2.1
Chapter 2 provides a brief outline of the elements influencing the
supply of, and demand for, water in South East Queensland (SEQ). This chapter also
provides the demand projections utilised by the Queensland Government and outlines
some of the major reports and research undertaken by the Queensland Government.
At the conclusion of this chapter, the initiatives which are being implemented or
have been identified for consideration to address water shortages and secure
future supply are listed, and the government agencies and authorities who have
roles and responsibilities in developing infrastructure and the delivery of water
supplies to SEQ are identified.
Introduction
2.2
SEQ as a region is experiencing the compound effects of the worst
drought in more than 100 years, a booming residential population and the
prospect of continuing irregular rainfall due to natural climate variability
and long-term climate change.[1]
Existing water supplies previously thought to be long-term and secure are currently
at or have recently been at record lows. For example, inflows to the major dam
systems in 2006, the Wivenhoe, Somerset and North Pine, are the lowest on
record and these systems were at 20.5 per cent of capacity in April 2007.[2]
The drought has exposed the vulnerability of the region's water supplies and
the fact that SEQ is experiencing huge population growth to the amount of
50,000–60,000 people per annum is increasing the water demand in an already
stretched system.[3]
2.3
Level 5 water restrictions were introduced in SEQ on 10 April 2007, as dam capacities dropped below 20 per cent. Water restrictions
apply to households as well as businesses, industries and government agencies,
and these restrictions now also address water use by some power stations and
licensed irrigators. The Queensland Government will also focus on household
water efficiency through a high volume water usage audit.[4]
2.4
The Queensland Water Commission have stated that SEQ residential water
consumption has already reduced from a pre-restrictions level of approximately
300 litres per person per day to approximately 180 litres per person per day
under level 4 water restrictions.[5]
The 'Target 140 campaign', a coordinated education and awareness program, focusing
on achieving a regional average target of 140 litres per person per day has
been implemented. The campaign has the potential to deliver significant water
savings and influence a more sustainable post-drought level of residential
water consumption.[6]
Mr Ken Smith, Director General, Department of Infrastructure, Queensland
indicated that people living in Queensland have responded well to the current
water crisis and requests for a decrease in residential water usage:
The community are responding marvellously. To get the level down,
we had a target of 140 litres. People have got down to 147 litres, which...is the
lowest level of average utilisation per person of any urban city in Australia—probably
around the world, really.[7]
Existing water supplies
2.5
SEQ has 19 major urban surface water storages with a diverse ownership
of 12 separate proprietors including: SEQWater, Sunwater, local governments and
a local government cooperative.[8]
The Queensland Government is working cooperatively with local governments to
implement drought contingency projects and ensure the security of the water supply.
Water Resource Plans (WRP) have recently been finalised for catchments in the
SEQ region. These plans define the balance between water to be available for
consumption and water to be available for environmental purposes.[9]
The Queensland Government explained the importance of WRPs when considering alternative
water supply options, and stated that:
WRPs are developed through detailed technical and scientific
assessment as well as extensive community consultation to determine the right
balance between competing requirements for water...When comparing various supply
sources, the restrictions imposed on supply sources by WRPs must be considered.
Hence, it may be that a particular water source may be favourable in an
economic and financial sense but cannot demonstrate compliance with the
relevant WRP.[10]
2.6
The Queensland Government indicated that while the total supply from the
major urban water sources in SEQ is 636,000 megalitres per annum (ML/a), not
all of this supply is actually available for consumption in SEQ as historical
no failure yield amounts for some water sources have been downgraded due to the
drought. The total available supply in the region is only 528,259 ML/a.[11]
Water demand projections
2.7
The Queensland Government provided extensive information detailing urban
and industrial water demand projections and highlighted that numerous
assumptions underpin these forecasts, such as the accuracy of population
projections, the assumed uptake or penetration rates of non-mandatory water
efficiency opportunities and the achievement of predicted rainwater tank
yields.[12]
The Queensland Government stated that:
Unrestricted existing urban and industrial water demands are
about 480,000 ML/a. The early implementation of water use efficiency and
customer side source substitution measures is likely to reduce SEQ urban and
industrial demand projections by about 30,000 ML/a. SEQ water demands are
anticipated to be about 520,000 ML/a in 2026 and 710,000 ML/a in 2051. If high series
population projections eventuate, the equivalent 2026 and 2051 demands are
590,000 and 1,100,000 ML/a.[13]
2.8
On the basis of the supply/demand gap analysis undertaken by the
Queensland Government between 540,000 and 720,000 ML/a will need to be provided
to satisfy projected 'business as usual' demand by around 2051 and between
150,000 and 200,000 ML/a of contingency will need to be identified and
pre-planned.[14]
2.9
The committee received a report titled Review of Water Supply-Demand
Options for South East Queensland – Final Report (the Review Report) which
questioned the Queensland Government's demand projection figures.[15]
The Review Report made the following comments:
The assumptions [regarding the level of restrictions (frequency,
depth, duration)] now being used are very conservative, and differ
significantly from standards that apply in comparable cities. In addition there
is no clear evidence that these changes have been based on any surveys or
community engagement processes to determine what is deemed acceptable to the
community.
...
The figure of 300 litres per capita per day being used for [business-as-usual]
projections is significantly higher than the demand in comparable eastern
seaboard capital cities. This projection being used to forecast to 2050 is
therefore likely to be a significant overestimate, as it does not adequately
take into consideration expected downward pressure on water demand due to
changes in land use (urban consolidation and the shift to more flats and units
with the associated reduction in lawn and garden area) and the improving
efficiency of water using equipment such as dual flush toilets and washing
machines.
The Queensland Government estimate of the supply-demand gap is
considered to be extreme and unjustified. The combination of these projections
of reduced yield and elevated demand has implications for the supply-demand
balance in 2050 of several hundred billion litres per year (GL/a).[16]
2.10
Mr John Bradley, CEO, Queensland Water Commission responded to the comments
made in the Review Report on demand projections and stated:
There are some significant errors in that analysis which raise
concerns about the conclusions that it draws, particularly around its
assessment of base line demand. They questioned the use within the SEQ regional
water supply strategy study of 300 litres per person per day and said that that
is excessive. They said that on the basis of interstate comparisons rather than
a substantiated analysis of demand. What we have done within the SEQ regional
water supply strategy over a long period is the largest study ever undertaken
of demand management trends, using very sophisticated analysis undertaken by
Montgomery Watson Hauser to assess our demand trends and the achievable savings
we can make in demand management. It is because of this difference in opinion
on demand management that Professor White came to a very different conclusion.[17]
Water allocations and the price of
water
2.11
The Queensland Government do not have pricing signals in their water
market. When questioned on their view of pricing signals, Mr Ken Smith,
Department of Infrastructure, Queensland, commented on a report released by the
Queensland Water Commission on pricing issues and stated that in that report
'there is a proposal with respect to both the wholesale price of water and the
impact on the retail price of water'.[18]
Mr Bradley also commented that 'the government has made an early response to
the commission's report indicating that they would be prepared to accept lower
rates of return on the drought infrastructure in order to minimise price shock
for the community'.[19]
2.12
The Queensland Government provided some evidence on the number of water
licences allocated in SEQ incorporating both sleepers and dozers (unused or
little used allocations). In their modelling, the Queensland Government have
assumed that all licences are being utilised and have identified that the next
step would be further consultations to quantify actual use. Mr Graeme Newton, CEO,
Queensland Water Infrastructure Pty Ltd (QWI), commented 'the reality is that
they [sleepers' and dozers' licences] are not all being used, but the quantum
is not yet defined because it is actually quite a thorough consultation
process'.[20]
Queensland Government
2.13
The Queensland Government has over many years conducted studies and
developed strategies and plans incorporating the region of SEQ, which identify
initiatives to secure water supplies for the region. This section provides
comments on studies, reports and initiatives that have been discussed at length
in evidence and have been identified as particularly relevant to the water
issues experienced in SEQ. Further information can be found in the Queensland
Government's submission and supporting documents provided to the inquiry.
Government studies and reports
2.14
The Queensland Government provided a number of reports and additional
information to the committee as evidence. The full reference details for the
reports referred to in this report are available in Appendix 3.
2.15
Two past reports, one titled SEQ Sources Study published in 1991
and the second report titled The SEQ and Water and Wastewater Management and
Infrastructure Study – Final Report for Phase 1 – Water Sources and
Infrastructure Needs – April 1999 noted that the Wyaralong Dam and the
Borumba Dam sites have been identified as alternative supply sources and have
been considered for development at various times.
2.16
A report produced in 1994 titled The Water Supply Sources for
the Sunshine Coast and the Mary River Valley identified that the Traveston Crossing
Dam on the Mary River did not warrant further investigation as a water supply
source. The report stated the following reasons '[e]xtensive alluvial flood
plain on right bank. Cost for dam updated from 1977 is $125 million. Damsite
considered unsuitable because of high capital cost, inundation of prime
agricultural land and displacement of rural population'.[21]
2.17
The SEQ Regional Water Supply Strategy – Stage 2 Interim Report was
released in January 2006 and outlined the approach needed to ensure water
supplies meet the short and medium-term water needs. It also provided details
of short-term priority projects and contingency planning initiatives to be commenced
in the period 2005–2009, and provides a commitment to medium-term (2010–2020) and
possible long-term (2021–2051) initiatives. Mr David Gibson, Member for Gympie,
commented on the absence of consideration of the Traveston Crossing Dam initiative
in this report:
...with regard to the South East Queensland Regional Water Supply
Strategy—the government was very clearly and very openly talking about a weir
on the Mary River at Coles Crossing... They reinforced that on 7 April with
another ministerial statement saying that they would proceed with that weir. On
20 April we have both the minister at the time and the Premier committing to
the South East Queensland Regional Water Supply Strategy which talks about a
weir. Seven days later, they talked about a dam—a mega dam is how they
addressed it—on the Mary River. The people of this electorate were
understandably very confused and incredibly frustrated at the information that
became available. Why was there a change from a two-year report that the
government commissioned to determine what were the best water supply strategies
to then suddenly—within seven days—appear to disregard that report?[22]
2.18
The report titled SEQ Regional Water Supply Strategy - Desk
Top Review of Identified Dam and Weir Sites - Report to the Bulk Supply
Infrastructure Task Group (the GHD report) was released in June 2006. This
report was commissioned by the Queensland Government and prepared by consultants
GHD Pty Ltd (GHD) who were asked to conduct a desktop review of existing
reports and data and publicly available information regarding dam and weir sites
that had previously been identified in the region.[23]
In preparing this report, GHD were specifically asked to:
- make recommendations regarding those sites that did not warrant
further consideration; and
- identify any shortfalls in available information that had the
potential to impact on the viability of a particular development.
Legislative amendments
2.19
The Water Amendment Regulation (No.6) 2006 (Qld) was made as a
response to the worst drought on record and aimed to expedite the coordinated
delivery of initiatives and projects. The Queensland Government explained the
intention of the amendment:
To ensure adequate supplies are maintained, the Queensland
Government is working with QWC, SEQWater, SunWater and SEQ councils to develop
and implement the large range of emergency projects and other drought
contingency measures detailed in the Water Amendment Regulation (No. 6) 2006.
These emergency projects and other measures (such as water restrictions) are
collectively designed to ensure ongoing water supply in the event that the
current drought continues.
The Water Amendment Regulation (No.6) 2006 provides a
coordinated set of actions to be undertaken by a number of State and local
government entities and provides details on project measures, outcomes,
timelines and target water volumes to be achieved.
Service providers develop monthly progress reports on their
projects for publication on the QWC website.[24]
2.20
The Queensland Government confirmed that a range of projects that QWI
are responsible for are included in the regulation. Mr Ken Smith stated '[a]s
you know, it was not just Traveston; it was a range of projects that QWI are
responsible for...All the ones we are talking about were in it: Wyaralong, Cedar
Grove Weir. There is a range of projects that were part of that'.[25]
2.21
Many witnesses and submitters questioned whether the Traveston Crossing Dam
initiative should be included in this regulation, given that Stage 1 of the
initiative will not be operating until 2011.[26]
Professor Stuart White, Director of the Institute of Sustainable Futures and
one of the authors of the Review Report commented:
...the Traveston Dam is not designed to solve the current drought.
This is an extremely important point...Unfortunately I am not sure that that
understanding is shared within the wider south-east Queensland community, and
it is extremely important in assessing this dam. This dam must be assessed on
its contribution to the medium to long-term supply demand balance for
south-east Queensland, not on its ability to solve the current drought. This is
despite the fact that it is included in the emergency legislation as if it were
part of that drought response package, which, as many of you realise, is quite
anomalous.[27]
2.22
The Queensland Government explained the reasoning for including the Traveston
Crossing Dam in the regulation, and stated:
The reason for including Traveston Crossing Dam and other
projects such as Wyaralong Dam and Hinze Dam Stage 3 in the Regulation was to
include a comprehensive enunciation of the short and medium term priorities of
the Queensland Government in achieving water security in SEQ and to indicate
the responsibilities of all water service providers and the State.[28]
Demand and supply initiatives
2.23
The Queensland Government has stated that 'a single solution to the
long-term water needs of SEQ does not exist' and is therefore instituting a
Water Grid which adopts a multi-faceted approach to meet future water demands.
This approach includes demand site management and the diversification of supply
sources, comprising dams and weirs, desalination, recycling and ground water
sources.
2.24
A range of demand management initiatives will be implemented by the
Queensland Government to target business and industry as well as residents with
rebate schemes and incentive programs. The offer of subsidies to local
governments has been expanded to accelerate the implementation of pressure and
leakage management programs.[29]
2.25
The Queensland Government identified the main bulk supply options to
meet the projected demands in SEQ as:
- additional ground water supplies;
- desalination;
- recycling; and
- new dams and weirs.[30]
2.26
The diversification of supply sources combined with a significant
infrastructure investment program provide the following water supply initiatives:
- Western Corridor Recycled Water Project;
- SEQ (Gold Coast) Desalination Project;
- Southern Regional Water Pipeline;
- Northern Pipeline Interconnector;
- Eastern Pipeline Interconnector;
- Cedar Grove Weir;
- Bromelton Offstream Storage;
- Wyaralong Dam; and
- Traveston Crossing Dam.
2.27
More detailed information on each of the initiatives listed above is
available at Appendix 4. The majority of evidence the committee received was in
relation to the Traveston Crossing Dam and the Wyaralong Dam, and these two
initiatives are discussed in further detail in chapters 3, 4, and 5.
State government roles and
responsibilities
2.28
The Queensland Government, through different agencies and authorities,
performs a number of roles and responsibilities in progressing proposed infrastructure
and water projects. Full details of relevant agencies and authorities are
available in the Queensland Government's submission.[31]
However, a brief outline of the major state government agencies and authorities
is given below:
- Department of Natural Resources and Water (DNRW) - administers
the Water Act 2000 (Qld), which puts in place the overall legislative and
institutional framework for the sustainable planning, allocation and use of
water. DNRW also provides ongoing advisory input and audits the results of the
substantial hydrological modelling exercises associated with the Environmental Impact
Statement (EIS) and the subsequent granting of a Resource Operations Licence (ROL).
- Queensland Water Corporation (QWC) - an independent,
statutory authority responsible for planning and achieving safe, secure and
sustainable water supplies in SEQ and other designated regions. The QWC is
currently completing a long-term water strategy to guide the region’s water initiatives
in conjunction with state and local governments.
- Coordinator General (CG) - the manager, coordinator and
key state decision maker in relation to the impact assessment process of any
major water storage proposal.
- Environment Protection Agency (EPA) - responsible for
protecting Queensland’s natural and cultural heritage, and promoting
sustainable use of its natural capital and ensuring a clean environment. The EPA
plays a key role in assisting the Coordinator General to assess the impacts of
a water storage proposal and develop strategies to suitably mitigate such impacts
on identified environmental values.
- Department of Primary Industries and Fisheries (DPIF) - strives
to ensure Queensland's primary industries and fisheries support sustainable
production systems and use best practice in water management and water allocation,
vegetation and pest management, and chemical use.
- Community Futures Taskforce (CFTF) - established to work
with communities affected by the proposed dams. The CFTF is chaired by
Major-General Peter Arnison, former Governor of Queensland. Comprising relevant
state agencies and representatives of councils, the CFTF is developing strategies
to maximise the medium to long-term opportunities presented by the development.
- Queensland Water Infrastructure (QWI) - a company incorporated
on 28 June 2006 pursuant to the Corporations Act 2001 (Cth)
and whose shares are wholly owned by the State of Queensland. QWI is the
proponent for the proposed Traveston Crossing Dam project, the Wyaralong Dam,
the Cedar Grove Weir and the Bromelton Offstream Storage. QWI was established
by the Queensland Government with the objectives of investigating, obtaining
all relevant approvals and constructing and operating a number of water infrastructure
projects in SEQ.
Conclusion
2.29
The region of SEQ is facing challenges in balancing the demand for, and
supply of water for urban, industrial and irrigation purposes. Through much analysis
and research, the Queensland Government have identified a range of initiatives
for implementation; some of which are currently in place and others which
represent long-term solutions. The fact that SEQ is experiencing a large rate
of population growth during an extended time of drought and rainfall
variability means that the Queensland Government needs to consider carefully
the implications of these planned initiatives, both present and future, when
endeavouring to meet the water supply requirements of the SEQ region.
Navigation: Previous Page | Contents | Next Page

Website feedback: web.senate@aph.gov.au
Last reviewed 16 August 2007 by the Senate Web Administrator
© Commonwealth of Australia
Parliament of Australia Web Site Privacy Statement
Images courtesy of AUSPIC
|