requirements. Appropriate investment is required by projects and the contractor from the outset to ensure such requirements are not over-optimistically represented or underestimated.

Projects operating in a developmental environment are to pay greater attention to workforce management and project governance. The project is also to frequently assess contractor resources, capabilities and capacity in the lead up and during project delivery.[44]

  • Joint Strike Fighter

Having a dedicated ICT SME team (CIOG) embedded within the Project Office was a significant contributor to reducing ICT risks.[45]

2.39Some lessons that remain in the PDSSs are:

  • Hunter Class Frigate

A Lessons and Opportunities Framework finalised and agreed to ensure lessons learnt are more robustly captured, assessed and where relevant encapsulated within processes, plans and procedures.[46]

  • JORN Mid-Life Upgrade

Maintaining collaboration, transparent communication and disciplined engagement with all stakeholders is critical for managing technical requirements and effective risk management.[47]

  • Battlespace Communications System Phase 2B

Collaborative engagement by the Contractor, CASG and the Capability Manager has resulted in better outcomes for the delivered capability.[48]

  • Pacific Patrol Boat Replacement

Work with Contractor to ensure the broader implications of key milestone delay and quality issues are understood and encourage early advice on delay.[49]

Committee comment

2.40With regard to the omitted lessons, the Committee notes that in effect Defence has changed its own policy for determining lessons and applied this to the MPR, in the place of the requirements set out in the Guidelines. The basis for the classification of lessons as potentially strategic/systemic and thus contained in the MPR, and not strategic/systemic and thus omitted, is not readily evident.

2.41The result, in the Committee’s judgement, has been that strategic/systemic lessons that hold important insights for Defence are now missing from the MPR, and the action has not met Defence’s intention to ‘focus the reader’ by providing a better understanding of systemic issues. It would be expected that strategic and systemic lessons would in fact be derived from project-level lessons.

2.42A change in Defence policy does not override the requirements of the MPR Guidelines. While the Committee is always mindful not to require Defence to undertake tasks that ultimately offer no value, it is the case that Defence projects are required to establish and maintain a lessons learned log and lessons collection and management plan, with the ultimate aim of improving project outcomes.

2.43Defence should reinstate the lessons learned to the MPR, as required by the Guidelines, and the Committee recommends accordingly. However, should Defence or the ANAO propose an amendment to the Guidelines that would meet the intent of this part of the Guidelines—that Defence projects should review and apply lessons learned to enable more consistent and improved project outcomes—the Committee would consider it with interest.

Recommendation 1

2.44The Committee recommends that the Australian National Audit Office and Department of Defence put forward amendments to the Major Projects Report Guidelines that ensure lessons are reinstated to the PDSSs and clarity is provided on the nature and scope of lessons to be included so the intent of this section of the Guidelines is fulfilled.

2.45Since the 2019–20 MPR, the ANAO has noted that Defence has yet to fully implement a lessons learned framework and compliance monitoring process. While Defence has issued new versions of its policy, compliance remains patchy. Projects that arguably could provide some systemic or strategic lessons, such as the Battlefield Command System, are identified as not having a lessons learned log or lessons collection and management plan. It is notable the MHR90 helicopter project did not have a lessons learned log or lessons collection and management plan. This is plainly unacceptable. Without full implementation of the lessons learned framework, the achievement of more consistent and improved project outcomes is at risk. The Committee will monitor this issue with interest in future MPRs.

PDSS accuracy—Battlefield Command System

Background

2.46As discussed in chapter 1, the accuracy of the PDSS for the Battlefield Command System (LAND 200 Tranche 2) was one of the bases for the Auditor-General’s qualified conclusion. For the ANAO, between 2021–22 and 2022–23,

… despite evidence that there had been a reduction in material capability and scope delivery … notwithstanding various commercial arrangements that had occurred through the year, there continued to be a fairly high level of confidence around delivery.[50]

2.47Defence referenced incremental improvements to capability and stated the assessment should remain the same as it had been previously.[51] The ANAO and Defence appear to have fundamentally different interpretations of the trajectory of capability and scope delivery.

2.48The LAND 200 project has, over many years, experienced delays and scope reductions but remains envisioned as a project to transform command and control of land forces.[52] It was the subject of an ANAO performance audit in 2019.

2019 ANAO performance audit

2.49LAND 200, comprising three tranches, is intended to transition the Army’s command and control from a paper-based system to a digital system to provide real-time situational awareness, combat planning tools and complex combat messaging. In 2017, LAND 200 was described by the Chief of Army as the ‘highest-priority project in the Army’.[53]

2.50LAND 200 has replaced an existing system, the Battlefield Command Support System, which was an incremental redevelopment between 1999 and 2014 of the earlier AUSTACCS, which had been delivered between 1982 and 1998. The Battlefield Command Support System was, according to the ANAO, ‘recognised as being significantly limited in its networking and data distribution capability’.[54]

2.51The capability being acquired through LAND 200 comprises two major systems:

  • Battle Management System (BMS)—electronic displays of maps of combat data
  • Tactical Communications Network (TCN)—secure mobile infrastructure (such as radios) to support the data and voice distribution of the BMS and other combat systems.[55]
    1. Details of the schedule include:
  • Tranche 1 achieved FOC in 2015, two years behind schedule[56]
  • first pass approval for Tranche 2 was obtained in August 2013, with second pass (work packages B-D) scheduled for September 2015 and FOC expected December 2018[57]
  • second pass approval was obtained in September 2017, with FOC initially expected in mid-2022; it remains to be achieved[58]
  • first pass approval was given for Tranche 3 in July 2023.[59]
    1. For several years until February 2017, Tranche 2 was managed by two Defence project offices who undertook their own definition and refinement processes prior to tender, despite a need to align the requirements for the interconnected projects:
  • LAND75 Phase 4—upgrade of the Battle Management System[60] and installation into further vehicle fleets
  • September 2015: sole-source request for tender to Elbit released
  • November 2016: Elbit tender found to represent value for money, following quantity reductions and other requirements adjustments
  • JP2072 Phase 3—Tactical Communications Network
  • April 2015: open request for tender released, one tender received from Harris
  • September 2016: Harris tender found to represent value for money, but unaffordable, despite significant reductions in scope.[61]
    1. A May 2016 Gate Review found, amongst other things, the project had a moving scope and approach, an inadequate budget, and an unworkable schedule. The total tendered price was over $1.5 billion, more than $720 million over Defence’s budget. There was also a lack of timely, technical expert advice on emerging technologies. The tender outcomes reflected a lack of alignment between the two projects, and there had been a lack of project management diligence. Further, the Army had moved its preference for the central capability for land platforms from the BMS on which the LAND75 request for tender was based, to an open architecture option, which it recognised as ‘currently unaffordable’.[62]
    2. At second pass (work packages B–D) on 12 September 2017, the Government approved:
  • expansion of the Battle Management System into Brigade and Joint Task Force Headquarters
  • introduction of the Battle Management System into four additional vehicle fleets: M1A1 tank, M88 recovery vehicles, Hawkei, and medium-heavy trucks
  • introduction of Battle Management System training and simulation facilities across Australia
  • software development to assist in managing the network and to support the exchange of data.[63]
    1. In September 2017, Defence identified the technical risk of Tranche 2 as ‘high’ and the overall risk as ‘medium-high’ consequent of ‘the complexity of the system; the lack of a clear and robust design for some network elements; and the technical challenges involved'.[64] Contracts with Elbit and Harris for Tranche 2 were signed on 26 September 2017.[65]
    2. In 2019, the ANAO audited the LAND 200 Tranche 2 program and concluded Defence had not conducted a fully effective acquisition process for LAND 200 Tranche 2 work packages B–D, but could achieve value for money if the contracted quality and quantity of goods and services were delivered according to the agreed scheduled and successfully integrated by Defence.[66]
    3. The ANAO also found, amongst other things:
  • Defence did not conduct an effective requirements definition process—the two project offices developed different conceptions of the capability and requirements were not aligned prior to the release of requests for tender
  • the 2015 procurement of the TCN was not effective, requiring a lengthy post-tender refinement process to bring the project within budget
  • the 2015 sole-source procurement for the BMS was ultimately effective, following significant refinement and scope reductions, though cost and risk ratings were adjusted to be more positive in successive tender evaluation reports with no reasons documented
  • Defence addressed affordability issues through project rationalisation and by adopting a ‘design to price’ strategy, significantly reducing project scope, and assuming additional risk and cost by taking on the role of Prime Systems Integrator
  • fully effective project governance arrangements were not established
  • Defence established an appropriate project review framework, though did not act on some of the advice provided for several years
  • effective contracting arrangements to monitor and manage the performance of the contractors were established.[67]
    1. The ANAO found the ‘difficulties encountered’ in LAND 200 Tranche 2 stemmed in large measure from one project office (TCN) releasing a request for tender with a scope that exceeded the approved cost and did not fully assess the budget consequences or governance coordination arrangements at a program level. The desired outcome had shifted from the simple procurement of radios to the procurement of a complex digital communications solution, at a time when Defence had not determined how it would operate in a digital environment. The ANAO found there was no documented government approval for the shift in scope from radios (approved at First Pass in 2013) to a complete, new network solution contained in the request for tender.[68]
    2. Internally, Defence’s approach to resolving the unaffordability impasse for both tender processes—which involved bringing the two tenderers together and seeking a ‘design to price’ solution—was described as ‘unique’, ‘unusual’, and ‘atypical’.[69]
    3. Defence concluded both tenders after accepting a significantly reduced project scope, and additional risk (and cost) by assuming the role of Prime Systems Integrator (neither tenderer could absorb this role within the affordability constraints). In September 2018, an Independent Assurance Review found the most significant challenge facing LAND 200 Tranche 2 was ‘Defence’s ability to effectively discharge its responsibilities as the Prime Systems Integrator’ and it did not support the project teams’ confidence the projects could be delivered as planned. In December 2018, Defence acknowledged it had limited resources to run the integration aspect of LAND 200, in its role as Prime Systems Integrator.[70]
    4. Because funding was insufficient, the cost for integrating the LAND 200 Tranche 2 capability into vehicles (tanks, recovery vehicles, some Bushmasters, Hawkeis) was removed from the 2017 acquisition contracts, in the expectation the contracts would be amended later for this purpose. Defence did not advise the Government at Second Pass in 2017 of this scope reduction and subsequently drew on project contingency funds to reinstate the scope.[71]
    5. Due to unaffordability, scope was moved from Tranche 2 to Tranche 3, without additional funding. An internal review of Tranche 3 (which commenced in 2017 and achieved First Pass approval in 2023) stated Tranche 1 and Tranche 2 ‘delivered well below expectations both in terms of capability and Basis of Provisioning’ [reductions in the amount of equipment acquired].[72]
    6. When speaking to the Committee during the inquiry, Defence stated, ‘We talked about LAND 200 phase 2. If you look at other failed projects, they've often failed in the first two steps, which meant they failed to achieve requirement certainty and failed to achieve or tailor the right approach to the outcome’.[73]

Subsequent amendments to LAND 200

2.65Subsequent to the ANAO report, Defence told the Committee that while LAND 200 Tranche 2 was to deliver tactical communications networks and a battle management system, it had removed the battle management system scope from LAND 200 Tranche 2 ‘a couple of years ago’ and,

… installed an interim battle management system and we capped, in the force, where that battle management system would be used down to. We then transferred the responsibility to deliver the battle management system, which will equip the full force. Initially it was transferred to LAND 200 phase 3 as part of the National Defence Strategy and the integrated investment plan. We recast that scope from LAND 200 phase 3, and the remaining scope of LAND 200 phase 2 was transferred into LAND4140, which is going to be considered by government in the near future.[74]

2.66Defence confirmed it would progress a permanent battle management system solution through LAND4140, the LAND C4 (command and control communications capability) program.[75]

2.67As to the tactical communications network, Defence stated commercial negotiations were ongoing but L3Harris had not been able to deliver a viable digital wave form and this would be removed from the scope, along with other networking elements.[76]

2.68Defence told the Committee the only component of the land force it would not fit out under LAND 200 Tranche 2 was the Hawkei protected mobility vehicles:

… we believe we have enough time and finances in the LAND 200 project to equip probably about half the Hawkei fleet from LAND 200 Tranche 2, and that's with the radios. The remainder of the fleet will look to either equip through sustainment or through LAND4140.[77]

2022–23 MPR and concerns with accuracy of the PDSS

2.69The ANAO’s concern about the accuracy of the PDSS for the Battlefield Command System was that between 2021–22 and 2022–23, the disclosed degree of confidence the capability would be met did not change, despite evidence there had been a reduction in materiel capability and scope delivery.[78]

2.70In the MPR, Defence acknowledged the Auditor-General’s opinion regarding the degree of confidence materiel capability would be met for the Battlefield Command System.[79] However, it considered ‘the forecast scope for LAND 200 as at 30 June 2023 to be essentially the same as the previous years’.[80]

2.71Defence stated:

In 2023, the project closed the BMS contract through a commercial agreement between Elbit Systems Limited and the Commonwealth, leaving the L3Harris Technologies TCN element as the remaining component of the BCS to be delivered.

… the Commonwealth continues to work with L3Harris Technologies relating to the inability to achieve contracted milestones affecting the schedule for TCN Systems Acceptance.

The effect of these actions in the BMS and TCN components of the BCS has meant that during the MPR process, only incremental improvements to capability have been achieved, leaving the current overall capability and scope assessment essentially the same as that in last year’s report.

In relation to remaining open commercial issues, Defence remain in negotiation with L3Harris Technologies to reach a solution for the TCN delay. Once this delay is resolved, an overall assessment of the BCS capability delivered and the Capability Manager’s requirements will be able to be undertaken.[81]

2.72The basis for the ANAO assessment was that Defence’s confidence in the achievement of materiel capability had not changed despite evidence of a reduction in material capability and scope delivery. Defence countered by arguing because there had been only incremental improvements to capability, the overall capability and scope assessment remained essentially the same.[82]

2.73Changes in the PDSSs between 2021-22 and 2022-23, show in 2022-23:

  • Battle management system: The scope was reduced in March 2023, and a version of the software (R1.1) was accepted,[83] which in the 2021–22 MPR had issues sufficiently significant to prevent it exiting the Software Release Review milestone.[84]

Following a demonstration in March/April 2022 of R1.1, Defence and Elbit were unable to agree issues of concern had been remediated such that ‘R1.1 was not achieved as at June 2022’.[85]

Defence subsequently agreed to accept nine configurations of the BMS R1.1 software in the state it existed on 30 June 2022, ‘with the remaining scope removed’.[86]

  • Tactical communications network: in April 2022 the contract was subject to a Stop Payment Notice (due to an inability to achieve system acceptance), in the 2022–23 MPR it was subject to a Default Notice.[87]

Defence did not approve L3Harris remediation planning and both parties ‘continue to engage constructively to ensure that there is a clear understanding of open matters between them’.[88]

2.74The LAND 200 Tranche 2 scope, according the PDSS, was focused on further development of the battle management system that had commenced under LAND75. The 2022-23 PDSS states, ‘the Elbit Systems of Australia scope component of the project has been reduced by agreement …’[89]

2.75During a public hearing, Defence stated further scope would be removed from the TCN contract:

There are currently commercial negotiations to close down that arrangement with L3Harris and for them to deliver the elements of scope that they have been contracted to deliver. One of those elements was a digital wave form. That wave form couldn't be delivered and wasn't viable. So that's going to be removed from scope as well as some other networking elements.[90]

2.76Defence admitted it had not articulated the impact of issues in the LAND 200 Tranche2 project across other projects that would rely on the implementation of the LAND 200 Tranche 2 capabilities. It stated, ‘we will take that on notice and ensure that, when we update for the next MPR, that impact across those other programs is clear’.[91]

2.77LAND400 is reliant on the delivery of LAND 200 Tranche 2 capabilities,[92] which as noted above have been descoped. In a supplementary submission it stated:

LAND 400 has adopted the current Tactical Communications Network baseline as well as a temporary Battle Management System to support platform development along its project schedule. This mitigates potential impacts to LAND400.[93]

2.78Defence stated delivery of a mature battle management systems and tactical communications networks would now be undertaken by LAND4140, which is ‘adopting a continuous delivery approach’, and is expected from 2026.[94]

Committee comment

2.79In general, with regard to the LAND 200 Tranche 2 project, the Committee notes evidence from Defence that LAND 200 Tranche 2 and other failed projects failed because they did not achieve ‘requirement certainty’ or ‘tailor the right approach to the outcome’. The Committee surmises that what Defence means by this is Defence had not finalised its requirements prior to going to tender, and did not apply appropriate expertise to manage the project to its successful conclusion.

2.80It is notable a Defence internal review described LAND 200 Tranche 1 and Tranche 2 as having delivered well below expectations in terms of capability and the actual amount of equipment that was acquired. Defence stated it transferred responsibility to deliver the battlefield management system, which will equip the full force, to other projects. The PDSS makes clear the battle management system was descoped and the tactical communications network was descoped.

2.81With regard to the Auditor-General’s independent assurance review and qualified conclusion, the Committee received no evidence that would lead it to question the Auditor-General’s conclusion that the identified sections of the PDSS ‘are materially inconsistent with evidence obtained during the course of the review’.[95]

2.82Project data summary sheets must accurately convey the information required by the Guidelines. The Committee will examine with interest, the status of this project in future MPRs.

Australian industry capability

2.83The AIC Program is intended to, amongst other things, provide opportunities for Australian companies to compete for Defence work, facilitate technology transfer and access to intellectual property rights, and encourage investment in Australian industry.[96]

2.84Tenderers for material and non-material procurements valued at or above $4 million (or $7.5 million for construction services), are required to demonstrate appropriate formal consideration of Australian industry capability through a schedule or plan in their tender response—with a version for public release. The exact requirements are determined by the size and the nature of the procurement. Government-to-Government procurements, including Foreign Military Sales and Direct Commercial Sales, are not exempt from AIC Program requirements.[97]

2.85The MPR Guidelines require the reporting on whether there is an AIC plan for disclosed major contracts, and a short description of the key elements of the plan. If there is no AIC plan relevant to the disclosed major contracts, this is to be disclosed, along with the reason.[98]

2.86The ANAO found three major projects did not have AIC plans in place—Joint Strike Fighter, Peregrine, and MQ-4C Triton. Defence stated these were collaborative programs with other countries, foreign military sales, or involved sole source procurement.[99] As noted above, Government-to-Government procurements, including Foreign Military Sales, and Direct Commercial Sales, are not exempt from the AIC Program requirements.[100]

2.87The ANAO also found several major projects where public AIC plans had not been published (when required) for at least one eligible contractor: Hunter Class Frigates; Combat Reconnaissance Vehicles; Advanced Growler; and Battlefield Command System.[101]

Committee comment

2.88Australian industry has been recognised as a fundamental input to capability, and more recently, Defence has identified the need for a number of sovereign industrial capabilities.[102]

2.89Having an industrial base that can effectively support Australia’s national security is crucial. The AIC requirements, which aim to ensure the consideration and inclusion of Australian industry capability in Defence acquisitions, are an important mechanism for building Australian industry, particularly by facilitating technology transfer and access to intellectual property, and encouraging investment. Publication of the AIC plans, where required, is an important transparency mechanism. The Committee has an expectation that where required, AIC plans will be in place and versions made available publicly.

2.90Foreign Military Sales and Direct Commercial Sales are not exempt from the AIC Program and the Committee will monitor this issue in future MPRs.

Implementation of a risk management system

2.91Risk management has been a long-running focus of the MPR, with the Committee recommending in 2018 the transitioning from spreadsheets to risk registers with more robust version control.[103] The ANAO has observed the use of spreadsheets as a primary form of record for risk management is itself a high-risk approach, particularly as spreadsheets lack formalised change/version control and reporting.[104] In May 2020, Defence advised it would mandate Predict! as its risk management system.[105]

2.92Though major risks and issues data is excluded from the formal scope of the Auditor-General’s assurance report because Defence systems are unable to provide complete and/or accurate evidence in a sufficiently timely manner, in forming the Auditor-General’s conclusion, the ANAO is required to consider material inconsistencies identified.[106]

2.93Of the 20 projects in the MPR, Predict! is in use in 19. In two of those 19, other risk management systems are also in use, CapabilityOne (Hunter Class Frigates) and MSSharePoint (CMATS). In one project, the MHR90 Helicopters, the primary risk management system remains MS Excel.[107]

2.94Notwithstanding the adoption of a risk management system, in its examination of project offers’ risk and issue logs at the Group and Service level, the ANAO found a number of risk management issues. These included:

  • variable compliance with corporate guidance—only six projects had reviewed or updated their risk management plan within six months, as required
  • visibility of risks and issues when a project is transitioning to sustainment
  • frequency with which risks and issues logs are reviewed to ensure accuracy and completeness, management in a timely manner, and accurate reporting to senior management
  • lack of quality control resulting in inconsistent approaches in recording of issues
  • lack of a clear link between allocations against risk in the contingency log and risk log
  • risk management logs and supporting documentation of variably quality.[108]
    1. Further, the ANAO found some controls within Predict! were not operating effectively, which increased the risk data generated from Predict! and information derived from that data, may not be reliable. The ANAO found the following control weaknesses in Predict!:
  • lack of segregation of duties between capturing and approving data in Predict! as well as capturing, and approving, any changes to risk identifiers or fields that determine the risk rating
  • no logging or reviewing high-risk user actions on application level and no controls in place to ensure that logs, or log descriptions, cannot be changed by users being logged
  • no identification of privileged user accounts, including ensuring that only those who require privileged access are assigned those roles, and no regular monitoring controls over the actions performed by privileged users
  • no regular process for the revalidation of user access to Predict! including privileged user access.[109]
    1. For the projects in the MPR, the ANAO found instances where risks and issues information in Predict! had not been updated in a timely manner, and instances where it was not a complete and accurate record of the current mitigations or ratings. The ANAO did not rely solely on Predict! to gain assurance over the risks and issues disclosures within the PDSSs.[110] The ANAO stated that while progress had been made, ‘there’s still disorder in the system’.[111]
    2. During the inquiry, Defence acknowledged a lack of capacity in its workforce:

One vexing problem is associated with the professionalisation of our project management workforce. That is an issue for us … Professionalisation of our project management, our procurement and commercial, our engineering and our logistics teams is critical moving forward. We have let some of that lapse, and that's one of my primary focuses—building that skill set through professionalisation and through making sure our internal processes and policies are implemented.[112]

Committee comment

2.98The Committee has been following Defence’s attempts to improve its risk management since the beginning of the MPR. It notes with satisfaction that in 2022–23, 19 of the 20 projects in the MPR are now using Defence’s risk management system, Predict! However, there remain shortcomings, as identified by the ANAO, in the use of that system.

2.99In particular, the Committee notes the lack of quality control that results in inconsistent approaches to the recording of issues; the lack of a clear link between allocations against risk in the contingency log and risk log; and the variable quality of documentation that supports risk management logs.

2.100It goes without saying the value of a robust risk management system can be undercut by the quality of the information in that system. The Committee will continue to monitor this issue.

Contingency statements and management

2.101The total approved budget for a project comprises the allocated budget and the contingency budget. The allocated budget covers the project’s approved activities. The contingency budget is set aside for the eventuality of risks occurring, including the need for unforeseen work that arises within the delivery of the planned scope of work.[113]

2.102The intent of contingency funding is to provide for cost, schedule and technical uncertainties that may arise over the life of a project. The use of funding from the contingency budget is dependent on the occurrence of a contingency risk—contingency funding cannot be used to pay for activities that increase the scope or capability of a project. Project managers are required to maintain a project contingency log to support control of the project contingency and facilitate reporting on its use.[114]

2.103The PDSSs in the MPR are required to include a statement regarding the application of contingency funds during the year, and where applicable, a disclosure of the risks mitigated by the application of the contingency funds.[115] This requirement was introduced in the 2013–14 MPR.[116] In 2022–23, two projects applied contingency to manage project risks: MHR90 Helicopters (supportability and performance risks) and SRGB Air Defence (additional contract costs associated with pandemic-related delays). In the ANAO’s judgement, all major projects had ‘complied with Defence’s financial policy relating to contingency funding’.[117]

2.104However, the ANAO examined the project contingency logs and highlighted a lack of clarity in the relationship between contingency allocation and identified risks. The ANAO found:

Two projects (Collins Comms and EW and ANZAC Air Search Radar Repl.) did not explicitly align the contingency log with the risk log to ensure that the expected cost impact of risks is maintained effectively, as required by the Capability Acquisition and Sustainment Risk Management Manual (CAS RMM) V1.0.[118]

2.105A similar observation with regard to the misalignment of contingency allocation and identified risks was made in the 2021–22 MPR on the Joint Strike Fighter, Hunter Class Frigate, and MHR90 Helicopter projects; and in relation to five projects in the 2020–21 MPR.[119] In the Committee’s Report 496, it was noted that Defence acknowledged the lack of alignment in the 2021–22 MPR projects and stated it was being addressed as part of the risk management processes. Nevertheless, the Committee recommended Defence provided a detailed update on the implementation of, and compliance with, internal policies for contingency funding.[120]

2.106The response from Defence does not go to the full intent of the recommendation. The discussion in Report 496 from which the recommendation arose raised specifically the issue of non-alignment between contingency allocations/funding and risk logs, as required by Defence guidance.[121]

2.107In its response to the recommendation, Defence stated:

An assessment of the projects in scope of the 2022–23 Major Project Report identified that all five projects that had used contingency had linked this to a risk in their respective logs, and followed the Defence policy. Defence continues to assess compliance for all major projects.[122]

2.108While the ANAO stated in the 2022–23 MPR all major projects had complied with contingency funding requirements—that is, that the use of contingency funding was dependent on the occurrence of a contingency risk event—it stated: the clarity of the relationship between contingency allocation and identified risks continues to be an issue’, and as noted above, identified two projects where there was no explicit alignment between the contingency log and risk log to ensure the expected cost impact of risks was maintained effectively.[123]

2.109The ANAO also highlighted in relation to the risk management framework, the lack of clear link between allocations against risk in the contingency log and risk log.[124]

2.110On this basis, it is not clear how Defence’s update on its compliance with internal policies for contingency funding, requested by the Committee, deals with the lack of alignment between risk logs and contingency allocation.

Committee comment

2.111It was noted in Report496 that issues relating to risk management, including contingency, have been ongoing.[125] The MPR has been highlighting issues in the clarity of the relationship between contingency allocation and identified risks even before the 2013–14 MPR when the requirement for a contingency statement was introduced. In fact, all MPRs since 201112 have made a similar observation.[126]

2.112The Committee notes that while Defence may have responded to the letter of Recommendation 2 in Report 496, it has not responded the intent of the recommendation.

2.113The Committee will consider future recommendations should this long-running issue be reported as unresolved in future MPRs.

Terminology

2.114In previous reports, the Committee has commented on Defence’s creative use of non-specific terminology to obscure the extent to which key milestones identified as ‘achieved in principle’ have outstanding actions to be rectified or mitigated, given the common sense understanding of the concept ‘achieved’.[127] In Report489, the Committee recommended that Defence clarify the definition of any term used in the MPR associated with a deviation from project milestones being achieved.[128]

2.115Defence subsequently defined ‘caveat’ and ‘deficiency’ but not terms like challenge, concession, condition, exception, impact, issue, and risk, which had previously been used, and then closed the recommendation.[129] These nebulous terms can be used to confound readers as to what ‘achieving’ a milestone actually means. The Committee found Defence’s definition of ‘caveat’ and ‘deficiency’ only, did not meet the Committee’s recommendation to clarify any term relating to a deviation from project milestones being achieved. The Committee noted that Defence continued to use other non-defined terms with regard to milestone achievement such as ‘minor exception’, and ‘issues for resolution’.[130]

2.116The ANAO advised that in 2022–23, Defence did not declare the achievement of any IOC, FOC, or other capability milestones for the major projects[131] and as such, declaring milestones with ‘caveats’ and ‘deficiencies’ or other hazy qualifications, did not arise for the major projects.

2.117In its commentary, Defence stated its definitions of ‘caveat’ and ‘deficiency’ were ‘endorsed’ and ‘authorised terms describing a … deviation from project milestones being achieved’. It defines these terms as follows:

  • Caveat—In relation to the declaration of IOC or FOC or other capability milestone, is a plan, stipulation, condition or limitation to mitigate the capability impact of a Deficiency.
  • Deficiency—In relation to the declaration of IOC or FOC or other capability milestone, is a shortfall between the Government agreed requirements and that which is provided at the milestone.[132]
    1. The definitions were ‘endorsed’ and ‘authorised’ by Defence, and clarified in its Product Life Cycle Guidance glossary in late 2022.[133]
    2. Defence stated in the 2022–23 MPR, three projects continued to use the ‘legacy’ term ‘exception’ but it would ‘adhere consistently to these [caveat and deficiency] definitions for all future project milestones’.[134]
    3. In its response to a recommendation arising from Report 496 that was dealing with Defence’s decision to close the recommendation from Report 489 despite not defining all terms used to modify achievement of a milestone, Defence acknowledged:

… the definition of the two terms does not meet the intention of the Committee’s recommendation to clarify any terms relating to a deviation from project milestones being achieved.[135]

2.121However, Defence stated its intention at the time was that ‘caveat’ and ‘deficiency’ would be the only terms used henceforth, and that it intended to define in the 2022–23 MPR any remaining legacy references. Subsequently, it provided definitions for ‘exception’, ‘issue’, and ‘risk’ in the 2022–23 MPR glossary. Defence stated ‘all projects will adhere to the endorsed terms of “caveats” and “deficiencies” going forward’.[136]

2.122The Committee notes that Defence’s response to the recommendation was dated December 2023, but not received by the Committee until 24 June 2024.

Committee comment

2.123The Committee has a long-standing interest in the use of precise definitions so as to ensure transparency and accountability as to the achievement of milestones. In general, it questions whether a milestone can be ‘achieved’ with a ‘deficiency’ when a deficiency means the requirements of a milestone have not been met, notwithstanding there may be a caveat as to how the impact of failing to deliver the requirements of a milestone might be mitigated.

2.124The Committee will continue to monitor with interest, the use of qualifications to the achievement of milestones in future MPRs.

Scope and the relationship between capability and delivery managers

2.125Considering the broader strategic environment and the need to accelerate the delivery of capability, the Committee examined the issue of scope creep, which can be a key reason for delays and cost escalations, and in this context, the relationship between capability and delivery managers.

Governance arrangements for scope changes

2.126The Mortimer review in 2008 addressed the issue of capability managers and changes to scope, including through a recommendation to improve governance:

Recommendation 3.13

Changes to the scope of projects should occur through a disciplined process that considers the merit of the change mindful of the impact on cost and schedule.[137]

2.127The review also called for more formal and robust arrangements when scope changes were proposed:

Changes to the scope of a project should only occur after assessing their merit mindful of the impact on cost and schedule. PMSG [Project Management Stakeholder Groups] are an appropriate venue to carry out such an assessment. Proposed changes should be assessed by the relevant PMSG and a recommendation made to the delegated authority. For significant changes this will mean formally going back to one of the capability committees convened by CDG [Capability Development Group] and may, in some cases, require a decision from Government.[138]

2.128More than fifteen years later, Defence acknowledged governance of scope changes remained an area that needed to be better managed:

This has always been a vexing problem for projects, and in particular large, complex projects, where scope is expansive and often open to interpretation, no matter how hard you try to get a functional performance specification laid out. There are always trade-offs that need to be made through the life of a project.[139]

2.129Defence stated there was ‘a natural tension’ between the capability manager, who desires the best possible capability and has particular expertise that is critical from a war-fighting perspective; and the delivery manager, who is responsible for delivering the contracted scope. It was important that where tensions existed they had to be escalated, and in this area, Defence’s ‘governance needs to be strengthened’.[140]

2.130In a supplementary submission to the inquiry, Defence stated that through a strengthened One Defence Capability System and the acquisition and sustainment procurement processes within it, there would be ‘reinforcement of the accountability model for managing agreed baselines and articulating escalation criteria for where there are required or proposed changes to scope’.[141]

2.131This same submission stated in reforming the One Defence Capability System, ‘many lessons from previous reviews would inform implementation’, specifically, the following:

  • Kinnaird Review—Defence Procurement Review – 2003
  • Mortimer Review—Going to the Next Level: Report of the Defence Procurement and Sustainment Review – 2008
  • Black Review—Review of the Defence Accountability Framework – 2011
  • First Principles Review—Creating One Defence – 2015
  • ANAO audit—Department of Defence’s Procurement of the Hunter Class Frigates – 2023.[142]
    1. The First Principles Review noted that, notwithstanding many reviews, there had been only incremental change within Defence. Reviews have identified recurring issues with a lack of accountability, ill-defined authority, unclear allocation of responsibility and great difficulty measuring and monitoring real performance; the requirement for fundamental and sustained changes in attitude and culture across all arms of the organisation; and the persistence of fundamental problems in the Defence capability system, from capability and planning to acquisition, delivery and finally sustainment. The review stated, ‘the recurring themes and the continuing need for external review are symptomatic of an organisational culture within Defence that is risk-averse and resistant to change’.[143]
    2. During the hearings, the Committee was assured by Defence that as part of its procurement reform, it was looking at how it could put in place ‘more disciplined processes’[144] and further:

… in CASG … we provided explicit advice to all of our team, from the deputy secretary level down, that there will be no changes to requirements that aren’t escalated up. On your point around the triggers, we need to work on what those triggers might be’.[145]

2.134Defence stated it had to strengthen its governance processes to ensure that where there was a significant deviation from scope proposed, it was ‘escalated back up through the committee process, the decision-makers and to government,’ rather than being agreed at a lower level.[146]

2.135However, the extent to which changes to governance processes may be implemented across projects is not clear. The Committee was told governance arrangements are still made at the project level:

… we’re a big and complex organisation … it is our express intent that scope is not changed without appropriate authority, but it is not codified in a set of rules yet because we are making decisions per project about the governance system that that project needs to have … we certainly endeavour to ensure CMs [capability managers] and DMs [delivery managers] are connected and there is attention to that, and the Joint Force Authority is the mechanism we are using to resolve that.[147]

2.136Defence agreed that in the case of the Hunter Class Frigate and the Offshore Patrol Vessel, governance arrangements for scope changes had fallen short: delegations for scope changes were ‘most probably set too low … we didn’t set ourselves up right’.[148]

Management of scope prior to Gate 2

2.137While scope has the potential to creep post-Gate 2, where scope, budget and delivery have apparently been agreed and the project is being executed, management of scope begins at the point of capability consideration.[149]

2.138‘The worst part of the equation,’ according to Defence, is where high-level requirements are insufficiently defined at the commencement of a program and where subsequent definition and realisation of the actual lower-level requirements results in difficult judgements:

… where scope may be ill-defined, and that is used to then expand scope, and, in expanding scope, adding risk and cost to the program. Sometimes we may do that within a fixed price context, which sets the contractor up for failure because they now have to increase the scope of the work being conducted within a constrained budgetary environment.[150]

2.139Defence emphasised the need for discipline:

… as people—the good-ideas fairies—look to continue to refine that capability. There will be times when that is justified, where the threat may change … But there will be times when that may not be affordable, in the context of our overarching budgets, and this is where those opportunity costs associated with doing something new, versus continuing the journey and investing in other things, need to be traded off.[151]

2.140Though procurement has long been a key capability requirement for Defence, it said it had learnt from the procurement of the Hunter Class Frigate and ‘recent’ ANAO reports the importance of ‘[setting] ourselves up strategically for success, rather than where we have potentially rushed that strategy phase and not established the firm foundations for a successful program’.[152]

Minimum viable capability

2.141Notwithstanding Defence’s failure to learn until recently the importance of setting itself up strategically for success, or to properly implement recommendations from Defence reviews as to governance arrangements, it suggested a new imperative would provide the necessary discipline in project planning. Discipline on scope prior to Gate2 may be provided by the strategic context, as described in the 2023 Defence Strategic Review, the classified version of which had given Defence a ‘very clear direction’ on the functional requirements for acquisitions, and where previously Defence had focussed on getting ‘the best’ that it could:

We are now in an environment where we talk about the minimum viable capability that meets the specification of performance criteria in a timeframe. With that trinity of resources—people, money, and time—in the past time was the sacrificial variable; you would go for quality. Now we have a time imperative. That's completely reset the structure.[153]

2.142Defence stated, ‘time is now of the essence,’ and it had to determine the ‘minimal viable capability’ aspect of the capability need during the strategy phase at Gate 0 and then implement the necessary systems to keep scope bounded:

What I'm trying to do from a procurement acquisition perspective is start to get the strategy right at that early stage and to establish an implementation risk assessment from a delivery manager perspective, which ties into the capability manager view of the capability need.[154]

2.143In Defence’s definition of the concept provided in its supplementary submission, however, it was not clear what might tightly bind scope other than the suggestion capability might be obtained ‘quickly’. Defence defined the attributes of minimum viable capability as a capability that provides what is required to achieve a military effect, quickly, demonstrating value for money[155] and with manageable technical and operational risk. Such capability, may be further developed through sustainment or subsequent investment phases. Minimum viable capability was also a capability ‘that can successfully achieve the lowest acceptable level of the directed effect in the required time, able to be acquired, introduced into service and sustained effectively’.[156]

2.144At this point, it might be noted Defence’s ability to meet deadlines has not been consistently demonstrated, even when it was attempting to be quick. The Committee was told Defence already ‘sets ambitious schedules to drive performance and efficiency and to get capability to the war fighter’.[157] However, there is a point at which ambitious schedules become unrealistic and damage the prospects for success, as suggested by a lesson from the CMATS PDSS:

Aggressive timeframes to meet schedule milestones often results in compressed timeframes to engage stakeholders (operational, engineering/technical and strategic), leading to compromises to proper requirements management. Consequently, a schedule needs to be developed to include opportunities for specified periods of stakeholder consultation and alignment during the capability delivery life-cycle.[158]

2.145Further, Defence stated the requirements for minimum viable capability were based on the strategic need, timing for delivery, approval pathway, procurement method, and industry capability and capacity.[159]

Compliance with Commonwealth Procurement Rules

2.146Defence acknowledged if a project was established professionally, there was appropriate flexibility in the Commonwealth Procurement Rules (CPRs) to determine the correct approach to market:

We can work within the CPRs … Part of the problem that we've got is how we make our people aware of what the CPRs are and how they best need to be applied. In particular, one of the areas that we need to strengthen is value for money … This is where we again need to do better work in training our people to understand the application of the CPRs. I still firmly believe that the CPRs are workable, that we can work within that framework.[160]

Committee comment

2.147The Committee notes that in its supplementary submission, Defence provided words to the effect that it would define roles and strengthen accountabilities; the Joint Force Authority would provide more direction and oversight; there would be disciplined management of requirements and baselines; Defence would comply with legislated requirements; assurance would be provided against operational scenarios; a new governance model would enhance the use of the test and evaluation framework; there would be continuing reporting and assurance; performance would be measured; and Defence would be skilling and professionalising its people. In an of itself, this reflects basic but sound management practices.

2.148However, the record of Defence’s performance on procurement leaves questions as to how effective the reforms will be in improving project performance. Defence stated lessons from the Mortimer review more than fifteen years ago, which recommended improvements to Defence governance, will inform its systemic reforms. The Committee will observe with interest the progress Defence makes in embedding these arrangements, in particular, the governance arrangements for scope changes.

2.149With regard to the suggestion ‘minimum viable capability’ will serve as something of a brake on scope changes, the Committee reserves its judgement. Given the plethora of considerations—strategic need, timing for delivery, approval pathway, procurement method, industry capability, manageable technical and operational risk, value for money, and the possibility for further development—it is not immediately clear how the concept of ‘minimum viable capability’ might introduce a level of discipline into Defence procurements.

2.150Quite aside from that, the potentially nebulous nature of terms like ‘minimum’ and ‘viable’ and ‘lowest acceptable’, which themselves could be subject to wide interpretation involving value judgements in practice, leaves questions as to the capacity of ‘minimum viable capability’ to resolve delays in Defence acquisitions. The suggestion that capability may be ‘further developed through sustainment or subsequent investment phases’ would seem to be an invitation for endlessly tranched or phased projects stretching into the future.

2.151Defence told the Committee it was implementing a more disciplined process for scope changes. Over the years the Committee has heard Defence state it is strengthening various aspects of its procurement process. The Committee cannot be certain how substantive this guarantee might be, given Defence acknowledged there was no agreement on triggers and the supplementary submission provided nothing further beyond there would be ‘mechanisms for escalation’ applied across all projects and tailored escalation arrangements for some projects appropriate to their urgency and complexity.[161]

2.152The Committee therefore recommends that Defence provides an annual update on the implementation of its improved governance and assurance process, including detail on triggers.

Recommendation 2

2.153The Committee recommends that Defence provides an annual update to the Committee on the implementation of its improved governance and assurance process as it applies to acquisitions, including progress on embedding this across all projects, and detail on the procedure for scope change decision escalation.

2.154The Committee notes Defence’s assurances that it is able to comply with the Commonwealth Procurement Rules, which as part of finance law, is a legal obligation.

Military off-the-shelf

2.155An issue of relevance to scope, and the relationship between capability and delivery managers, is the extent to which Defence legitimately considers off-the-shelf options in its procurements. Many Defence reviews have included discussion, and in some cases, recommendations, about consideration of off-the-shelf options in Defence procurements, including: Defence Governance, Acquisition and Support (2000); Kinnaird review (2003); Mortimer review (2008); Pappas review (2009); Black review (2011); First Principles Review (2015);[162] and the Defence Strategic Review (2023).[163]

2.156The Kinnaird review stated:

… an off-the-shelf alternative must be part of any set of options put to government to ensure that a benchmark is established against which the costs, military effects, and schedule of all proposals can be assessed.[164]

2.157The Mortimer review in 2008 noted that while the Kinnaird review had recommended an off-the-shelf solution must be put to government to ensure a benchmark for the comparison of options, this had not always occurred:

While project requirements must ultimately reflect the demands of operational performance, they need to be tempered by the realities of cost, risk and what the market can deliver off-the-shelf and otherwise. Unless this is done, informed decisions about the appropriate mix of cost, schedule, risk and capability are impossible.

… Defence should increase its use of off-the-shelf equipment … this can and will occur if Defence is more business-like in analysing its requirements against what is available in the marketplace.

… Recommendation 2.3: Any decisions to move beyond the requirements of an off-the-shelf solution must be based on a rigorous cost-benefit analysis of the additional capability sought against the cost and risk of doing so. This analysis must be clearly communicated to Government so that it is informed for decision-making purposes.[165]

2.158In 2013, the ANAO noted if the desired effect of the requirement announced in 2011 that all projects seeking Second Pass approval that are not off-the-shelf would include a rigorous cost-benefit analysis against an off-the-shelf option, Defence would ‘need to improve on previous performance and ensure routine compliance’.[166]

2.159In 2023, the Defence Strategic Review again stated:

When capability is readily available there should be an emphasis on getting it into service without delay and achieving value for money. Defence must, where possible, acquire more platforms and capabilities via sole source or off-the-shelf procurement, and limit or eliminate design changes and modifications. When subsequent design changes or enhancements to capabilities are proposed, we recommend these be independently tested by sceptical and truster advisers.[167]

2.160The requirement for a military off-the-shelf consideration and justification for any bespoke solution being presented to government is today, according to Defence ‘not as explicit. It's now evolved through that Smart Buyer process. We don't force that there must be a COTS [commercial off-the-shelf] or MOTS [military off-the-shelf] exemplar to be assessed against’.[168]

2.161The relationship between Smart Buyer and the consideration of military off-the-shelf options to provide a benchmark for time, cost and capability assessments is not clear. Smart Buyer was introduced in the First Principles Review (and has since been incorporated into the CASG Business Framework),[169] which described Smart Buyer as such:

A smart buyer is one who retains an in-house staff who understands the organization’s mission, its requirements, and its customer needs, and who can translate those needs and requirements into corporate direction. A smart buyer also retains the requisite capabilities and technical knowledge to lead and conduct teaming activities, accurately define the technical services needed, recognize value during the acquisition of such technical services, and evaluate the quality of services ultimately provided. As long as the owner retains the in-house capabilities to operate as a smart buyer of facilities, there does not appear to be any greater risk from contracting out a broad range of design review-related functions, so long as such functions are widely available from a competitive commercial marketplace. If the owner does not have the capacity to operate as a smart buyer, the owner risks project schedule and cost overruns and facilities that do not meet performance objectives.[170]

2.162It is not clear why the introduction of the Smart Buyer program was accompanied by a phase out of the consideration of military off-the-shelf options, given, as described by Defence itself, Smart Buyer is a decision-making framework, ‘which enables project sponsors and integrated project teams to identify key project risks and use that risk analysis to develop tailored project execution strategies’[171] and assists Defence in ‘setting projects up for success at Gate Zero’.[172] The Committee surmises Defence is of the view it can benchmark absent an exemplar.

2.163Information currently contained in the PDSSs does not always provide a clear understanding of the extent to which MOTS options were seriously considered, or used for the purposes of benchmarking. The following table summarises the information on MOTS in the 2022–23 MPR.

Table 2.3Off-the-shelf considerations noted in the 2022-23 Major Projects Report

Project

Consideration

MHR 90

AIR 9000 Phase 2/4/6: Incorrectly viewed as military off-the-shelf[173]

Collins Comms and EW

SEA1439 Phase 5B2: Stage 1 updated the obsolete COMCEN equipment on-board the Collins Class with a military off-the-shelf solution[174]

ANZAC Air Search Radar Replacement

SEA 1448 Phase 4B: Government at Gate 1 (March 2015) was presented multiple options including Developmental and Military Off-The-Shelf (MOTS) options, with the MOTS approach based on an upgraded variant of AN/SPS-49(V) not progressing further as it did not resolve the obsolescence issues[175]

Battlespace Communications System

JNT 2072 Phase 2B: I-BTN (Integrated Battlespace Communications System Network) capability is developmental as no off-the-shelf systems were available to meet the requirements for the I-BTN; the I-BTN is being developed to integrate developmental components and a range of off-the-shelf components, to meet requirements; Boeing Australia is buying and integrating off-the-shelf equipment[176]

Hawkei-related project – LAND 154 Phase 4

LAND 121 Phase 4/LAND154 Phase 4: Joint Counter Improvised Explosive Device Capability - This project replaces the ADF’s existing Force Protection Electronic Counter Measures (FPECM) capability through improved military off-the-shelf technology, procured via the US Foreign Military Sales program[177]

Battlefield Command System

LAND 200 Tranche 2: Scope - no Military Off-the-Shelf BMS product was available that provided all of the Army’s requirements[178]

Combat Reconnaissance Vehicles

LAND 400 Phase 2: an assessment prior to First Pass Approval identified current MOTS solutions were unlikely to meet all of Army’s capability requirements[179]

Heavy Armoured Capability

LAND 907 Phase 2/LAND 8160 Phase 1: As a largely off the shelf purchase of MBT (Main Battle Tank), CEV (Combat Engineering Vehicle) and ARV (Armoured Recovery Vehicles) via FMS (Foreign Military Sales), no major risks or issues have been identified at this stage[180]

Advanced Growler

AIR 5349 Phase 6: ADVM7, ADVM8, ADVM9 and ADVM11 systems are off-the-shelf CEA Technologies Pty Ltd products without any development required[181]

Source: 2022-23 Major Projects Report

2.164As noted above, Defence suggested to the Committee the introduction of the concept, ‘minimal viable capability, speed to capability being the mantra now … That’s going to change us back to looking at the MOTS-COTS solutions’.[182]

2.165Defence confirmed in a supplementary submission it would ‘consider more off-the-shelf, readily available options that require minimal or no modification,’ and the Smart Buyer process would support the consideration of these options in the early stages of a project.[183]

Committee Comment

2.166The Committee welcomes Defence’s confirmation it will consider more off-the-shelf, readily available options, however, is of the view absent a requirement, this cannot be guaranteed. Previous Defence reviews have made recommendations to this effect. Without a requirement, capability managers may be tempted to specify timelines, processes or requirements that rule out certain options.

2.167The Committee will consider whether the Guidelines might be amended at some future stage to require the provision of clear and unambiguous evidence an off-the-shelf option has been seriously considered for all projects.

Future of the MPR

2.168The MPR is intended to provide information and assurance on the performance of selected major Defence acquisition projects. Its objective is to improve the accountability and transparency of Defence acquisitions for the benefit of Parliament and other stakeholders.[184]

2.169As it stands:

  • limited assurance standard: the level of assurance provided by the Auditor-General relies primarily on an agency’s representations and other evidence generated by the agency, and expresses opinion in negative terms
  • PDSS information excluded from assurance: AIC, forecast dates, expected capability/scope delivery performance, and future risks are out of scope of ANAO’s assurance because Defence systems cannot provide complete and/or accurate evidence in a sufficiently timely manner[185]
  • accuracy of PDSSs: the ANAO ‘observed ongoing quality issues relating to Defence’s preparation of iterations of the PDSSs,’ including instances where internal project reporting—relating to financial data, schedule milestone dates, quantities of material, and risks and issues—though accurate, was not accurately reflected in the PDSSs[186]
  • secrecy: classification of information has led the ANAO to conclude ‘there has been a reduction in the level of transparency and accountability, to the Parliament and other stakeholders since the 2020–21 MPR’,[187]a trend that will continue
  • risk management: the MPR process provides limited insight into the accuracy of risk assessments and effectiveness of risk management.
    1. Defence put forward its views on how the MPR might evolve in a context where it is classifying increasing amounts of information on national security grounds. It suggested, broadly, considering projects of strategic importance; better capturing thematic and systemic findings; focusing findings on certain matters; and refining in-year longitudinal analysis. Each of these is considered below.

Considering projects of strategic importance

2.171Defence suggested the report could evolve to ‘present a similarly holistic view of the Defence major project portfolio by considering projects of strategic importance’.[188]

2.172Defence does not explain what is meant by ‘strategic importance’. The projects in the MPR represent a selection of the most significant major projects managed by CASG and the Naval Shipbuilding and Sustainment Group (NSSG). The selected projects are ‘strategic’ in the sense that they are generally high cost, complex and important in terms of expected capability.

Better capture thematic and systemic findings

2.173Defence suggested a future MPR could focus on the performance categories of: capability, schedule, cost and delivery and in so doing, better capture thematic and systemic findings.[189]

2.174The MPR presently requires Defence to report on capability, schedule, cost and delivery. However, Defence’s decision to classify information as ‘not for publication’ means full public reporting on schedule has not been possible. This impacts on the ability of the Parliament to understand capability and delivery.

Focus of findings

2.175Defence suggested findings, thematic and systemic, could focus on actual cost pressures resulting in a real cost increase, and schedule delays which impact on the achievement of operational capabilities, milestones, and the realisation of delivery risks, which impact on scope.[190]

2.176The disclosure of such issues is expected of Defence in the PDSS, and the ANAO provides assurance over this information.

Refinement of in-year longitudinal analysis

2.177Defence suggested the ANAO’s in-year longitudinal analysis of aggregate project data could be refined ‘to provide meaningful and insightful understanding of the risk relating to financial, schedule and performance associated with project complexity’. It stated the focus should be on the lessons that can be learnt for application to future projects.[191]

2.178The MPR is a limited assurance engagement that focuses on the integrity of Defence reporting in the PDSSs against the requirements of the MPR guidelines. This allows the ANAO to cover a broad range of projects annually in a structured way.

2.179A performance audit would allow the ANAO to look deeply to form an independent and holistic view on the full range of risks—financial, schedule, performance, and corresponding project complexity. However, a positive assurance, or performance audit, approach would require significant ANAO and Defence resources and would be considerably more intrusive than the current limited assurance approach.

2.180The MPR does not prevent Defence from learning lessons, and indeed it could readily draw from the PDSSs, lessons for its own purposes.

Committee comment

2.181Now in its sixteenth year, the Committee considers it timely to assess whether the MPR continues to provide the necessary scrutiny and accountability for Defence acquisitions that was intended at its inception.

2.182While the Committee has previously noted that the discipline of the MPR has had positive impacts on Defence’s internal management of major projects, it is notable that the ANAO experiences ongoing quality issues in Defence’s preparation of PDSSs. In 2022–23, the ANAO assessed the PDSSs through four key milestones: a preliminary assessment of the initial drafts; a first assurance review; a second assurance review; and a third and final assurance review. Even after the third and final assurance review, the ANAO continued to advise Defence of material errors and quality issues in the PDSSs.[192]

2.183Further, forecast information relating to Australian Industry Capability, material capability/scope delivery performance, risks and issues, and forecast dates is excluded from the scope of the ANAO’s review because Defence systems cannot provide complete and/or accurate evidence in a sufficiently timely manner to complete the review.[193]

2.184In Report 503, the Committee examined major projects reports undertaken in other jurisdictions. Alternative models have both benefits and drawbacks; but no jurisdiction has in place the type of structured scrutiny and granularity across projects provided by the MPR, conducted with the rigour of public, independent assurance via a national audit institution.[194]

2.185The Committee has considered bespoke options, including a hybrid option that would slightly reduce the number of projects but examine each in greater detail. This would be complemented with a higher level dashboard-type approach on a broader suite of projects.

2.186As it considers how the MPR can best deliver on its intent, the Committee continues to support the work undertaken by Defence and the ANAO to evolve the Guidelines through the annual Guidelines process. It has been noted in this report that the MPR is an important mechanism for scrutiny and accountability and as such, the Committee recommends it be strengthened to provide a more thoroughgoing account of project costs and greater transparency as to project modifications over the life of each project. Accordingly, the Committee makes the following recommendations.

Recommendation 3

2.187The Committee recommends the Department of Defence examines and provides to the Committee in the Major Projects Report 2025–26, an assessment of the full project costs for each project, including fundamental inputs to capability: organisation, command and management, personnel, collective training, major systems, facilities and training areas, supplies, support, and industry.

Recommendation 4

2.188The Committee recommends the ANAO and Department of Defence examine and provide to the Committee in the draft 2025–26 Major Projects Report Guidelines, options for including in the MPR, in an easily accessible format, a high-level summary of modifications to scope, schedule and budget for ‘in-year’ and ‘life-to-date’ of each project. This would allow for the easy identification of project variations, scope changes, and real cost increases. It would include an explanation of: the source of funding for scope changes, whether scope was transferred to other projects/phases, the extent of real budget increases and how they have been met, and whether timeframes were extended.

Hon Linda Burney MP 
Chair

10 December 2024

Footnotes

[1]Australian National Audit Office (ANAO), 2022–23 Major Projects Report, Report No. 14, 2023–24,hereafter 2022–23 MPR, p. 18.

[2]ANAO, 2022–23 MPR, p. 6.

[3]Offshore Patrol Vessel, Peregrine, SRGB Air Defence, JORM Mid-Life Upgrade. ANAO, 2022–23 MPR, p. 6.

[4]ANAO, 2022–23 MPR, pages 67.

[5]ANAO, 2022–23 MPR, pages 7, 28.

[6]These projects are the Joint Strike Fighter, Advanced Growler, Peregrine, Heavy Armoured Capability, JORN Mid-Life Upgrade, Battlefield Command System, Maritime Comms, and ANZAC Air Search Radar Replacement. ANAO, 2022–23 MPR, p. 18.

[7]ANAO, 2022–23 MPR, p. 48 (fn 90).

[8]ANAO, 2022–23 MPR, p. 11.

[9]ANAO, 2022–23 MPR, p. 13.

[10]ANAO, 2022–23 MPR, p. 48.

[11]ANAO, 2022–23 MPR, p. 90.

[12]Major General Anthony Rawlins, Head of Force Design, Department of Defence (Defence), Committee Hansard, 24 April 2024, p. 10.

[13]Major General Anthony Rawlins, Defence, Committee Hansard, 24 April 2024, p. 10.

[14]Major General Anthony Rawlins, Defence, Committee Hansard, 24 April 2024, p. 10.

[15]Joint Committee of Public Accounts and Audit (JCPAA), Report 503: Inquiry into the Defence Major Projects Report 2020–21 and 2021–22 and Procurement of Hunter Class Frigates: Final Report, June 2024, hereafter Report 503, p. 14.

[16]JCPAA, Report 496: Inquiry into the Defence Major Projects Report 2020–21 and 2021–22 and Procurement of Hunter Class Frigates – Interim Report on the 2020–-21 and 2021–22 Defence Major Projects Report, hereafter Report 496, pages 21, 25.

[17]ANAO, 2019–20 MPR, pages 33–34.

[18]ANAO, 2020–21 MPR, p. 35.

[19]JCPAA, Report 496, pages 2122; ANAO, 2021–22 MPR, p. 39.

[20]ANAO, 2022–23 MPR, p. 44.

[21]ANAO, 2022–23 MPR, p. 44.

[22]ANAO, 2022–23 MPR, p. 101.

[23]ANAO, 2022–23 MPR, p. 44.

[24]Original planned final operational capability: December 2023. ANAO, 2022–23 MPR, p. 278.

[25]Original planned final operational capability: NFP. ANAO, 2022–23 MPR, p. 238.

[26]Original planned final operational capability: January 2029. ANAO, 2022–23 MPR, p. 248.

[27]Original planned final operational capability: June 2022. ANAO, 2022–23 MPR, p. 213.

[28]Original planned final operational capability: December 2023. ANAO, 2022–23 MPR, p. 151.

[29]Original planned final operational capability: June 2024. ANAO, 2022–23 MPR, p. 159.

[30]ANAO, 2022–23 MPR, p. 338.

[31]ANAO, 2009–10 MPR, pages 122, 273.

[32]ANAO, 2022–23 MPR, p. 338.

[33]ANAO, 2022–23 MPR, pages 45, 102.

[34]ANAO, 2022–23 MPR, p. 102.

[35]ANAO, 2022–23 MPR, p. 216.

[36]LAND 200 Tranche 2 entered the MPR in 201920; LAND75 Phase 4 was first reported in the 201516 MPR.

[37]ANAO, 2022–23 MPR, p. 216; ANAO, 2019–20 MPR, p. 302; ANAO, 2020–21 MPR, p. 266; ANAO, 2021–22 MPR, p. 264.

[38]All nine were published in 201920 and 202021; eight were published in 202122; three in 202223. ANAO, 2019–20 MPR, p. 140; ANAO, 2020–21 MPR, p. 134; ANAO, 2021–22 MPR, pages 134–135; ANAO,2022–23 MPR, p. 281.

[39]ANAO, 2022–23 MPR, p. 45.

[40]ANAO, 2022–23 MPR, p. 44.

[41]Mr Chris Deeble, Deputy Secretary, Capability Acquisition and Sustainment Group, Defence, Committee Hansard, 24 April 2024, p. 7.

[42]Mr Chris Deeble, Defence, Committee Hansard, 24 April 2024, p. 7.

[43]ANAO, 2021–22 MPR, p. 264.

[44]ANAO, 2021–22 MPR, p. 212.

[45]ANAO, 2021–22 MPR, p. 135.

[46]ANAO, 2022–23 MPR, p. 178.

[47]ANAO, 2022–23 MPR, p. 250.

[48]ANAO, 2022–23 MPR, p. 311.

[49]ANAO, 2022–23 MPR, p. 169.

[50]Dr Tom Ioannou, Group Executive Director, Performance Audit Services Group, ANAO, Committee Hansard, 24 April 2024, p. 5.

[51]Mr Chris Deeble, Defence, Committee Hansard, 24 April 2024, p. 2; ANAO, 2022–23 MPR, p. 95.

[52]Defence, ‘Battlefield Command System’, www.defence.gov.au/defence-activities/projects/battlefield-command-system, viewed 23 July 2024.

[53]ANAO, Modernising Army Command and Control—The LAND 200 Program, Report No. 40 2018–19, May2019, hereafter LAND 200 report, p. 14.

[54]ANAO, LAND 200 report, p. 14.

[55]ANAO, LAND 200 report, pages 7, 14.

[56]According to the ANAO, Tranche 1 comprised 3 separate projects intended to equip a third of the Army: LAND75 Phase 3.4—Battle Management System; LAND125 Phase 3A—dismounted (soldier carried) Battle Management System; JP2072 Phase 1—vehicle-mounted radios and vehicle installation kits. ANAO, LAND 200 report, pages 14–16.

[57]ANAO, LAND 200 report, p. 19.

[58]Tranche 2 contained four work packages: A - follow on purchase of mounted Battle Management System and associated radios and integration into certain vehicles; B – Integration of BMS into certain vehicles, TCN; C – integration of capability into the Army training system; D – development of software to enable interoperability with joint and coalitions systems, development of weapon-integrated BMS for the M1A1 tank. Work Package A obtained simultaneous first and second pass approval on 5 August 2013, and first pass approval for packages B–D was obtained on the same date—the day the writs were issued for the 2013 federal election. ANAO, LAND 200 report, pages 17, 19.

[59]ANAO, LAND 200 report, p. 14; Department of Defence, ‘New battlefield command system to improve Defence’s tactical communications’, www.defence.gov.au/news-events/releases/2023-07-13/new-battlefield-command-system-improve-defences-tactical-communications, viewed 22 July 2024.

[60]This was described as a ‘major software enhancement’ for Army headquarters functions. ANAO, LAND 200 report, p. 29.

[61]The tender price was over half a billion dollars or 370 per cent greater than the $180 million expected. ANAO, LAND 200 report, pages 8–9, 17, 21, 24–25, 27, 31.

[62]ANAO, LAND 200 report, p. 40.

[63]ANAO, LAND 200 report, p. 19.

[64]ANAO, LAND 200 report, p. 20.

[65]ANAO, LAND 200 report, p. 21.

[66]ANAO, LAND 200 report, p. 8.

[67]ANAO, LAND 200 report, pages 810, 23–24.

[68]ANAO, LAND 200, pages 8–9, 23, 25–26.

[69]ANAO, LAND 200 report, p. 34.

[70]ANAO, LAND 200 report, pages 910, 35, 42, 48.

[71]ANAO, LAND 200 report, pages 10, 35–36, 43, 47.

[72]ANAO, LAND 200 report, p. 43.

[73]Mr Chris Deeble, Defence, Committee Hansard, 28 June 2024, pp. 3-4.

[74]Major General Richard Vagg, Head of Land Capability, Defence, Committee Hansard, 24 April 2024, p. 5.

[75]Major General Vagg, Defence, Committee Hansard, 24 April 2024, pages 4, 6.

[76]Major General Vagg, Defence, Committee Hansard, 24 April 2024, p. 5.

[77]Major General Vagg, Defence, Committee Hansard, 24 April 2024, p. 6.

[78]ANAO, 2022–23 MPR, p. 120.

[79]ANAO, 2022–23 MPR, p. 94.

[80]Mr Chris Deeble, Defence, Committee Hansard, 24 April 2024, p. 2.

[81]ANAO, 2022–23 MPR, p. 95.

[82]ANAO, 2022–23 MPR, pages 95, 120.

[83]ANAO, 2022-23 MPR, pages 211213.

[84]ANAO, 2021-22 MPR, pages 255256, 260.

[85]ANAO, 2021-22 MPR, pages 92, 256257.

[86]ANAO, 2022-23 MPR, pages 208, 210, 212, 214.

[87]ANAO, 2022-23 MPR, p. 208; ANAO, 2021-22 MPR, pages 255256.

[88]ANAO, 2022-23 MPR, pages 208, 212213.

[89]ANAO, 2022-23 MPR, pages 207208.

[90]Major General Vagg, Defence, Committee Hansard, 24 April 2024, p. 5.

[91]Mr Chris Deeble, Defence, Committee Hansard, 24 April 2024, p. 5.

[92]ANAO, MPR 2022–23, p. 218.

[93]Defence, Submission 1.1, p. [3].

[94]Defence, Submission 1.1, pages [2], [3].

[95]ANAO, 2022–23 MPR, p. 120.

[96]ANAO, 2022–23 MPR, pages 35–36.

[97]ANAO, 2022–23 MPR, p. 36.

[98]Defence and ANAO, 2022–23 Major Projects Report Guidelines, 23 September 2022, hereafter MPR Guidelines, section 2.4.

[99]ANAO, 2022–23 MPR, p. 37.

[100]ANAO, 2022–23 MPR, p. 36.

[101]ANAO, 2022–23 MPR, p. 37.

[102]Department of Defence, ‘Sovereign Defence Industrial Priorities’, www.defence.gov.au/business-industry/industry-capability-programs/sovereign-defence-industrial-priorities, viewed 15 July 2024.

[103]JCPAA, Report 473: Defence Major Projects Report (2016–17), September 2018, pages 2, 5, 13–14.

[104]ANAO, 2022–23 MPR, p. 42.

[105]ANAO, 2022–23 MPR, p. 41.

[106]ANAO, 2022–23 MPR, pages 25, 40.

[107]ANAO, 2022–23 MPR, pages 4142.

[108]ANAO, 2022–23 MPR, p. 42.

[109]ANAO, 2022–23 MPR, p. 42.

[110]ANAO, 2022–23 MPR, p. 43.

[111]Ms Rona Mellor, Acting Auditor-General, ANAO, Committee Hansard, 24 April 2024, p. 9.

[112]Mr Chris Deeble, Defence, Committee Hansard, 24 April 2024, p. 9.

[113]ANAO, 2022–23 MPR, p. 38.

[114]ANAO, 2022–23 MPR, p. 38.

[115]ANAO, 2022–23 MPR, p. 39.

[116]ANAO, 2013–14 MPR, p. 31.

[117]ANAO, 2022–23 MPR, p. 39.

[118]ANAO, 2022–23 MPR, p. 39.

[119]ANAO, 2022–23 MPR, p. 39; ANAO, 2020–21 MPR, p. 30.

[120]JCPAA, Report 496, pages 21,25.

[121]JCPAA, Report 496, p. 21.

[122]Australian Government Response to Report 496, 24 June 2024, p. 3.

[123]ANAO, 2022–23 MPR, p. 39.

[124]ANAO, 2022–23 MPR, p. 42.

[125]JCPAA, Report 496, p. 21.

[126]See the following MPRs: 2011–12 MPR, pages 99-100; 2012-13 MPR, pages 33-34; 2013–14 MPR, pages 31-32; 2014–15 MPR, pages 26-27; 2015–16 MPR, p. 24; 2016–17 MPR, p. 24; 2017-18 MPR, p. 27; 2018–19 MPR, p. 28; 2019–20 MPR, p. 29; 2020–21 MPR, p. 30; 2021–22 MPR, p. 35.

[127]Key milestones are: Initial Material Release (IMR), Initial Operational Capability (IOC), Final Material Release (FMR), Final Operational Capability (FOC).

[128]JCPAA, Report 489: Defence Major Projects Report 2019–20, March 2022, hereafter Report 489, p. 26.

[129]Defence did not define these terms in the Executive Minute to the recommendation, but in a later update to its internal capability guidance. Executive Minute on Joint Committee of Public Accounts and Audit Report 489: Defence Major Projects Report 2019–20, 13 September 2022, p. 7.

[130]See discussion in: JCPAA, Report 496, pages 23–24.

[131]ANAO, 2022–23 MPR, p. 47.

[132]ANAO, 2022–23 MPR, p. 111.

[133]ANAO, 2022–23 MPR, p. 47.

[134]ANAO, 2022–23 MPR, p. 111.

[135]Australian Government Response to the Joint Committee of Public Accounts and Audit Interim Report: Inquiry into the Defence Major Projects Report 2020–21 and 2021–22 and the Procurement of Hunter Class Frigates, 24 June 2024, hereafter Australian Government Response to Report 496, p. 4.

[136]Australian Government Response to Report 496, p. 4.

[137]D Mortimer, Going to the Next Level: The Report of the Defence Procurement and Sustainment Review, September 2008, hereafter Mortimer Review, p. xiv.

[138]D Mortimer, Mortimer review, pages 4344.

[139]Mr Chris Deeble, Defence, Committee Hansard, 28 June 2024, p. 1.

[140]Mr Chris Deeble, Defence, Committee Hansard, 28 June 2024, p. 2.

[141]Defence, Submission 1.3, p. 2.

[142]Defence, Submission 1.3, p. 2.

[143]D Peever, 2015, First Principles Review: Creating One Defence, hereafter First Principles Review, pages14,15.

[144]Mr Chirs Deeble, Defence, Committee Hansard, 28 June 2024, p. 1.

[145]Mr Chris Deeble, Defence, Committee Hansard, 28 June 2024, p. 8.

[146]Mr Chris Deeble, Defence, Committee Hansard, 28 June 2024, p. 1.

[147]Mr Matt Yannopoulos, Associate Secretary, Defence, Committee Hansard, 29 June 2024, p. 5.

[148]Rear Admiral Stephen Hughes, Head, Navy Capability, Defence, Committee Hansard, 28 June 2024, pages6–7.

[149]Mr Chris Deeble, Defence, Committee Hansard, 28 June 2024, p. 1.

[150]Mr Chris Deeble, Defence, Committee Hansard, 28 June 2024, p. 1.

[151]Mr Chris Deeble, Defence, Committee Hansard, 28 June 2024, p. 2.

[152]Mr Chris Deeble, Defence, Committee Hansard, 28 June 2024, p. 3.

[153]Major General Anthony Rawlins, Acting Vice Chief of the Defence Force, Defence, Committee Hansard, 28June 2024, p. 3.

[154]Mr Chris Deeble, Defence, Committee Hansard, 28 June 2024, p. 3.

[155]Demonstrating value for money is an existing legal requirement under finance law.

[156]Defence, Submission 1.3, pages 34.

[157]Mr Chris Deeble, Defence, 24 April 2024, p. 2.

[158]ANAO, 2022–23 MPR, p. 269.

[159]Defence, Submission 1.3, p. 4.

[160]Mr Chris Deeble, Defence, Committee Hansard, 28 June 2024, p. 4.

[161]Defence, Submission 1.3, p. 2.

[162]While the First Principles Review did not specifically call for MOTS, it noted it as a recurring theme in other reviews. D Peever, First Principles Review, p. 92.

[163]ANAO, Capability Development Reform, Report No. 6 201314, hereafter Capability Development Reform report, p. 20; D Peever, First Principles Review, p.92; Defence, Defence Strategic Review, 2023, p. 91.

[164]M Kinnaird, L Early, B Schofield, Defence Procurement Review 2003, August 2003, , p. 19.

[165]D Mortimer, Mortimer review, pages 17, 1920.

[166]ANAO, Capability Development Reform report, pages 3637.

[167]Defence, Defence Strategic Review, p. 91.

[168]COTS—commercial off-the-shelf; MOTS—military off-the-shelf. Mr Matt Yannopoulos, Defence, Committee Hansard, 28 June 2024, p. 9.

[169]Defence, The CASG Business Framework: Working together to deliver Defence capability to our customers, 2017, p. 5.

[170]D Peever, First Principles Review, p. 33.

[171]ANAO, 2015–16 MPR, p. 66.

[172]ANAO, 2016–17 MPR, p. 67.

[173]ANAO, 2022–23 MPR, p. 302.

[174]ANAO, 2022–23 MPR, p. 140.

[175]ANAO, 2022–23 MPR, p. 156.

[176]ANAO, 2022–23 MPR, p. 304.

[177]ANAO, 2022–23 MPR, p. 199.

[178]ANAO, 2022–23 MPR, p. 208.

[179]ANAO, 2022–23 MPR, p. 217.

[180]ANAO, 2022–23 MPR, p. 226.

[181]ADVM—Advanced MTTES (Mobile Threat Training Emitter System) ANAO, 2022–23 MPR, p. 255.

[182]Mr Chris Deeble, Defence, Committee Hansard, 28 June 2024, p. 9.

[183]Defence, Submission 1.3, p. 4.

[184]ANAO, 2022–23 MPR, pages viii, 4; Defence and ANAO, MPR Guidelines, paragraph 1.1.

[185]ANAO, 2022–23 MPR, pages 5–6.

[186]ANAO, 2022–23 MPR, p. 27.

[187]ANAO, 2022–23 MPR, p. 48.

[188]Mr Chris Deeble, Defence, Committee Hansard, 24 April 2024, p. 2.

[189]Mr Chris Deeble, Defence, Committee Hansard, 24 April 2024, p. 2.

[190]Mr Chris Deeble, Defence, Committee Hansard, 24 April 2024, p. 2.

[191]Mr Chris Deeble, Defence, Committee Hansard, 24 April 2024, p. 2.

[192]ANAO, 2022–23 MPR, p. 27.

[193]ANAO, 2022–23 MPR, p. 25.

[194]JCPAA, Report 503, p. 12.