| 3.1 | 
    This chapter considers stages in the project  life-cycle under the RPP, and its  implications for the RLCIP. These stages include: applications, assessment,  decision-making on grants, project management and monitoring, and project  evaluation.  | 
  
  
    | 3.2 | 
    Under the RPP,  stake-holders experienced considerable frustration. Delays in assessment and  approval were cited as problematic, as were a lack of transparency and  certainty in connection with application approvals.1 In practice, delays and subsequent increases in cost threatened the viability  of projects.2 In  a more general sense, delays also reduced the degree to which the program was  seen as fair and above-board by applicants and associated parties.3        | 
  
  
    | 3.3 | 
    Similar concerns were expressed from an audit  perspective: the ANAO cited delays and project cost-increases as matters of  concern.4 Added to this were questions about the adequacy of DOTARS’ actions relating to due  diligence, financial management, and adherence to—and the adequacy of—departmental  procedures.5 There  have also been broader concerns about the relationship of political and  administrative processes under the RPP: one  example of which has been the timing of announcements for political rather than  administrative advantage.6        | 
  
  
     | 
      | 
  
  
    Applications | 
    
  
    | 3.4 | 
    The Committee heard that preparing an application  under the RPP represented a considerable  investment of resources, often entailing significant levels of unpaid work by  members of the applicant organisation.7 It also represented an investment of hope and expectation on the part of  regional communities, and in instances where the management of applications  fell below community expectations, particularly where they were unduly delayed,  this resulted in significant damage to morale.8        | 
  
  
    | 3.5 | 
    In some cases, delays have led to partners  withdrawing, so that projects have ceased to be viable.9 Together with considerable project-cost increases where outcomes have been delayed,  these factors underscore the importance of effective handling of applications  through the full program life-cycle.10        | 
  
  
     | 
      | 
  
  
    Making the application process easier | 
    
  
    | 3.6 | 
    A significant number of contributions to the inquiry  expressed dissatisfaction with the application process as it stood under the RPP.  A view commonly expressed in submissions and roundtable hearings was that application  forms were unduly complex and difficult to complete, and that this disadvantaged  applicants from less prosperous regional communities.11        | 
  
  
    | 3.7 | 
    It was suggested that the complexity of  application forms, and the application process in general, often made it  necessary to engage professional third parties to undertake the application  process, if there were to be any hope of a successful outcome.12 There was a perception on the part of some ACCs and applicants that DOTARS gave  undue emphasis to format and presentation in assessing applications.13 It was suggested that in practice this led to inequities: less well-to-do  regional communities had a smaller pool of local expertise to draw on, and were  therefore more in need of assistance from third parties, but were less able to  purchase it.14        | 
  
  
    | 3.8 | 
    Contributors to the inquiry were consistent in  the view that the application process for a future regional funding program  should be less complex than it was under the RPP.  However, it is necessary to weigh this perceived need to improve access against  the need to obtain good-quality information—particularly financial information—if  the DITRDLG is to fulfil its obligation to provide a good standard of management.   | 
  
  
    | 3.9 | 
    As noted above, under Financial Management Act  (FMA) Regulations, parties directly involved in delivering programs must take all  reasonable steps to ensure that good value for money is obtained for expenditure  from the public purse (FMA Regulation 9).15 This obliges agencies to perform due diligence in relation to grant applications,  which is to say that all reasonable steps be taken to acquire appropriate  financial and other information related to expenditure.16        | 
  
  
    | 3.10 | 
    For the former program, the ANAO consistently  found that too little information, of insufficient quality, was brought to bear  on applications, and that this had a negative effect on the Department’s  ability to discharge its obligations for good management.  | 
  
  
    | 3.11 | 
    With these considerations in mind, there are a  number of imperatives to be balanced. Reduced requirements for applications may  lower barriers to access, and may also reduce delays and program administration  costs. However, good standards of public administration for a grants program  require high-quality information about applicants and projects.   | 
  
  
    | 3.12 | 
    A suggested response from contributors to the inquiry  was to make the complexity of the application process, including the depth of  information required, commensurate with the amount of contribution sought from  the program, thus differentiating levels of risk to which the Commonwealth  would be exposed if funding were to be approved for smaller and larger grants.17 This is consistent with practice adopted by the former program in the latter  part of its life, during which different application processes, and  requirements for information, were set according to level of contribution  sought from the RPP.18         | 
  
  
    | 3.13 | 
    Consistent with this, contributors suggested  that there be different application forms and processes for applications  seeking different amounts of program contribution.19 A number of different thresholds were proposed for this purpose, including that  applications seeking less and more than $500,000 should be treated differently;  above and below $200,000, or $100,000; and, more commonly, that $50,000 of program  contribution be considered a significant point of differentiation.20         | 
  
  
    | 3.14 | 
    Others proposed two threshold points, so that three  streams would exist. One such model was that of the VicHealth program in Victoria,  which has a $10,000 ceiling for program contributions sought by small grants, a  range of $10,000 to $100,000 for middle-order grants, and an upper category for  applications which seek more than $100,000 from the program.21          | 
  
  
    | 3.15 | 
    The Committee agrees with proposals for  differentiating between grant applications on the basis of the amount of money  sought from the program. In the Committee’s view, this holds out the prospect  of increasing access to the program by applicants and rationalising administrative  work-loads, and management of risk, by applying a greater level of scrutiny  where projects involve a greater contribution from the federal government. The  Committee noted that this should result in an enhanced capacity by the DITRDLG to  process applications, and to perform other administrative processes associated  with the program, in a timely fashion.  | 
  
  
    | 3.16 | 
    Recommendation 13
      
      The Committee recommends that there be a sliding  scale of complexity for forms and of information requirements for applications,  commensurate with the level of contribution sought from the program, and thus  the level of risk to which the Commonwealth is exposed if the application is  approved.  | 
  
  
    | 3.17 | 
    Recommendation 14
      The Committee recommends that applications be  separated into three streams: those seeking less than $50,000 in contribution  from the program, those seeking between $50,000 and $250,000, and those seeking  more than $250,000.  | 
  
  
     | 
      | 
  
  
    Integration of state, local, and Commonwealth Government applications | 
    
  
    | 3.18 | 
    According to former applicants and RDA  representatives, further difficulties in the RPP  application process stemmed from differences in administrative settings in  different tiers of government: state, territory and federal.  | 
  
  
    | 3.19 | 
    With respect to applications, the Committee  heard that applicants were often obliged to invest considerable amounts of time  in order to conform to the formats and expectations imposed under grants schemes  in different tiers of government.22 This was a particular feature of the RPP because,  as a partnerships program, applications necessarily entailed synchronising  contributions from a variety of funding bodies, governments among them.        | 
  
  
    | 3.20 | 
    Differences in closing dates of grants programs  were noted as a special difficulty. Mismatches in round scheduling, for  example, could result in one jurisdiction requiring funds to be expended before  another was ready to disburse funds.23 Indeed, it has been suggested that one of the chief virtues of the open  application process employed under the RPP  was that it countered the influence of these differences, allowing greater  opportunities for synchronisation between the RPP  and other grant programs.24        | 
  
  
    | 3.21 | 
    Similar difficulties were identified for definitions,  by each tier of government, of the different geographical areas they define for  the purposes of program administration. Where these definitions are  significantly different, it imposes a further obstacle to applicants who wish  to establish funding combinations involving more than one layer of government.25        | 
  
  
    | 3.22 | 
    Contributors to the inquiry, such as program clients  and program facilitators, suggested ways to resolve these differences. It was  proposed that delineations of area for the purposes of a program work best when  they define ‘communities of interest’: where communities united by an area boundary  have sufficiently strong interests in common to allow effective planning and  administration.26 This proposal holds out the possibility that regions or areas could be defined  on the basis of comparatively objective criteria, on which local, state and  federal governments would be more likely to find agreement.         | 
  
  
    | 3.23 | 
    From the perspective of governments, however,  this may appear more difficult: constitutional distinctions between layers of  government are reflected in a history of distinct separation at a practical  level. Uniform processes may also be regarded, from a governmental point of  view, as similarly difficult to achieve.  | 
  
  
    | 3.24 | 
    Recognising both the significance of these  differences, and challenges in resolving them, the Committee proposes an  evolutionary approach toward harmonisation of regional boundaries and  administrative processes. The Committee proposes that if the state and  territory based assessment panels outlined in Recommendation 11 of this report  are adopted, that they be used as the vehicle through which to identify and  respond to differences between federal and other governments, which would  otherwise present undue obstacles to applicants and projects. This would allow  the new program to drive reform in this area, without obliging it to wait on change  from an external source.  | 
  
  
     | 
      | 
  
  
    Prescriptive process with understood timelines  | 
    
  
    | 3.25 | 
    Contributions to the inquiry attested to the  sense of uncertainty generated by variable time-lines under the former program,  a lack of known parameters in this regard, and resulting costs and other consequences.  An alternative is to create timelines for the application process—including  assessment, final decisions and notification, announcement and feedback—that  are binding on the DITRDLG, and clearly communicated to program clients.  | 
  
  
    | 3.26 | 
    Program design is implicated in this. The open  rounds format of the RPP, in which  applications were accepted at any time, is less well-suited to the  establishment of reliable time parameters for application assessment. Closed  rounds, in which applications are accepted within a certain window of time,  with the undertaking that a decision will be made by a particular date, provide  better support. Adopting this approach would allow this, and other dimensions  of program management, to be made more predictable. The issue of closed rounds  is discussed further below.  | 
  
  
     | 
      | 
  
  
    Assisting applicants | 
    
  
    | 3.27 | 
    Under the RPP,  the ACCs performed a range of functions. In general, they have been a point of  interface between the Commonwealth Government and regional communities, both  gathering and disseminating information. As former applicants to the program  have attested, ACCs often rendered considerable assistance and support to  applicants, having a better appreciation of the format and standard of  application required by DOTARS.27        | 
  
  
    | 3.28 | 
    The Committee notes that the role of RDA  is to be determined. One possibility is that its role will be largely of a  consultative nature, advising government on regional affairs rather than  directly assisting applicants to the new regional development scheme. This  would be consistent with the second option canvassed in Recommendation 8 of this  report. In Recommendation 9, administrative functions previously shared between  ACCs and DOTARS’ regional and central offices, would be performed by DITRDLG,  either in a central office, or by the DITRDLG field officers.   | 
  
  
    | 3.29 | 
    If the Government decides that the DITRDLG  should undertake the primary applicant assistance role (as recommended in  option two of Recommendation 8), the Department needs to ensure that sufficient  resources are put in place so that it can replace functions hitherto undertaken  by ACCs, and regional offices. A particular focus must be to assist proponents  with their applications. The Committee notes that the DITRLG would be obliged  to take deliberate measures to foster effective relationships between program  clients and program officers to ensure the new program’s success. Such measures  could include locating field officers within RDAs, local government or Commonwealth  Government programs located in regions, as is the case with AusIndustry or  AusTrade. The DITRDLG will also be obliged to guard against potential conflicts  of interest due to the application being developed and assessed by a single organisation.  | 
  
  
    | 3.30 | 
    Recommendation 15
    If the Government decides that the DITRDLG should  undertake the primary applicant assistance role (as recommended in option two  of Recommendation 8), the Committee recommends that DITRDLG build capacity and  staff expertise such that the Department is capable of acting as a single point  of contact for applicants, providing advice, feedback and application writing  and development capabilities with regard to the program.  | 
  
  
    | 3.31 | 
    Recommendation 16
    If the Government decides that the DITRDLG should undertake  the primary applicant assistance role (as recommended in option two of  Recommendation 8), the Committee recommends that the DITRDLG assign staff to  manage the program for particular regions, allowing them to develop and retain  that expertise with respect to those regions. Options are to: 
entrust  responsibility for particular regions to identified staff in the DITRDLG  central office; or
    
      entrust  responsibility for particular regions to identified DITRDLG field officers based  in regional areas. 28  | 
  
  
    | 3.32 | 
    Recommendation 17
    If the Government decides that the DITRDLG  should undertake the primary applicant assistance role (as recommended in  option two of Recommendation 8), the Committee recommends that the DITRDLG  provide resources such that there are sufficient staffing levels, and  sufficient staff travel to regions or staff located in regions, to allow  one-to-one support for applicants, including for application drafting, and  related matters such as engaging with prospective funding partners.  | 
  
  
     | 
      | 
  
  
    Paul   Neville MP – alternate comment
      Alternative Recommendation 16
      I recommend that the DITRDLG  assign staff to manage the program for particular regions, allowing them to  develop and retain that expertise with respect to those regions. It should: 
        - entrust  responsibility for particular regions to identified DITRDLG staff based in  regional areas; and
 
        - establish 13  small regional offices, 3 in Queensland, 3 in New South Wales, 2 in Victoria, 2 in Western Australia, and one each in the other States and Territories.
 
         | 
    
  
     | 
      | 
  
  
    Developing applications | 
    
  
    | 3.33 | 
    ACCs often performed an informal filtering role where  the application was considered unlikely to attract funding in its present form.29 Contributors to the Inquiry suggested that this reduced the cost of program  administration.30 However,  ACCs were not empowered to perform this function in a formal sense, and this left  them—and consequently the program—open to risk and uncertainty.31         | 
  
  
    | 3.34 | 
    The Committee also heard from the DITRDLG that  80 per cent of applications to the former program, whether they had been  through an ACC or not, were insufficiently developed to allow the assessment  process to begin on receipt of the application, and that this made a  significant contribution to the long assessment periods noted elsewhere in this  report.32        | 
  
  
    3.35  | 
    In the Committee’s view it would be beneficial  to clarify informal practices under the former program in this regard, so that formal  Expressions of Interest become a standard first step for all applicants.   | 
  
  
    | 3.36 | 
    In this proposed process, RDAs or departmental field  officers would work with proponents to develop Expressions of Interest to the  point where they can be accepted as fully-fledged applications under the  program. It is anticipated that such a process, in which a clear delineation is  made between application development and assessment, would reduce the length of  time needed for assessment, and improve the transparency of the application process  as a whole.  | 
  
  
    | 3.37 | 
    Recommendation 18
    The Committee recommends that for all applications,  Expressions of Interest are to be lodged with the program prior to applications  being lodged, and that:
- the  primary objective of the Expression of Interest process is to develop  applications;
 
- Expressions of Interest are to be accepted at any time of year;
 
- Expressions of Interest are to receive feedback and assistance sufficient to allow further  development of application, or to allow applicants to approach another, more  suitable program; and
 
     - Expressions  of Interest and feedback are to go on file, as part of the evidence upon which  assessments are made, for those projects which develop into applications.
 
   | 
  
  
     | 
      | 
  
  
    Open or closed funding rounds | 
    
  
    | 3.38 | 
    For non-profit projects, the former program  accepted applications at any time of year, regardless of the size of  contribution sought. Each application was assessed by DOTARS , which forwarded  applications with the results of that assessment attached as advice to  Ministerial decision-makers. Ministerial decision-makers then approved, or did  not approve, applications individually and at their discretion, rather than by  ranking them against a field of other applications.   | 
  
  
    | 3.39 | 
    It is thought that this combination of  arrangements made the program more difficult to administer, in that DOTARS was  unable to be certain about the weight or status accorded its advice.33 As noted, the doctrine of ministerial discretion over application approvals obliged  DOTARS to perform due diligence on all applications, regardless of merit, and  it proved unable to meet its obligations in this regard.         | 
  
  
    | 3.40 | 
    These elements of program design were problematic  for all parties involved in the process. Program clients were unable to be certain  about the parameters of the program, and this made writing applications  difficult, as it did their assessment by DOTARS.   | 
  
  
    | 3.41 | 
    A more common practice is for grants programs to  consider applications in a series of rounds, which open and close on nominated  dates. Applications for each round are then considered in a group, and ranked  according to program criteria. This is generally considered a more transparent  and reliable method of arriving at application approvals, in that the ranking  process provides a further layer of assessment, in combination with attention  to program criteria.34         | 
  
  
    | 3.42 | 
    There are other administrative benefits  attributed to funding rounds. Under this process the relationship to overall program  budget is more readily perceived, and there is a clearer perception of how much  is to be allocated at a given time. Because rounds entail processing of batches  of applications, timeliness is also better supported by this model.  | 
  
  
    | 3.43 | 
    Some elements of the former program were better  supported by the open applications process. As noted, one important attribute  was that it compensated, to a degree, for differences in closing and acquittal  dates employed by funding agencies in the states and territories.35  Program clients also expressed positive views of being able to apply at any  time of year.36          | 
  
  
    | 3.44 | 
    The Committee takes the view that strong concern  over lack of timeliness under the former program, and about a lack of  transparency and certainty, warrant the adoption of a rounds process for grant  applications: a significant number of contributors to the inquiry indicated timeliness  as a primary concern.  | 
  
  
    | 3.45 | 
    The Committee accepts that some applications  take longer to process than others, due to the higher level of due diligence  and other preparatory work necessary where applications seek a higher level of  contribution from the program. With this in mind, the Committee proposes two  separate funding rounds for the application streams recommended above.  | 
  
  
    | 3.46 | 
    Recommendation 19
    The Committee recommends that regular, closed funding rounds  be adopted for all streams, specifically:
- three-monthly  rounds for less than $50,000; and
 
      - six-monthly  rounds for more than $50,000, including applications seeking a $50,000 -  $250,000 contribution from the program and those seeking more than $250,000.
 
   | 
  
  
     | 
      | 
  
  
    Paul   Neville MP – alternate  comment
      Alternative Recommendation 19
      I recommend that regular  closed funding rounds be adopted for all (except those for deprived regions and  larger grants above $500,000), namely: 
        - 3-monthly rounds  of grants to $50,000;
 
        - 6-monthly rounds  for applications seeking between $50,000 and $500,000;
 
   		- rolling round of $50,000 to $2.5 million for  deprived regions or declared areas within regions;
 
        - a rolling round  from $500,000 to $7.5 million for major projects; and
 
        - emergency grants  in exceptional circumstances to $500,000 on Ministerial direction and with a  3-month application completion provision.
         | 
    
  
    | 3.47 | 
    As noted above, the Committee acknowledges that the  adoption of closed competitive funding rounds for the program, without  harmonisation of application dates between federal and other jurisdictions,  presents problems for some partnership projects. The option of assessment panels  in each state and territory could be a vehicle through which federal  representatives, and those of the states and territories, will identify and  work to resolve problems in this regard (see discussion regarding state and  territory based assessment panels in Chapter 2). In addition to conducting a  process to harmonise these facets of state, territory and federal programs, it  is anticipated that Assessment Panel members would be in a position to  negotiate optimum time-frames for the funding of particular grant applications  to minimise the ill-effects of differences between programs.  | 
  
  
     | 
      | 
  
  
    Assessments  | 
    
  
    | 3.48 | 
    Contributions to the inquiry show that under the  former program the assessment process occasioned concern amongst a number of  participants. As noted, there were widespread perceptions that the period of  time from lodging an application to being notified of an outcome was excessive,  and that the process was both less transparent and less predictable than anticipated.37          | 
  
  
    | 3.49 | 
    It appears that for applicants there was a significant  disjunction between the experience of preparing an application and having it  assessed. Preparing an application involved a consultative, regionally-based  process where applicants worked in close cooperation with other local  organisations, particularly the local ACC and local government. Contributors to  the inquiry suggested that this process in itself was an important positive  effect of partnership grants schemes, in that it created new working  relationships, and consequently social capital, in regional areas.38          | 
  
  
    | 3.50 | 
    While the RPP  appears to have been designed, in part, to foster such outcomes, its assessment  process was not entirely consistent with them. While the partnership model in  the program acted as a valuable social catalyst, the process of assessment has,  in part, reduced the full benefits of this effect.  | 
  
  
     | 
      | 
  
  
    Assessment models | 
    
  
    | 3.51 | 
    By contrast, Regional Development Victoria  employs a similar, but more thorough model which keeps the process closer to  regional stake-holders. In this model, departmental officers work closely with potential  aspiring applicants to the program, acting as facilitators, among other things,  to support the application process.39 RDV officers foster partnerships, identify opportunities, encourage applicants  to initiate projects, and provide feedback on applications.40 There is no formal Expression of Interest process,41 but through its close involvement with applications from their inception, RDV  is able to filter applications effectively.42  
       | 
  
  
    | 3.52 | 
    Responses to applications are made in considerably  shorter time-frames than for the RPP: in as  little as two-weeks, despite the program’s open application process.43 This provided considerable benefits in ensuring that applications did not go out  of date while being considered for funding.44 
       | 
  
  
    | 3.53 | 
    In essence, this approach combines, under program  management, the components that were separated under the RPP,  where facilitation was done at arm’s length by ACCs, then assessed by DOTARS.   | 
  
  
    | 3.54 | 
    Should the DITRDLG undertake the primary  assistance role (point 2, Recommendation 8), then the Committee is of the  belief that there would be clear benefits in integrating facilitation of  applications and assessment in the one department. Alternately, should RDAs be  tasked with assisting proponents (point 1, Recommendation 8), then the former RPP  model of ACC facilitation with DOTARS assessment, would have to be employed  again. In either case, sufficient resources will need to be allocated to the  DITRDLG in order for assessments to be performed effectively.  | 
  
  
    | 3.55 | 
    Recommendation 20
    The Committee recommends that the Regional and  Local Community Infrastructure Program be supported with sufficient resources  to allow the DITRDLG to assess applications effectively.  | 
  
  
     | 
      | 
  
  
    Assessment criteria | 
    
  
    | 3.56 | 
    Contributors to the inquiry have suggested that,  under the former program, it was difficult for applicants, ACCs, or even departmental  staff to establish a clear sense of assessment criteria. Rather, grant  applicants had the sense that ‘goal posts were being shifted’, and ACCs perceived  a need to ‘seek inside information’ to gain a sense of program priorities at  any given time. This situation, which appears to have been a product of  insufficient communication, combined with ways in which ministerial discretion  was exercised, is said to have contributed to perceptions of political bias in  the administration of the program.45 
       | 
  
  
    | 3.57 | 
    In the Committee’s view, this underscores the  importance of clear and effective dissemination of assessment criteria for the  new program, amongst applicants to the program and staff of the administering department.  Elsewhere this report recommends that where ministerial decision-makers diverge  from departmental advice on program applications, the reasons should be  recorded. As noted, this is consistent with the recommendations of the ANAO: that  reasons be recorded and that FMA Regulations be amended to make this a  mandatory requirement.46 
       | 
  
  
    | 3.58 | 
    Better definitions of key elements of the new program are a further means to avoid  some of the drawbacks of the RPP. A  key improvement in this respect depends on the clarifications of regional  plans, and their ownership, recommended in Chapter 2 of this report. There are  also further advances to be made by arriving at better definitions of other  elements of assessment criteria that were identified as problematic for the former  program. Each of these makes a contribution to the relative ease or difficulty  with which applications are approved. As applicants have told the inquiry, too  many unfavourable conditions amount to a filter that can be unduly difficult to  overcome.47 On  the other hand, clarification of such criteria can facilitate the drafting of  applications, and render them more likely to succeed.48 | 
  
  
     | 
      | 
  
  
    Partnership requirements | 
    
  
    | 3.59 | 
    As already noted, the partnership funding model  was an integral part of the former RPP. For  assessment criteria, this was expressed as the requirement that, for each  application considered, a particular proportion of project budget would be  provided by applicants and their partners, and a particular proportion by the program.   | 
  
  
    | 3.60 | 
    Although definitions varied over the life of the  program, in general the requirement for not-for-profit applications was that the  applicants and partners would contribute more than 50 per cent of project  budget.49 Requirements for for-profit applications were higher, but are not considered  here as this report does not recommend their inclusion in the future program. 
       | 
  
  
    | 3.61 | 
    Under the former program, applications that showed  applicants and their partners together contributing more than half of project  budget were in general rated more favourably.   | 
  
  
    | 3.62 | 
    Contributors to the Inquiry expressed concern  that these requirements could result in problems with equity. Less prosperous  regional communities were less likely to be able to provide money, as  applicants, or to find willing partners with the financial wherewithal to  contribute.50 
       | 
  
  
    | 3.63 | 
    Documentation for the RPP  specifically stated that economic circumstances could be grounds for waiving  strict application of the requirements for a certain proportion of the project  budget to come from applicants and partners.51 It is notable that although this was specifically indicated in written guidance  to assessors, there remained a perception amongst applicants that this  flexibility was not available under the program.52 
       | 
  
  
    | 3.64 | 
    This underscores the need for reliable  definitions and effective communication with stakeholders, for those circumstances  where partnership requirements may be modified. Applicants from regional areas  facing particular economic hardship are an important instance of this. This should  be characterised in formal terms, so that adaptations of this nature can be  made to program requirements without causing undue uncertainty.  | 
  
  
     | 
      | 
  
  
    Viability | 
    
  
    | 3.65 | 
    Under the former program, applicant and project  viability were both part of assessment considerations for projects. This  dimension of assessment proved to be a challenge for DOTARS. Due to an apparent  lack of financial expertise and capacity, the Department was unable to  generate, or to commission financial assessments from third parties, and in a  reliable way provide that as part of its advice to ministerial decision-makers.53  
       | 
  
  
    | 3.66 | 
    These challenges were particularly evident in  relation to for-profit applications. However, this report recommends that for-profit  applications no longer be accepted. This reduces, but does not remove, the  necessity for viability assessments for applicants and projects under the  scheme.  | 
  
  
    | 3.67 | 
    In view of shortfalls in capacity under the  former program, deliberate action must be taken by the Department managing the program  to ensure that sufficient, thorough viability and other financial analysis be  undertaken so that the Department can meet its due diligence obligations. | 
  
  
    | 
         3.68  | 
    The Committee acknowledges the challenges  involved in attracting and retaining staff with specialist skills in the  current labour market. The Committee proposes a combination of senior staff  skilled in these areas, to champion improved practice in this area, with  continued, more consistent use of third-parties to provide this technical analysis.  | 
  
  
    | 3.69 | 
    Recommendation 21
    The Committee recommends that the DITRDLG  increase its capacity to perform viability and other financial analysis on  applications lodged under the program, through a combination of senior  appointments requiring these skills, use of third-party providers, and training  for departmental staff.  | 
  
  
     | 
      | 
  
  
    Competitive neutrality       | 
    
  
    | 3.70 | 
    A further dimension of application criteria that  proved challenging, and at times confusing, for applicants were requirements relating  to so-called “competitive neutrality”. This term was used to indicate instances  where the funding of an application would provide the applicant with an undue  advantage over another provider of that good or service. This criterion was framed  with for-profit applications in mind, but has also been applied to  not-for-profit projects.54  
       | 
  
  
    | 3.71 | 
    In general, apparent disparities in requirements  caused considerable confusion amongst applicants, and competitive neutrality  appears to have been a particular instance of this. Some contributors to the inquiry  suggested that this criterion had been given undue weight in the RPP  process, and had made it difficult for applications in some areas of activity  to succeed.55 
       | 
  
  
    | 3.72 | 
    While there were a number of contributors who  raised concerns, few solutions were offered beyond relaxing the requirement. However,  one contributor to the inquiry argued that adopting a ‘fresh legislative policy’,  expressed as mild levels of reform, was the most efficient way to resolve these  problems.56 The Committee takes the view that this approach has merit and should be  investigated. 
       | 
  
  
    | 3.73 | 
    The Committee is also aware that there were  perceptions that the criteria for RPP was  constantly shifting.57 To avoid perceptions of changing criteria in the new program, the Committee is  of the opinion that criteria should be set for a defined period of time. 
       | 
  
  
    | 3.74 | 
    Recommendation 22
    The Committee recommends that the DITRDLG define  key assessment criteria in the clearest possible way, and act to ensure that  applicants and departmental staff are aware of these criteria. Criteria should  be set for a defined period of time.  | 
  
  
     | 
      | 
  
  
    Final decisions | 
    
  
    | 3.75 | 
    The way decisions were made under the former program  was a key part of its character. As noted, the full process saw applications  lodged after: development and an informal filtering process associated with  ACCs, followed by further processing by DOTARS’ regional-based officers and the  Department’s central office, together with any further financial analysis which  the Department commissioned from third-party providers. The process up to this  point resulted in advice which was attached to applications before they were put  before ministerial decision-makers for a final determination.  | 
  
  
     | 
      | 
  
  
    Ministerial discretion     | 
    
  
    | 3.76 | 
    This program design had a number of effects. First,  the nature of the involvement of Ministers in decision-making allowed Ministers  to have a direct impact on policy as it was expressed in the program. As noted  in the ANAO audit report on the program, this entailed ‘considerable’  decision-making flexibility for Ministers.58 
       | 
  
  
    | 3.77 | 
    This was part of an overall flexibility that has  been considered a strong point of the former program. On this basis, it could  support innovative projects, including those that would otherwise ‘fall between  stools’ because they involved more than one portfolio area.59 
      This flexibility was a key part of the program  from its inception, and did, in fact, allow the program to fund a variety of  project types.60 
     
     
       | 
  
  
    | 3.78 | 
    Some other consequences of ministerial  decision-making were less positive. A negative effect was that the nature of Ministers’  direct involvement in decisions over applications was seen as calling the  political neutrality of the program into question, and this affected the program’s  status in the eyes of stakeholders.61 The former government responded to these perceptions by creating a Ministerial  Committee to consider applications, with the object of improving transparency  and reducing time-lines for decision-making.62 It is unclear whether this change in design achieved either of its intended  effects.63 
       | 
  
  
    | 3.79 | 
    Another effect of Ministerial discretion, as it  was exercised under the former program, was that decisions were made at  variance with program guidelines, and with advice tendered by DOTARS.64 This contributed to a sense of uncertainty about the status of those guidelines,  and appears to have had a negative effect on compliance within DOTARS. The  consequences of this pattern of decision-making were increased because reasons  for these departures from guidelines and advice were often not recorded and  were not required to be recorded under current FMA Regulations. A number of the  recommendations of the ANAO Audit Report were framed to address this and  related matters.65 
       | 
  
  
    | 3.80 | 
    The funding of election commitments under RPP,  also a function of the program’s flexibility, was considered to have had a further  negative effect on both perceptions of the program and standards of public administration.  Representatives of the ANAO, appearing before the Committee, advised that there  were other avenues through which to fund election commitments, other than  through such programs, which do not produce the negative consequences seen when  the RPP was used for this purpose.66 
       | 
  
  
    | 3.81 | 
    In the Committee’s view, a constructive approach  to the new program is to maximise the benefits of the program’s flexibility  while reducing the risk this method of decision-making entails. This risk is  that, as under the former program, it could lead to a perception that program  administration falls below acceptable standards of public administration and  ministerial discretion.   | 
  
  
    | 3.82 | 
    There are still some outstanding issues relating  to the FMA Regulations and relevant sections of the ANAO report, which the  Committee intends to examine in further detail in its final report.  Nevertheless, the Committee endorses, and highlights the importance of, changes  to the FMA Regulations as recommended by the ANAO Audit Report—that Ministers (or  other approvers) be obliged under FMA Regulations to record ‘the basis on which  the approver is satisfied’ that expenditure ‘represents efficient and effective  use of the public money’ and ‘is in accordance with the relevant policies of  the Commonwealth’.67 The Committee understands that the Department of Finance is currently reviewing  regulations regarding the administration of government grants and will make  recommendations to the Commonwealth Government. 
       | 
  
  
    | 3.83 | 
    Changes to the FMA Regulations will also  reinforce Ministerial responsibility for the new program. For example, if  Ministers are required in the future to record the basis upon which they have  chosen to execute their duties under FMA Regulation 9 (expenditure represents  efficient and effective use of the public money), then any breaches of FMA Regulation  9 will be recorded and therefore subject to the penalties for offences against  the Regulations.  | 
  
  
    | 3.84 | 
    Recommendation 23
    The Committee endorses the recommendation of the ANAO that  Ministers (or other approvers) be obliged under FMA Regulations to record the  basis on which the approver is satisfied that expenditure represents efficient  and effective use of the public money and is in accordance with the relevant  policies of the Commonwealth. 
         
      The  Committee recommends that the review of the FMA Regulations be expedited so  that any changes are in place for the commencement of the new program.  | 
  
  
    | 3.85 | 
    The Committee notes negative consequences for program  administration where ministerial decision-makers make frequent departures from program  guidelines and departmental advice. However, ministerial decision-makers for the  former program also retained a role in ‘developing and approving Program  Guidelines’.68 In  the Committee’s view the consistent exercise of this power represents an avenue  through which Ministerial decision-makers can exercise discretion over  individual applications while informing, explicitly, both DITRDLG and  applicants of program as to current priorities and parameters. 
       | 
  
  
    | 3.86 | 
    Recommendation 24
    The Committee recommends that ministerial  decision-makers exercise discretion over applications, and shape program  guidelines and administrative arrangements to accurately reflect program  priorities.  | 
  
  
     | 
      | 
  
  
    Unsuccessful applications | 
    
  
    | 3.87 | 
    A number of contributors to the inquiry have  noted the lack of appropriate feedback processes for unsuccessful applications  in the RPP.69 A situation whereby applicants are unable to ascertain the basis upon which  their applications were unsuccessful may call into question the level of  transparency in a program.  
       | 
  
  
    | 3.88 | 
    In order to addresses this concern, the RLCIP should  have in place a process whereby unsuccessful applicants have the ability to ask  for a briefing or explanation from DITRDLG as to why their application was not  successful.  | 
  
  
     | 
      | 
  
  
    Monitoring and managing projects | 
    
  
    | 3.89 | 
    While much attention has been given to the  application and approval process in the former program, the ANAO Audit Report  found that there were important ways in which processes, after approvals were  made, could be improved. These included changes in ways Funding Agreements were  managed, the timing of payments, project management, and acquittals.  | 
  
  
    | 3.90 | 
    The ANAO found that DOTARS was not, under the  former program, always able to express the results of financial analysis, or  conditions imposed with respect to approvals in the terms of Funding Agreements.70 This was addressed in the Report’s Recommendations 1 and 9, to which DOTARS  agreed.71 
       | 
  
  
    | 3.91 | 
    For timing of payments, the ANAO found that the  timing of payments to projects were made in response to the federal budgetary  cycle rather than at times that would best fit for projects at their respective  stages of development.72 As a result, a high proportion of first instalments paid to proponents were 50  per cent or greater of the total program contribution, and this was not  considered the most efficient use of public money.73 
       | 
  
  
    | 3.92 | 
    The nature of project time-lines under the  former program was such that the program was both unable to expend all of its  appropriation and needed to seek approval from the Finance Minister to go  beyond its appropriation, in successive financial years, due to the need for  project payments needing to be entered against current appropriations.74 
       | 
  
  
    | 3.93 | 
    As for facilitation and assessment of  applications, the centralisation of functions in DITRDLG’s central office will make  it necessary for the Department to ensure that sufficient resources are devoted  to project management and monitoring functions. Despite some inquiry  participants’ view that project management performed by regional offices was  beneficial in ensuring that local circumstances were taken into account and  understood, it appears that these functions were not carried out to an adequate  standard by DOTARS’ regional offices, which had carriage of them under the  former program.75 The  new program will face similar challenges, and the Committee again notes the  need for adequate resourcing to address these requirements.  
       | 
  
  
    | 3.94 | 
    As for other administrative functions, there are  questions as to the degree to which project management functions can be  packaged together with other functions, for the sake of economy, and the degree  to which they require separation for the purposes of good public administration.  An effective balance needs to be established between these two imperatives.  | 
  
  
     | 
      | 
  
  
    The acquittal process | 
    
  
    | 3.95 | 
    The way acquittals were managed under the RPP  reduced DOTARS’ ability to ensure that expenditures were an efficient use of public  money. The ANAO found that DOTARS’ practice for the acquittals process fell  below good standards of administration in a number of respects, notably that  they were inconsistent, insufficiently thorough, and that they consequently  formed an inadequate basis for further decisions on project funding.76 The ANAO found that in a number of instances acquittals were either not  provided by proponents, or were provided with insufficient information, and  that DOTARS’ response had been inadequate.77  
       | 
  
  
    | 3.96 | 
    The Committee believes a better standard of  acquittals management is essential to the good administration and transparency  of the RLCIP. The DITRDLG will therefore be obliged to ensure that it can bring  sufficient expertise to bear on this issue, and to target its efforts in this  respect, so that better levels of administration may be achieved.  | 
  
  
    | 3.97 | 
    Regarding information required prior to approval  of projects, the level of information required for project acquittals should be  commensurate with the amount of program contribution and therefore risk carried  by the federal government.  | 
  
  
    | 3.98 | 
    In conclusion, the Committee wishes to note that  with regards to the acquittal process there are still some outstanding issues  which the Committee intends to examine in further detail in its final report.  | 
  
  
     | 
      | 
  
  
    Assessing project and program outcomes | 
    
  
    | 3.99 | 
    The report of the Senate inquiry into the former  program, and the ANAO report, both noted the connection between accurate  assessment of project outcomes and that of program outcomes: project management  tools can and should generate data that can be used to provide a basis on which  to consider the success of the program as a whole.78 | 
  
  
    | 3.100 | 
    Drafting of funding agreements provides an  opportunity to set agreed project targets, and the means by which these will be  verified. This clarifies targets for both proponent and funder, and creates a  test for project success. Under the former program, this was hampered by  inadequately framed and executed funding agreements—definitions were not written  into funding agreements in every case and, where they were, were not always  followed-up by DOTARS officers.79 This serves further to underscore the importance of the Department attracting  sufficient expertise and capacity to support the new program.       | 
  
  
    | 3.101 | 
    The Committee believes that the prescribed  details of a funding agreement are vital to assessing a project’s outcomes and  should be clearly defined within a funding agreement. This will avoid confusion  on the part of funding recipients as to expected outcomes. The Committee would  also like to see language within all funding agreements which specifies the  exact purpose of the funding received. Should a funding recipient fail to meet  objectives stipulated within a funding agreement and not use funding for its  intended purpose, this would constitute a breach of the agreement thereby  providing the Commonwealth with a measure of redress.  | 
  
  
    | 3.102 | 
    These are challenges of bottom-up data gathering  for program evaluation. However, the manner in which the former program’s  objectives were framed also presented top-down challenges in this regard.   | 
  
  
    | 3.103 | 
    The Senate Committee report into the program  criticised the form of program objectives on the grounds that they were not  sufficiently precise as to allow the program to be evaluated against its  objectives.80 Indeed,  an analysis of the former program’s Performance Indicators over its lifetime  suggests that they were not framed, to a sufficient degree, around an  overriding objective that would provide a test for its performance.81 
       | 
  
  
    | 3.104 | 
    In the Committee’s view, this suggests a need for  further policy development that would allow the new program to retain the broad  accessibility of its predecessor, in terms of the types of projects that will be  considered for funding, while providing a more precise overall objective for  the program.  
        
      
        Catherine King MP 
         
        Chair 
         
        November 2008 
        | 
  
  
    | 1  | 
     Mr Trevor, Wide Bay Burnett ACC, Official Committee Hansard, Toowoomba, Monday  21 July 2008, p.26; ACC – Illawarra, Submission  No.1, pp.3-4; Ms Dorn, BGT Employment, Official  Committee Hansard, Ballarat, Wednesday 6 August 2008, p.32.; Mr Mike Hyde,  Wingecarribee Shire Council, Submission  No.125, p.3; Mr Ian McPhee, Australian National Audit Office, Submission No.49, p.3. Back  | 
  
  
    | 2  | 
    Mr Russell, Central Murray ACC, Proof Committee Hansard, Shepparton,  Friday 8 August, 2008, p.31; Mr Marshall, Maningrida JET  Centre, Official Committee Hansard,  Darwin, Monday 28 July 2008, p.47;  Dr  John O'Brien, ACC - Hunter, Submission  No.104, p.7. Back | 
  
  
    | 3  | 
    Prof. Arlett, North  Queensland ACC, Official Committee  Hansard, Cairns, Friday 25 July, 2008, pp.20, 32; Mr Pollock, North  Queensland ACC, Official Committee  Hansard, Cairns, Friday 25 July, p.33. Back | 
  
  
    | 4  | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  pp.124-127, pp.316-318. Back | 
  
  
    | 5  | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  pp.112, 305, 390, 310-313, 316-318. Back | 
  
  
    | 6  | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  p.133. Back | 
  
  
    | 7  | 
    Mr Peter   O'Rourke, Shellharbour City Council, Submission No.123, p.3. Back | 
  
  
    | 8  | 
     Mr Peter   Couper, ACC - Melbourne East, Submission No.96, p.10. Back | 
  
  
    | 9  | 
    Dr John   O'Brien, ACC - Hunter, Submission No.104, p.14. Back | 
  
  
    | 10  | 
    Mr Ian   McPhee, Australian National Audit Office, Submission No.49, p.3. Back | 
  
  
    | 11  | 
    Mackay Region ACC Inc, Submission No.198, p.4; Mr Trevor, Wide Bay Burnett ACC, Official Committee Hansard, Toowoomba, Monday 21 July 2008, p.25; Mr  Keenan, Economic Development Australia, Proof  Committee Hansard, Shepparton, Friday 8 August 2008, p.8. Back | 
  
  
    | 12  | 
    ACC - Illawarra, Submission No.1, p.6; Ms  Mary Walsh, Wide Bay Burnett ACC,  Submission No.114, p.6; Mr Peter O'Rourke, Shellharbour City Council, Submission No.123, p.3. Back | 
  
  
    | 13  | 
    Mr Peter   O'Rourke, Shellharbour City Council, Submission No.123, p.3. Back | 
  
  
    | 14 | 
    Ms Mary   Walsh, Wide Bay Burnett ACC, Submission No.114, p.6. Back | 
  
  
    | 15 | 
    Australian National Audit Office (ANAO), Performance Audit of the Regional  Partnerships Programme: Volume 2, Report No. 14, 2007-08, pp.50-51. Back | 
  
  
    | 16 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  p.393. Back | 
  
  
    | 17 | 
    Mr Trevor, Wide Bay Burnett ACC, Official Committee Hansard, Toowoomba, Monday  21 July 2008, p.26; Ms Admans, Foundation for Rural & Regional Renewal, Official Committee Hansard, Ballarat, Wednesday,  6 August 2008, p.35. Back | 
  
  
    | 18 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  p.107. Back | 
  
  
    | 19 | 
    Mr Russell, Central Murray ACC, Proof Committee Hansard, Shepparton,  Friday 8 August 2008, p.16; Clr McLean, Central Victoria ACC, Official Committee Hansard, Ballarat, Wednesday,  6 August 2008, p.17. Back | 
  
  
    | 20 | 
    Mr Iaccarino, Melbourne’s North & West  ACC, Official Committee Hansard,  Ballarat, Wednesday, 6 August 2008, p.16; Mr Buckley, Regional Cities Victoria, Proof Committee Hansard, Shepparton,  Friday 8 August 2008, p.40; Mr Keenan, Economic Development Australia, Proof Committee Hansard, Shepparton,  Friday 8 August 2008, p.20; Ms Dorn, BGT Employment, Official Committee Hansard, Ballarat, Wednesday 6 August 2008,  p.50; Clr McLean, Central Victoria ACC, Official  Committee Hansard, Ballarat, Wednesday 6 August 2008, p.17. Back | 
  
  
    | 21 | 
    Ms McCann,  Melbourne East   ACC, Official Committee  Hansard, Ballarat, Wednesday 6   August 2008, p.37. Back | 
  
  
    | 22 | 
    Mr Buckley, Regional Cities Victoria, Proof Committee Hansard, Shepparton,  Friday 8 August 2008, p.32; Mr Ray Hortle, ACC - Albury Wodonga, Submission No.188, p.11; Mr Crouch, Sunraysia  ACC, Proof Committee Hansard, Shepparton,  Friday 8 August 2008, p.29. Back | 
  
  
    | 23 | 
    Mr Crouch,  Sunraysia ACC, Proof Committee Hansard, Shepparton, Friday 8 August 2008, p.29. Back | 
  
  
    | 24 | 
    Ms Linley,  Regional Development Victoria, Official  Committee Hansard, Ballarat, Wednesday   6 August 2008, p.40. Back | 
  
  
    | 25 | 
    Mr Ferrie,  Department of Planning & Community Development (VIC), Official Committee Hansard, Ballarat, Wednesday 6 August 2008, p.25. Back | 
  
  
    | 26 | 
    Mr Iaccarino,  Melbourne’s North  & West ACC, Official Committee  Hansard, Ballarat, Wednesday 6   August 2008, p.16. Back | 
  
  
    | 27 | 
    Mr Nick   Machan, Tulgeen Disability Services, Submission No.106, p.1; Ms Jean Brewer, PERFEX Working Group, Submission No.136, p.2. Back | 
  
  
    | 28 | 
    An example of this exists in Victoria  where single regional field officers are located in each of the State’s regions  with the job of assisting applicants to access state government programs and  work up applications to the Regional Development Infrastructure Fund. Back | 
  
  
    | 29 | 
    Mr Crouch, Sunraysia ACC, Proof Committee Hansard, Shepparton,  Friday 8 August 2008, p.24; Mr Eastoe, Albury Wodonga ACC, Proof Committee Hansard, Shepparton, Friday 8 August 2008, p.30. Back | 
  
  
    | 30 | 
    Mr Trevor,  Wide Bay Burnett ACC, Official Committee  Hansard, Toowoomba, Monday, 21   July 2008, p.19. Back | 
  
  
    | 31 | 
    Mr Crouch,  Sunraysia ACC, Proof Committee Hansard, Shepparton, Friday 8 August 2008, p.24. Back | 
  
  
    | 32 | 
    Mr Angley,  DITRDLG, Proof Committee Hansard, Canberra,  Monday 13 October 2008, pp.32-33. Back | 
  
  
    | 33 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  pp.84-85, 447-448. Back | 
  
  
    | 34 | 
     ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  pp.189, 386. Back | 
  
  
    | 35 | 
    Ms Linley,  Regional Development Victoria, Official  Committee Hansard, Ballarat, Wednesday   6 August 2008, p.40. Back | 
  
  
    | 36 | 
    Mr Budge, Official Committee Hansard, Ballarat,  Wednesday 6 August 2008,  p.42. Back | 
  
  
    | 37 | 
    Mr Trevor, Wide Bay Burnett ACC, Official Committee Hansard, Toowoomba, Monday  21 July 2008, p.19.; Mr Xynias, Greater Brisbane ACC, Official Committee Hansard, Toowoomba, Monday 21 July 2008, p.55; Mr  Russell, Central Murray ACC, Proof  Committee Hansard, Shepparton, Friday 8 August 2008, p.31. Back | 
  
  
    | 38 | 
    Ms McCann, Melbourne East ACC, Official Committee Hansard, Ballarat,  Wednesday 6 August 2008, pp.29, 45. Back | 
  
  
    | 39 | 
    Mr Budge, Official Committee Hansard,  Wednesday, Ballarat, 6 August 2008,  p.18. Back | 
  
  
    | 40 | 
    Mr Sharp,  Regional Cities Victoria, Proof Committee Hansard, Shepparton, Friday 8 August 2008, p.31. Back | 
  
  
    | 41 | 
    Mr Budge, Official Committee Hansard, Ballarat,  6 August 2008, p.18. Back | 
  
  
    | 42 | 
    Mr Sharp,  Regional Cities Victoria, Proof Committee Hansard, Shepparton, Friday 8 August 2008, p.23. Back | 
  
  
    | 43 | 
    Mr Budge, Official Committee Hansard, Ballarat, Wednesday 6 August 2008,  p.42; Ms Linley, Official Committee  Hansard, Ballarat, Wednesday 6 August 2008, p.40. Back | 
  
  
    | 44 | 
    Mr Budge, Official Committee Hansard, Ballarat,  Wednesday 6 August 2008,  p.42. Back | 
  
  
    | 45 | 
     ACC - Illawarra, Submission No.1, p.2. Back | 
  
  
    | 46 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  pp.90-92, 93. Back | 
  
  
    | 47 | 
    Ms McCann,  Melbourne East   ACC, Official Committee  Hansard, Ballarat, Wednesday 6   August 2008, p.29. Back | 
  
  
    | 48 | 
    Ms Lewis,  Southern Inland Queensland ACC, Official  Committee Hansard, Toowoomba, Monday   21 July 2008, p.59. Back | 
  
  
    | 49 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  pp.265-266. Back | 
  
  
    | 50 | 
    Cr   O’Brien, Murweh Shire Council, Official Committee Hansard, Toowoomba, Monday 21 July 2008, p.15. Back | 
  
  
    | 51 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  p.265. Back | 
  
  
    | 52 | 
    Cr   O’Brien, Murweh Shire Council, Official Committee Hansard, Toowoomba, Monday, 21 July 2008, p.15. Back | 
  
  
    | 53 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  p.447. Back | 
  
  
    | 54 | 
    Mr Iaccarino,  Melbourne’s North  & West ACC, Official Committee  Hansard, Ballarat, Wednesday 6   August 2008, p.36. Back | 
  
  
    | 55 | 
    Mr English, Orana ACC, Official Committee Hansard, Dubbo, Tuesday  12 August 2008, p.51 ; Ms Bentick, Central NSW ACC, Official Committee Hansard, Dubbo, Tuesday 12 August 2008,  pp.51-52; Mr Clements, Gowest Regional Development Fund, Official Committee Hansard, Dubbo, Tuesday 12 August 2008,  pp.52-53. Back | 
  
  
    | 56 | 
    Mr Clements,  Gowest Regional Development Fund, Official  Committee Hansard, Dubbo, Tuesday   12 August 2008, pp.52-53. Back | 
  
  
    | 57 | 
    Ms Lewis,  Southern Inland Queensland ACC, Official  Committee Hansard, Toowoomba,  Monday  21 July 2008, p.59; Illawarra Area Consultative Committee, Submission no.1, p.2. Back | 
  
  
    | 58 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  p.387. Back | 
  
  
    | 59 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  pp.12, 14, 33; Mr Ian   McPhee, ANAO, Submission No.49, p.1. Back | 
  
  
    | 60 | 
    Dr Stone MP, Offical Committee Hansard, Ballarat, Wednesday 6 August 2008, p.25;  Mr Hansen, Official Committee Hansard, Ballarat, Wednesday 6 August 2008, p.52. Back | 
  
  
    | 61 | 
    Mr Graham, Mount Isa Townsville Economic  Zone, Official Committee Hansard,  Cairns, Friday 25 July 2008, p.37; Mr Wallace, Northern Tasmania Development, Official Committee Hansard, Launceston, Monday  4 August 2008, p.5. Back | 
  
  
    | 62 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  pp.39-40 & ff. Back | 
  
  
    | 63 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  Figure 2:3:2, p.104. Back | 
  
  
    | 64 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  pp.75-76, 77 & ff. Back | 
  
  
    | 65 | 
    See ANAO, Performance Audit of the Regional Partnerships Programme: Volume 2,  Report No. 14, 2007-08, pp.82-91, and Recommendations 2, 6 & 7, pp.93,  183, & 190. Back | 
  
  
    | 66 | 
    Mr McPhee  and Mr Boyd,  ANAO, Proof Committee Hansard, Canberra,  Monday 13 October 2008,  pp.28-29. Back | 
  
  
    | 67 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  p.93. Back  | 
  
  
    | 68 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  p.15. Back | 
  
  
    | 69 | 
    Centroc, Submission No. 139, p.6; Mid West Gascoyne Area Consultative  Committee, Submission No. 22, p.12;  Melbourne East Area Consultative Committee, Submission  No.96, pp.8-9. Back | 
  
  
    | 70 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  pp.55, 58-59, 255, 330-331. Back | 
  
  
    | 71 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  Recommendations 1 & 9, pp.59, 257. Back | 
  
  
    | 72 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  pp.510-11, 513, 516-527. Back | 
  
  
    | 73 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  Figure 5:2.4, p.513. Back | 
  
  
    | 74 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  pp.50, 54-57. Back  | 
  
  
    | 75 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  pp.578-579 ff, pp.590-591, 595. Back | 
  
  
    | 76 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14,  2007-2008, pp.308, 355, 509. Back | 
  
  
    | 77 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 3, Report No. 14,  2007-2008, pp.35, 79, 106. Back | 
  
  
    | 78 | 
    Senate Committee Report, Finance and  Public Administration References Committee, Regional  Partnerships and Sustainable Regions programs, October 2005, p.39, cited in  ANAO, Performance Audit of the Regional  Partnerships Programme: Volume 2, Report No. 14, 2007-08, pp.613-614. Back | 
  
  
    | 79 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  pp.602-610. Back | 
  
  
    | 80 | 
    Senate Committee Report, Finance and  Public Administration References Committee, Regional  Partnerships and Sustainable Regions programs, October 2005, p.93, cited in  ANAO, Performance Audit of the Regional  Partnerships Programme: Volume 2, Report No. 14, 2007-08, p.493. Back | 
  
  
    | 81 | 
    ANAO, Performance  Audit of the Regional Partnerships Programme: Volume 2, Report No. 14, 2007-08,  Table 5:1.1, p.492. Back |