 |
Research Paper no. 1 2002-03
Public Private Partnerships: An Introduction
Richard Webb and Bernard Pulle
Economics, Commerce and Industrial Relations Group
24 September 2002
Contents
Major Issues
Introduction
What are Public Private Partnerships?
Role and Responsibility of Government
Applications
Why do Governments use Public Private Partnerships?
Value for Money
Risk Transfer
Incentives
Public Sector Comparator
Political Attraction
Budget Constraints
Issues in PPPs
Public Versus Private Finance
Accounting for Public Private Partnerships
Transaction Costs
Other Issues
Government Policy Towards Public Private Partnerships
Conclusions
Appendix One: Forms of Public-Private involvement
in Infrastructure
Appendix Two: Effects of Section 51AD and Division
16D of the Income Tax Assessment Act 1936 on Public Private Partnerships
Endnotes
The private sector has long provided goods and services
to the public sector. However, a trend seems to be developing in a number
of countries, notably the United Kingdom, towards increasing involvement
of the private sector in the provision of goods and services traditionally
provided by, and seen as a function of, the public sector. This entails
a shift in the role of the public sector from supplying to buying services,
with private firms designing, constructing, financing, operating and maintaining
infrastructure, and the public sector paying for these services. Such
arrangements are called public private partnerships (PPPs). Contracting
out differs from PPPs in that the latter usually entail a combination
of services (for example, design, construction and maintenance) whereas
contracting out is usually for one or relatively simple services.
Key features of infrastructure PPPs include:
- the private sector invests in infrastructure and provides related
services to the government
- the government retains responsibility for the delivery of core services,
and
- arrangements between the government and the private sector are governed
by long-term contract. It specifies the services the private sector
has to deliver and to what standards. Payment depends on the private
partner meeting these standards.
PPPs take many forms such as design, construct and maintain,
and build, own, operate and transfer. The choice of form depends on factors
such as the government's objectives, the nature of the project, the availability
of finance, and the expertise that the private sector can bring. The main
applications (by value) of PPPs in Australia and overseas are transport-related.
However, PPPs are increasingly being used in social infrastructure such
as hospitals and schools.
Governments are attracted to PPPs because they may provide
value for moneyat least in the short term. The ability to transfer risk
to whichever of the public or private partner is better able to manage
the risk is a source of value for money. PPPs often involve the private
sector providing a 'bundle' of services. Bundling can provide value for
money that contracting services separately cannot. PPPs can contain incentives
for the private sector party to perform well. For example, under a contract
to construct a road, the developer has an incentive to do the minimum
necessary to meet the contract terms. However, under a design, construct
and maintain arrangement, the developer has an incentive to build the
road to the standard necessary to provide services for the period of the
contract. For heavily indebted governments, an attraction of having the
private sector finance infrastructure is that it obviates the need to
borrow, and can allow projects to be brought forward. But even if the
private sector finances a project, the government has to fund payments
to the private partner for the services provided. Assessment of whether
a PPP offers value for money entails the preparation of a 'public sector
comparator'. This is an estimate of what the proposed project would cost
if the public sector were to undertake it, based on 'best-practice' assumptions.
The shift from supplying to buying services changes demands on the public
service towards output specification and contract management including
specification of the measures by which the performance of the private
sector partner is assessed.
Advocates of private sector finance claim that it provides
incentives for the private partner to deliver projects to time and budget,
and operate infrastructure soundly. Critics of PPPs claim that public
sector finance is cheaper than private sector finance and so the latter
should not be used. But critics of this argument claim that the government's
ability to borrow cheaply is a function of its capacity to levy taxes.
They say that what determines the real cost of finance for a project is
its risks. The private sector explicitly prices these risks into the cost
of finance. When the public sector finances a project, taxpayers bear
the risks and implicitly subsidise the cost of the project because the
risks are not factored into the government borrowing rate.
Critics of PPPs claim that governments can use PPPs to
understate debt by not recording in the balance sheet the total value
of payments payable to private sector providers, that is, PPP obligations
are 'off the balance sheet'. In the United Kingdom, the Accounting Standards
Board argued that payments should be brought into the balance sheet. But
subsequent UK Treasury guidelines allow most PPP transactions to be excluded
from government borrowing on the grounds that they are operating and not
finance leases. No Australian accounting standard deals with risk allocation
issues associated with PPPs. Instead, agencies have adopted the accounting
standards for leases. The Australian Accounting Standards Board, with
heads of Treasury representation, has established a working group to determine
how PPPs should be treated in government accounts.
The private sector sees the lack of accounting standards,
transaction costs and taxation issuesespecially the so-called leasing
sections51AD and Division 16Dof the Income Tax Assessment Act 1936
as barriers to the greater use of PPPs. In certain situations, these sections
deny to the private owner of an asset certain tax deductions related to
the asset. The effect is to reduce the potential value of income from
a project. In 1999, the Ralph Review of Business Taxation recommended
that section 51AD be abolished and that Division 16D be replaced. Treasury
is reviewing these sections and plans to introduce legislation in the
autumn 2003 sittings of Parliament.
State governments are likely to be the main users of
PPPs. The Commonwealth has not yet entered a privately financed project.
As to the Government's position on the use of private finance, following
Cabinet's rejection of using private finance for the patrol boats contract,
the Minister for Finance and Administration was reported as saying that
the Government sees few opportunities to use PPPs. The Minister for Revenue
and Assistant Treasurer has since said that the Commonwealth will evaluate
individual proposals on the basis of their ability to offer value for
money.
Introduction
The private sector has long provided goods and services
to the public sector. At the Federal government level, this role has expanded
beyond relatively small-scale activities to the provision of so-called
non-core activities such as corporate services. The Government is committed
to competitive
tendering and contracting, and market
testing is mandated for most Federal agencies. The Government has
also involved the private sector in the operation of publicly-owned assets.
For example, beginning in 1997, the Government has granted long-term leases
to private companies to operate the major Commonwealth-owned
airports.
The expansion of private sector involvement in the provision
of 'public services' is even more pronounced at the State level. An indicator
of the magnitude of this involvement is that over ten years, the contribution
of private sector funding to infrastructure provision in NSW was equivalent
to about seven per cent of the State's capital budget.(1) An
example of the increasing role of the private sector is roads. Whereas
the public sector used to design, construct and maintain roads, private
contractors are increasingly undertaking these activities.(2)
A major departure from traditional practice has been the use of the private
sector not only to construct infrastructure but finance and operate it
as well. This is perhaps most evident in NSW and Victoria whose governments
have used build, own, operate and transfer (BOOT) arrangements for toll
roads in Sydney and Melbourne. Victoria and South Australia have also
adopted franchise arrangements for some public transport services. While
the focus of past private sector involvement has been economic infrastructure
such as roads, an emerging trend seems to be towards private sector involvement
in the provision of social infrastructure such as hospitals and schools.
For example, the Port Macquarie Base Hospital is the first public hospital
that a private firm manages on behalf of the NSW government, and a private
company won the contract to design, build and operate the prison at Junee.
These developments are part of what seems to be a trend
around the worldmost notably in the United Kingdomtowards increased
involvement of the private sector in the provision of goods and services
traditionally provided by and seen as a function of the public sector.
In particular, private firms have become increasingly involved in the
design, financing, operation and maintenance as well as the more traditional
construction of public infrastructure. Such activities are called public
private partnerships (PPPs).(3) Contracting out differs from
PPPs in that the latter usually entail a combination of services (for
example, design, construction and maintenance) whereas contracting out
is usually for one or relatively simple services.
This paper seeks to explain what PPPs are, why governments
have used PPPs, some consequences of their use, and the debate surrounding
their use. It also reviews some infrastructure taxation matters that some
claim impede the greater use of PPPs. The paper does not examine the reasons
for the alleged success or failure of individual PPPs.(4) There
are several reason for this approach. First, as the Organisation for Economic
Cooperation and Development noted of PPP projects in the United Kingdom:
Unfortunately, there is a lack of systematic evaluations of the
results from PPP projects and it is still too early to judge whether
savings can be maintained in the long run as many contracts are still
in their early stages. The potential for future savings could be undermined
by the long time horizon of contracts.(5)
Second, it is difficult to assess the merits of claims
and counter-claims about individual PPPs. Third, much of the discussion
of the alleged success or failure of particular PPPs is indeterminate.
For example, if the government decides to use a PPP, it may be difficult
to determine whether public sector provision would have produced better
outcomes. Finally, while noting that some governments may be attracted
to PPPs for political reasons, the paper does enter the political debate
about PPPs.
There is no hard and fast definition of PPPs. One definition
is:
partnerships between the public sector and the private sector
for the purposes of designing, planning, financing, constructing and/or
operating projects which would be regarded traditionally as falling
within the remit of the public sector. Infrastructural projects such
as roads and bridges are prime examples.(6)
A project does not have to contain all these features
to be called a PPP because, as discussed below, PPPs can take a number
of forms.
PPPs entail a sharing of responsibility between government
and the private sector:
For example, the private sector contributes design, construction,
operation, maintenance, finance and risk management skills while the
government is responsible for strategic planning and industry structure,
obtaining permits, some customer interface issues, regulation, community
service obligations and (sometimes) payment on behalf of the service
users.(7)
The key features of infrastructure PPPs have been identified
as:
- a private partner investing in public infrastructure, and providing
related non-core services to the government or to the community on the
government's behalf
- the government retaining responsibility for the delivery of core services
such as teaching and clinical services, and
- the government and private party working together under long-term
arrangements, whereby the payments to the private sector party depend
upon its continuing to deliver the specified services to the agreed
performance standards. Failure to meet these standards results in the
private partner not being paid.(8)
In the United Kingdom, the main form of PPP is the Private
Finance Initiative (PFI). The main features of PFI have been described
as follows:
Considerable capital expenditure
by the contractor. The contractor is usually
expected to invest heavily in productive assets such as buildings,
roads or other physical infrastructure or IT-systems. These investments
are financed by private sources involving the issuing of equity and
debt securities.
The bundling of different operational tasks within a partnership.
Rather than outsourcing each activity separately (like cleaning, heating
or maintenance), PFI combines several or most operations that together
constitute a package of services within one long-term contract, thus
enabling the contractor to seek innovative solutions for cost reductions
within a longer planning horizon. Performance-based payment schemes.
Both classical outsourcing and PFIs normally rely on competitive tendering.
However, unlike classical outsourcing, PFI contracts make payments
during the contract period dependent on a set of performance measures
evaluated at regular time intervals. Moreover, PFI contracts typically
set requirements regarding the quality of outcomes (rather than quantity
of input or output) and leave the contractor freedom as to how to
meet them.(9)
PPPs take many forms. Examples are design, construct
and maintain (DCM); build, own operate (BOO); and build, own, operate
and transfer (BOOT). (Appendix One contains definitions of some forms
of infrastructure PPPs). PPPs can be thought of as falling along a spectrum
of different combinations of public and private arrangements:(10)
The spectrum of possible PPPs extends from businesses almost
entirely controlled by the private sector, at one end, to those almost
entirely controlled by the public sector, at the other. Outside the
United Kingdom, there are PPP businesses jointly owned by the public
and private sectors, but with the majority ownership held by the public
sector. Examples include water utility companies within continental
Europe.(11)
Partnerships
Victoriathe Victorian Government's policy towards and guidance
for PPPsidentifies models ranging from maximum to minimum retention of
service delivery by government.(12) PPPs generally do not,
however, involve privatisation, that is, the sale of equity in public
enterprises with the public sector no longer participating in their operation.(13)
The choice of form depends on factors such as the government's
objectives, the nature of the project, the availability of finance, and
the expertise that the private sector can bring. Partnerships Victoria
lists three considerations in determining the preferred form:
-whether any part of the proposed service should be delivered by
government itself; -whether involvement of the private sector will
deliver value for money and, if so, how to optimise that value; and
-whether the project will satisfy the pubic interest criteria which
form part of the Partnerships Victoria policy.(14)
Some forms of PPP are more suited than others for a particular
task. For example, with respect to the use of BOOT schemes, the Private
Infrastructure Task Force Report opined:
In the broad, BOOT-type structures are likely to be least beneficial
for road and urban rail projects. They are advantageous for long distance
rail and for utility services such as electricity and water. But for
utility services it is possible that privatisation of networks might
offer even greater gains. This is particularly so if competition can
be introduced through, for example, breaking up generation or distribution.(15)
The use of PPPs entails changes to the role of government.
This often entails a shift from being the supplier to the buyer of services:
The PFI transforms Government Departments and Agencies from being
owners and operators of assets into purchasers of services from the
private sector.(16)
Nonetheless, governments retain overall responsibility
for service delivery:
within a Private Finance Initiative project, the public sector
pays for services on behalf of the general public and retains ultimate
responsibility for their delivery, whereas the private sector's role
is limited to that of providing an improved delivery mechanism for
the services.(17)
The use of PPPs has important consequences for the public
service. The key shift is from the role of supplying services to buying
them:
The essential role of the public sector in all PPPs is to define
the scope of business; specify priorities, targets and outputs; and
set the performance regime by which management of the PPP is given
incentives to deliverand, in the case of PFI projects, also to pay
forthe services.(18)
The consequences of PPPs for the public sector are thus
similar to those resulting from contracting out. But because PPPs are
usually more comprehensive in scope than contracting out, PPP place even
greater demands on the public service.
State governments have been the main users of PPPs in
Australia. This is likely to remain the case since the States bear primary
responsibility for providing economic and social infrastructure. The main
applications (by value) of PPPs in Australia and overseas are transport-related.
The largest PPP in the United Kingdomthe Channel Tunnel Rail Linkwas
valued at 4178 million (almost $12 billion).(19) However,
PPPs are increasingly being used for social infrastructure such as the
hospitals and schools. The NSW green paper on PPPs listed 23 projects
involving private sector funding of infrastructure including toll roads,
hospitals, water and sewerage infrastructure, and Olympic venues.(20)
In the UK, the application of PPPs has extended to hospitals, schools,
prisons and defence projects.(21)
Still, PPPs account for a relatively small proportion
of capital expenditure with NSW, Victoria and Queensland collectively
accounting for around only nine per cent.(22)
There are a number of reasons governments are attracted
to PPPs. They include the potential for value for money, early project
delivery, gains from innovation, obviating the need to borrow to finance
infrastructure investment, and access to improved services. The relevant
government agency is responsible for assessing whether a project offers
value for money compared with the most efficient form of public delivery.
To do this, the agency uses a 'public sector comparator' (discussed below).
Some governments might find PPPs politically attractive in that PPPs entail
private sector partners supplying 'public' services.
PPPs operate at the boundary of the public and private
sectors, being neither nationalized nor privatized assets and services.
Thus, politically, they represent a third way in which governments
may deliver some public services.
The underlying rationale for PPPs is that they may offer
value for money:(23)
the [NSW and Victorian] policies require that privately financed
options demonstrate superior value-for-money to the Government and
community compared to conventional, publicly funded approaches to
infrastructure provision. This is the sole reason for considering
private financing and deliverywith both States having low debt levels,
off-balance sheet borrowing is not an attraction in its own right.(24)
The forms that value for money can take include:
lower construction costs, lower operating costs and perhaps more
efficient maintenance in the long run, than comparable public sector
projects.(25)
With respect to construction costs, UK evidence on PPP
projects is mixed with some projects coming in under cost and others incurring
cost overruns.(26)
PPPs often involve the private sector partner providing
a 'bundle' of services such as the design, construction and maintenance
of a road. Bundling thus differs from traditional contracting out whereby
separate contracts are let for each service. Bundling can provide value
for money that cannot be obtained by contracting services separately:
Integration of design, operation and maintenance over the life
of an asset, within a single-project finance package improves performance
and reduces whole-of-life costs.(27)
For example, there may be economies in construction when
a road is built as a single project rather than in stages as funding becomes
available.(28)
The sources of value for money ('drivers') have been
described as follows:
At the heart of all PPPs is the deployment of private sector capital.
Within a PPP framework, this can result in greatly improved value
for money for the government in terms of the risks transferred to
the private sector (in cases where the latter is better able to assess
the risks) and powerful private sector incentives for the long-term
delivery of reliable public services.(29)
Partnerships Victoria lists four major 'drivers':
risk transfer, whole-of-life costing, innovation and asset utilisation.(30)
Risk Transfer
As noted, the transfer of risk is a driver of value for
money. Risk can take many forms including those relating to construction,
the size of the market (demand risk), the cost of operations and maintenance,
declarations of force majeure, and changes to the law and regulations.(31)
Whatever the nature of the risk, the principle of optimal risk transfer
is:
that the risk should be allocated to whoever from the public
or private sector is able to manage it at least cost.(32)
The nature of risk allocation has been described as follows:
The essence of a public-private partnership arrangement is the
sharing of risks. Central to any successful public-private partnership
initiative is the identification of risk associated with each component
of the project and the allocation of that risk factor to either the
public sector, the private sector or perhaps a sharing by both. Thus,
the desired balance to ensure best value (for money) is based on an
allocation of risk factors to the participants who are best able to
manage those risks and thus minimize costs while improving performance.(33)
Partnerships Victoria, in the Risk Allocation
and Contractual Issues guide, classifies major project risks into ten
categories and recommends a government-preferred position on allocating
each of the risks. In practice, the allocation of risk has not always
been appropriate, and the government has had to assume risks that were
initially transferred to the private party. An example is the Sydney airport
rail link, which the NSW Government took over after the company that built
and operated the link failed to meet scheduled payments to creditors.
Incentives
PPPs can contain incentives for the private sector party
to perform well in order to earn a profit:
Much of the improved value for money comes from the fact that when
private sector capital is deployed and is at riskto, for example,
the long-term performance of public service deliverythe right commercial
decisions are made about design, operating regime, human resource
planning, whole-life-of-asset costings, and so on.(34)
For example, under a contract to construct a road, the
developer has an incentive to do the minimum necessary to meet the contract
terms. However, under a design, construct and maintain arrangement, the
developer has an incentive to minimise whole-of-life costs(35)
and so construct the road to the standard that will minimise those costs.
This incentive is reinforced by the fact that payment under PPPs depends
on the developer meeting agreed maintenance standards.
PPPs can contain negative incentives for the public sector.
Where the contract specifies that the asset is to be returned to the public
sector at the end of the contract period, the private partner has an incentive
to run the asset down especially in the later years of the contract. However,
contracts typically specify that the government has a right to review
the asset's condition before it is returned to ensure that the condition
is acceptable. A third party sometimes conducts this review. Further,
if running down the asset results in standards lower than those specified
in the contract, the private sector partner will not be paid.
Public Sector Comparator
Assessment of whether it offers value of money is an
essential part of a PPP process. This entails comparing the proposed PPP
with the cost of the public sector undertaking the project. This requires
the preparation of a public sector comparator (PSC):
In most cases, value for money will need to be demonstrated by
comparison of private sector PFI bids with a detailed public sector
comparator (PSC). The PSC describes the option as to what it would
cost the public sector to provide the outputs it is requesting from
the private sector by a non-PFI route.(36)
The comparator is based on 'best practice' assumptions.
The Department of Finance and Administration has issued guidelines requiring
that agencies prepare a PSC in certain circumstances.(37)
However, governments consider other factors as well as
the comparator.(38) NSW and Victorian policies specifically
include a public interest test:
P[rivately] F[inanced] P[rojects]/PPPs are assessed against public
interest criteria including effectiveness, impact on key shareholders,
accountability and transparency, public access and equity, consumer
rights, security, and privacy. This assessment takes place before
the project is put to the market.(39)
Political Attraction
Some governments might find PPPs politically attractive:
PPPs operate at the boundary of the public and private sectors,
being neither nationalized nor privatized assets and services. Thus,
politically, they represent a third way in which governments
may deliver some public services. Moreover, in a practical sense,
PPPs represent a form of collaboration under contract by which public
and private sectors, acting together, can achieve what each acting
alone cannot.(40)
How a PPP is paid for depends on whether it is self-financing.
When a project is self-financingfor example, when the private sector
finances, constructs, and operates roads and recovers costs through direct
tolls on road usersthe government does not have to borrow or levy taxes
to finance the project because it is paid for by direct user charges.
When the project is not self-financing the government has to levy taxes
to meet payments to the private sector provider. This does not necessarily
mean that the government has to raise taxes since the project could be
financed from within the existing tax framework. A third category of project
combines cost recovery and government subsidy. Many social infrastructure
projects are not self-financing.
In the UK, PFIs were introduced to circumvent constraints
on public sector borrowing. The main alternative to PPPs with private
sector finance is for the government to borrow through the issue of debt
such as bonds. For governments with large debts and hence reluctant to
borrow more, having the private sector finance infrastructure obviates
the need to borrow. An example of where the use of PPPs is being considered
mainly because national government funding will not cover the cost, is
the proposed Trans-European
Network for Transport.
Private sector financing can allow governments to bring
forward projects that might otherwise be delayed because of budget constraints.
Delaying projects can have adverse consequences:
the public sector will often find it difficult to provide dedicated
funding for large projects out of annual budgets. In the past, this
has resulted in lengthy delays before projects proceed and/or projects
proceeding incrementally over a number of years. Delayed access to
necessary infrastructure is costly to the community. Also, budget
constraints can lead to sub optimal project forms. For example, government
agencies may opt for lower up front cost infrastructure with much
higher maintenance costs or a shorter life.(41)
On the other hand, given that political considerations
often drive the timing of projects, bringing forward projects may not
result in the optimal timing of investment in that economic benefits may
not be maximised. For example, benefit-cost analyses of toll roads in
Norway indicate that delaying projects would have resulted in increased
net benefits.(42)
The NSW and Victorian Governments deny that borrowing
constraints are the reason they consider using PPPs. Rather:
with both States having AAA balance sheets, it is these ongoing
availability and performance payments (or depreciation and debt servicing),
which are more important constraints on governments.(43)
When a project is not self-financing, regardless of whether
the public sector or the private sector under a PPP finances investment,
governments have to fund payments to meet future costs:
Even though social infrastructure may be financed by the private
sector, the government, through payments made during the contract's
life, will ultimately fund it through payments for the services provided.
These payments commitments are as real as those associated with servicing
balance-sheet debt and, in the context of a government's fiscal strategy,
need to be considered in a similar manner.(44)
The case for using private sector finance in PPPs has
been put as follows:
The importance of the finance element of privately provided infrastructure
lies in the incentive it can provide for the performance of the infrastructure,
and the disciplines external financiers can provide on the delivery
of project to time and budget. It is difficult to replicate the strength
of these incentives and disciplines within a conventional funding
process where all the risks of delivery reside with the government.(46)
Critics have claimed that PPPs involving private sector
finance should not be used because public sector finance is cheaper. The
Department of Finance and Administration's policy principles for the use
of private financing state:
it is generally more expensive for the private sector to raise
capital through private capital markets, than for the Commonwealth
to do so directly.(47)
However, critics of the argument that public sector finance
is cheaper claim:
It's a myth that governments have access to 'cheaper' finance to
undertake projects: a government's ability to borrow more cheaply
is purely a function of its capacity to levy taxes to repay borrowings.
But, when it comes to raising finance for a project, it's the risk
of the individual project that determines the real cost of finance.
The difference between the private and public sectors is that private-sector
capital markets explicitly price in the risk of the project into the
sources of finances. In the public sector, taxpayers implicitly subsidise
the cost of a project by bearing the risk of cost overruns, time delays
or performance failures, which are not priced into the government
borrowing rate.(48)
It has been claimed that when risks are factored into
the cost of government debt, the differential between the cost of government
debt and private debt in the case of a project with a 'guaranteed' revenue
stream from government is only 15 basis points.(49) If so,
it is difficult to use the 'higher cost of funds' argument especially
if the benefits of risk transfer outweigh the additional cost of private
finance.
The Bureau of Transport and Communications Economics
observed that:
The transfer of financial risk from lenders to taxpayers provides
no obvious benefit to society. The interest rate differential [between
government and private sector borrowings] is therefore no indication
that public ownership reduces the cost of capital to society.(50)
From a government budget perspective, PPPs involving
the government buying services move spending from the capital to the recurrent
budget or, to put it another way, today's capital investment by the private
sector becomes tomorrow's current spending by the government. However,
an issue is how governments should account for PPP payments and, in particular,
whether they should be brought into the government's balance sheet as
debt. When the government issues debt, it has to repay the interest and
principal to debt holders. The government records the total outstanding
debt as a liability in its balance sheet. Repayments of principal are
recorded as reductions in outstanding debt. Critics of PPPs claim that
governments can use PPPs to understate debt by not recording in the balance
sheet the total value of payments. In other words, PPP obligations are
'off the balance sheet'.
Accounting for PPPs is an issue in the UK:
In September 1998, the [UK] Accounting Standards Board (ASB) stated
that the capital value of P[rivate] F[inance] I[nitiative] schemes
should appear on the Government's "balance sheet". However, following
negotiations between the ASB and the [UK] treasury, in June 1999 the
treasury issued a new version of their note How to account for
PFI transactions which allowed most PFI transactions to be excluded
from Government borrowing figures on the grounds that they were "operating
leases", not "finance leases" ... The ASB has said that the revised
accounting guidance is to be kept under review and updated as necessary
in the light of developments in the PFI (51)
The Accounting Standards Board standard referred to above
(FRS 5) deals with 'reporting the substance of transactions':
FRS5 addresses the problem of what is commonly referred to as 'off
balance sheet financing'. One of the main aims of such arrangements
is to finance a company's assets and operations in such a way that
the finance is not shown as a liability in the company's balance sheet.
A further effect is that the assets being financed are excluded from
the accounts, with the result that both the resources of the entity
and its financing are understated. FRS 5 requires that the substance
of an entity's transactions is reported in its financial statements.
This requires that the commercial effect of a transaction and any
resulting assets, liabilities, gains and losses are shown and that
the accounts do not merely report the legal form of a transaction.
For example, a company may sell (ie transfer legal title to) an asset
and enter into a concurrent agreement to repurchase the asset at the
sales price plus interest. The asset may remain on the premises of
the 'seller' and continue to be used in its business. In such a case,
the company continues to enjoy the economic benefit of the asset and
to be exposed to the principal risks inherent in those benefits. FRS
5 requires that the asset continues to be reported as an asset of
the seller, notwithstanding the transfer of legal title, and that
a liability is recognised for the 'seller's' obligation to repay the
sales price plus interest.(52)
In its publication How
to Account for PFI Transactions, the UK Treasury draws a distinction
between finance and operating leases. No Australian accounting standard
deals with risk allocation issues associated with PPPs. Accounting Standard
AAS17, which deals with leases, is relied on to classify PPP arrangements.
But this Standard does not deal adequately with the unique nature of PPPs.
The Australian Accounting Standards Board, with Heads of Treasury representation,
has establish a working group to determine how these issues should be
treated in government accounts.
The treatment of a lease depends on whether it is a finance
or operating lease. A finance lease is one where substantially all of
the leased asset effectively passes from the lessor to the lessee. For
such a lease, the lessee must, at the beginning of the lease, recognise
an asset and liability equal to the 'present value'(53) of
the minimum lease payments. The leased asset must be written off over
the period in which it is expected benefits will be consumed. Minimum
lease payments must be apportioned between interest expense and a reduction
in the lease liability. An operating lease, on the other hand, is one
where substantially all the risks and benefits incidental to the ownership
of the asset remain with the lessor. For such a lease, the minimum lease
payments are an expense.
The NSW and Victorian Governments acknowledge the need
for accounting standards:
A recognised Australian Accounting Standard capable of addressing
the complex risk allocations issues in a PFP/PPP transaction does
not exist, and the existing standard on accounting for operating and
finance leases has tended to be adopted by some parties as a default.
An inter-jurisdictional group has been working actively to develop
proposals for a better accounting treatment of these transactions,
to ensure that they are appropriately reported within a State's accounts.(54)
The process of defining and bidding for PPPs is costly
for the private sector and the government. The Australian Council for
Infrastructure Development has described these 'transaction costs' as
follows:
Bidding for complex PPPs is time consuming and expensive. Unless
tendering processes are well run it is possible that the benefits
of using a PPP for delivering the project may be outweighed by the
tendering costs. For this reason it is essential for the government
to prepare good processes with a common approach across the whole-of
government Transaction costs can also be reduced by following the
UK's example and developing standard risk allocations and conditions
of contract(55)
The often short-term focus of government budgeting decisions
and delays in making decisions are particular difficulties for private
firms. Standardisation of some contract documentation, procedures and
definitions(56) can reduce bid costs and accelerate project
timetables.(57) But the fact that each project is different
limits the scope for contract standardisation.
The traditional contracting out of activities to the
private sector means that some of the benefits of private sector involvement
in the provision of public goods and services have already been obtained.
PPPs potentially may offer additional value for money especially if services
are bundled to incorporate design, build, and lifetime operation and maintenance
of assets, and through appropriate risk transfer. And the use of comparators
and other considerations helps to ensure that PPPs offer value for money.
However, PPPs are potentially fraught with difficulty.
The design and implementation of PPPs are usually very complicated. The
essence of the business relationship between the public and private sectors
is contractual. This requires that the services to be delivered have to
be specified in great detail. Assessment of whether a PPP would offer
value for money is often difficult to determine. Some risks are difficult
to identify let alone quantify, and it is difficult to assess to what
extent the transfer of risk is deemed optimal.(58)
These considerations have been summarised as follows:
In areas like infrastructure, where large-scale investment is needed,
so-called public private partnerships (PPP) may be an option, where
private investors design, build, own, maintain and operate facilities
like highways under long-term contracts. By deferring payment and
by making it contingent on facilities being operable through the contract
period, PPP contracts transfer investment risks to the private investors,
such as those arising from delays in construction projects, and ensure
a life-cycle perspective on costs. Private contractors may be better
equipped than government for managing construction projects, especially
where there is considerable scope for reducing maintenance and operation
costs through innovative design. However, PPP usually entails a higher
cost of capital than if the risks were carried by the general government
budget and investment were financed via public lending. Moreover,
complex financial contracts, involving commitments to future payments,
may reduce transparency, requiring strong institutional checks. And
while PPP contracts shift investments off the government's balance
sheet, the commitments to pay for future service-flows have largely
the same macroeconomic effects as public debt. Most importantly, the
inherent long-term character and complexity of PPP contracts may pose
a number of problems. It may have adverse effects on the effectiveness
of competition, as fewer firms are able to make a bid, and contracts
must be able to accommodate changes in future need which are inherently
difficult to foresee. As far as large-scale infrastructure is concerned,
achieving co-ordination among alternative routes and means of transport
is crucial and having a range of different private owners may entail
complicated and costly negotiations to accommodate changes. Furthermore,
insofar as the government may ultimately be held responsible for outcomes,
the transfer of risks to private contractors may be partial, with
the government having to step in if something goes wrong.(59)
Note that this summary seems to accept the claim that
government finance is cheaper than private finance.
PPPs could have adverse effects on competition. As noted,
the potential for savings from PPPs could be undermined by the long time
periods of contracts. Moreover:
the specificity of assets (such as a hospital building or an
IT-system) implies that the private and public partners become mutually
dependent in a way that may stifle competition. When the contract
expires, other potential contractors may be reluctant to undertake
the effort necessary to make a bid in a renewed tender process, knowing
that the incumbent will have a considerable cost advantageother things
being equal.(60)
INGREDIENTS FOR A SUCCESSFUL PPP
The UK National Audit Office (NAO) in a
report titled Managing
the Relationship to Secure A Successful Partnership in PFI Projects
found that most (81 per cent) public bodies involved in PFI projects believed
that they are achieving satisfactory or better value for money from their
PFI contracts. Feedback from service users was generally positive. Over
70 per cent of authorities and contractors viewed their relationship as
being good or very good with only four per cent of contractors feeling
their relationship with authorities was poor.
The NAO report identified the following
necessary ingredients for a successful PPP:
- As PFI projects are long-term arrangements, a successful
outcome is best achieved by authorities and contractors balancing both
contractual and relationship issues to approach projects in a spirit
of partnership. Authorities and contractors should seek to understand
each others businesses and should have a common vision of how they
will work together to achieve a mutually successful outcome to the project.
Authorities should regularly reassess their relationships with contractors
and the value for money their projects are delivering, to identify ways
in which relationships can be improved.
- The long-term nature of PFI projects means that some
contractual changes are likely to be necessary during the life of the
project. The report found that although most PFI projects are still
at an early stage, around half of the contracts surveyed had been changed
since they were entered into. Changes related to the specification,
new services, additional building work or design changes and performance
measurement arrangements. Appropriate procedures for dealing with change
should be built into the contract. This includes procedures to ensure
that value for money is maintained when contract changes occur.
- Having staff with the right skills is critical to good
contract management, yet there is considerable variation in the extent
of training provided in contract management skills, with some authorities
providing little or none. Attention needs to be given early in the procurement
process to staffing, training and contract management issues, and how
the relationship between authority and contractor will be developed.
The Channel Tunnel Rail Link (Link) is the
largest (by value) PFI undertaken in the United Kingdom. However, the
project almost collapsed partly because of overly optimistic forecasts
for the company responsible for operating the UK section of the train
service. As a result, the project was refinanced and risks redistributed
among the various parties. The NAO examined the reasons for the near collapse
of the arrangements in a report titled the Channel
Tunnel Rail Link. The NAO concluded that the lessons
learned from this experience are relevant to other PPPs. These lessons
include:
- make sure that bidders for a PFI deal are not encouraged
to be over-optimistic
- if a deal goes wrong, private sector partners should
bear their share of the risk
- substantial risks arise if public sector assets are transferred
in advance
- the proportion of equity capital in a PFI project should
reflect the risks involved
- the Department [of the Environment, Transport and the
Regions] should monitor the expected benefits from the Link
- government guarantees of project debts are unlikely to
be costless, and
- if a project requires public funding, give careful consideration
to the most cost-effective route.
To date, the Commonwealth has not entered into a privately
financed project. But a number of agencies have been preparing for the
possible use of private financing. In December 1998, the Department of
Defence undertook:
a review of options for the greater use of private financing
of its procurement requirements ... The Defence Executive decided
that Private Financing be considered for proposals requiring investment
of Defence resources ...(61)
On 20 May 2002, the Department issued a Private Financing
Manual. This is a guide to the use of private finance in major capital
equipment and infrastructure projects. The Department rejected using private
finance for the patrol boats contract.(62)
The Private Financing Unit has been established in the
Department of Finance and Administration:
[to] work collaboratively with Commonwealth agencies and their
advisers to assist with assessing the relative merits and viability
of private financing proposals.(63)
The Unit has released an issues paper titled Taxation
and Private Financing Initiatives for comment. The paper deals, among
other things, with the definition and measurement of tax advantage, and
relevant provisions of the Income Tax Assessment Act 1936. In October
2001, the former Minister for Finance and Administration, the Hon. John
Fahey, issued a paper titled Commonwealth
Policy Principles For The Use Of Private Financing. This paper:
establishes policy principles and processes for the use of private
financing by Commonwealth departments and agencies subject to the
Financial Management and Accountability Act 1997 (agencies).
The Department of Transport and Regional Services has
been investigating the use of PPPs to develop roads.(64) The
Government's AusLink
proposal may entail the use of PPPs (see the quote below). The proposed
Western Sydney Orbital Road to which the Commonwealth is contributing
funds may be the first stretch of the National Highway to be largely privately-funded.
However, the NSW government will be primarily responsible for developing
the PPP for the Orbital Road.
As to the Government's position of the use of private
finance, following Cabinet's rejection of private financing of the patrol
boats contract,(65) the Minister for Finance and Administration,
the Hon. N. Minchin, is reported as saying that the Commonwealth Government
sees few opportunities to use PPPs.(66) The Minister for Revenue
and Assistant Treasurer, Senator the Hon. Helen Coonan, has since stated:
The Minister for Finance and Administration recently indicated
that there currently appear to be limited opportunities for the use
of private financing at the Commonwealth level. However in saying
that, it is important to emphasise that individual proposals will
continue to be evaluated on the basis of their ability to offer value
for money to the Commonwealth. As my colleague, the Minister for Industry,
Tourism and Resources outlined yesterday, in May 2002, the Minister
for Transport and Regional Services indicated that the Government
will be developing a new transport infrastructure plan -Auslink. This
is a plan to reform Australia's land transport arrangements. The Government
will be releasing a discussion paper - a Green paper - in relation
to AusLink later this year. It will establish the basis for developing
a formal statement of Government policy in May 2003. Under the proposed
AusLink plan the Minister emphasised that proposals for PPP arrangements
would be given equal treatment with other project bids to advance
the plan's strategic land transport infrastructure priorities.(67)
To date, State governments have been the main users of
PPPs in Australia. This is likely to remain the case since the States
bear primary responsibility for providing economic and social infrastructure,
and several States have issued guidelines
for the use of PPPs. A risk is that each State will 'go its own way'.
However, steps are being taken to try to ensure consistency in approach
across the States and Commonwealth:
In a small country like Australia, the existence of separate state-based
P[rivately]F[inanced]P[rojects]/PPP markets is unsustainable, and
can only contribute to the (often significant) transaction costs associated
with getting projects up and running. Accordingly, all states, the
territories and the Commonwealth have been working through the Heads
of Treasuries forum to promote consistent approaches.(68)
The development of PPPs is an on-going process. Shortcomings
of early PPPs have been recognised and the lessons learned incorporated
into subsequent projects. For example, it has been recognised that:
Early in both States' [NSW and Victoria] experience the temptation
was for maximum transfer of risk, and inevitably risks were sometimes
transferred that ultimately came back to Government.(69)
It is also recognised that the 'one size fits all' approach
doesn't work. For example, whereas BOOT schemes have been the preferred
form of PPP for urban roads, design, construct and maintain arrangements
might be better suited to rural roads.
Despite the difficulties that PPPs have encountered,
it seems likely that more and more countries will use them and for increasingly
varied purposes. One person involved in PPPs has predicted 'explosive
growth' in PPP programs internationally over the next few years and expects
the following developments:
More diversity in PPP models Design Build Finance Operate contracts
will always be important, but so too is the need for flexibility and
closer alignment of the private sector with public sector objectives.
Structural changes in the private sector Consortia will give way
to genuine operator companies, a trend already being seen in the UK.
Corporate finance will become as important as project finance in supporting
PPP investment. Structural changes in the public sector - Aside from
the need for changes to initially facilitate PPP programmes, new structures
will develop. More focus on the workforce involved in PPPs Internationally,
there is growing concern about the impact on public sector employees
transferring to the private sector where much greater efficiencies
are being promised. Increasing internationalisation Many of the
players in PPPs are still domestically focussed, but will follow international
opportunities where they have competitive advantage from past experience.(70)
Traditional Design and Construction (TDC)
The Government, as principal, prepares a brief setting
out project requirements before inviting tenders for the design and construction
of the project. Private sector contractors undertake to design the project
in accordance with the brief, and construct it for an agreed sum, which
may be fixed or subject to escalation.
Operation and Maintenance Contract (O&M)
These projects involve the private sector operating a
publicly-owned facility under contract with the Government.
Lease - Develop - Operate (LDO)
This type of project involves a private developer being
given a long-term lease to operate and expand an existing facility. The
private developer agrees to invest in facility improvements and can recover
the investment plus a reasonable return over the term of the lease.
Build - Own - Maintain (BOM)
This type of arrangement involves the private sector
developer building, owning and maintaining a facility. The Government
leases the facility and operates it using public sector staff.
Build - Own - Operate - Transfer (BOOT)
Projects of the Build-Own-Operate-Transfer (BOOT) type
involve a private developer financing, building, owning and operating
a facility for a specified period. At the expiration of the specified
period, the facility is returned to the Government.
Build - Own - Operate (BOO)
The Build-Own-Operate (BOO) project operates similarly
to a BOOT project, except that the private sector owns the facility in
perpetuity. The developer may be subject to regulatory constraints on
operations and, in some cases, pricing. The long term right to operate
the facility provides the developer with significant financial incentive
for the capital investment in the facility.
Source: Tasmanian Department of Treasury and Finance,
Guiding
Principles for Private Sector Participation in Public Infrastructure Provision
Introduction
The so-called leasing sections51AD and Division 16Dof
the Income Tax Assessment Act 1936 (ITAA 1936) apply to many PPPs.
In certain circumstances, these sections deny to the owner of an asset
(the private sector) certain tax deductions related to the asset. The
effect is to reduce the potential value of income from a project. In 1999,
the Ralph Review of Business Taxation recommended that section 51AD be
abolished and that Division 16D be replaced. Treasury is reviewing these
sections and plans to introduce legislation in the autumn 2003 sittings
of Parliament. Consultation with the States and industry indicates support
for proposed amendments. The following examines the issues surrounding
the leasing sections.
What Exactly Do These Two Provisions of
the ITAA 1936 Do?
Section
51ADDeductions Not Allowable
in Respect of Property Used Under Certain Leveraged Transactions
To claim deductions relating to the ownership of property
(e.g., for depreciation or repairs) it is normally necessary for the taxpayer
to show that the property was used for the purpose of producing assessable
income or in carrying on a business for that purpose. Such deductions
are therefore normally not available to tax-exempt bodies such as public
authorities or non-resident bodies operating exclusively overseas because,
in neither case, is the body producing assessable income.
Section 51AD is an anti-avoidance provision and applies
to property acquired by a taxpayer under a contract entered into after
1 pm on 24 June 1982, or constructed by a taxpayer where construction
commenced after that time. Where the conditions specified in section 51AD
apply, subsection 51AD(10) operates to treat the owner of the property
as not having used it for the purpose of producing assessable income or
in carrying on a business for that purpose. The effect is that the owner
is denied deductions attributable to the ownership of the property, including
depreciation, repairs and interest on borrowings.
By the operation of subsection 51AD(8), section 51AD
will not apply unless the cost of the acquisition or construction of the
property by the taxpayer is wholly or predominantly financed by non-recourse
debt, that is, where the rights of the creditor in the event of default
by the taxpayer, are predominantly limited to rights against the property
itself, or against the income, goods or services generated by the property,
or to rights in respect of a security over the property. A debt is also
a non-recourse debt if the creditor would not have access to all the unsecured
assets of the taxpayer in a recovery action.
Where the conditions relating to time of acquisition
and non-recourse debt are satisfied, section 51AD applies to property
in either of two broad sets of circumstances. The first is where the property
is leased and:
-
- the lessee (or sub-lessee) is not a resident of Australia and
the property is, or is to be, used wholly or principally outside
Australia
-
- the property is, or is to be, used otherwise than solely for producing
assessable income, or
-
- the property was owned and used, or held for use, by the lessee
or sub-lessee before the taxpayer acquired it.
The second circumstance in which section 51AD can apply
concerns property that is owned by a taxpayer but the use of which in
the production, supply, carriage, transmission or delivery of goods or
the provision of services is effectively controlled by another person.
Section 51AD will apply if that other person (called the 'end-user'):
-
- is not a resident of Australia and the property is, or is to be,
used wholly or principally outside Australia
-
- uses the goods or services produced by means of the property otherwise
than solely for the purpose of producing assessable income
-
- derives no income, or derives income that is wholly or partially
exempt, in providing those goods or services, or
-
- owned and used the property, or held it for use, before the taxpayer
acquired it.
Taxation
Ruling TR 96/22 discusses the application and interpretation of section
51AD. It provides a general overview of the provision. In particular,
it deals with the following matters:
- tax-exempt end users
- the nature of non-recourse finance
- the meaning of 'predominant'
- how non-recourse finance is affected by assurances, guarantees, put
or call options and the release of securities
- the Commissioner's discretion to treat a debt as if it were not non-recourse
debt, and considerations affecting its exercise
- the meaning of 'use'
- the meaning of 'control of use', and
- the consequences of section 51AD applying to property in relation
to a taxpayer.
What is a Leveraged Lease Transaction?
A leveraged lease transaction is generally one in which
a partnership of companies or other taxpayers acquires plant, which it
leases for a term of years to a lessee and where, by reason of the 'leverage'
obtained from the borrowing of a substantial non-recourse loan (or a similar
arrangement), the members of the partnership are not effectively at risk
for any more than a relatively small part of the funds used to acquire
the plant. The lenders' security for the substantial amounts lent to acquire
the plant is limited to the subject plant or to the rentals payable by
the lessee.
Taxation
Ruling IT 2051 sets out the basic views of the Australian Taxation
Office on the minimum standards with which leveraged lease transactions
must comply if they are to be accepted under the income tax law.
What is a Non-Recourse Debt?
Broadly, a non-recourse debt is one where the lender's
rights against the borrower in the case of default in repayment are effectively
limited to rights against the property, or against income generated or
goods produced by the property. Generally, this test is satisfied either
by a contractual limitation of the rights of the creditor against the
assets of the borrower or by the fact that the borrower has insufficient
assets, to satisfy the claims of the creditors in the event of a default.
In other words the lender would not have the usual rights of access to
the general assets of the taxpayer in any action for recovery of the debt.
Taxation
Ruling TR 96/22 discusses the nature of non-recourse finance.
Division
16DCertain Arrangements Relating
to the Use of Property
Division 16D of Part III of the ITAA 1936 treats certain
non-leveraged finance leases and similar arrangements as if they were
loan arrangements. Arrangements to which the Division applies are, broadly,
those under which all, or substantially all, the risks and benefits associated
with the ownership of the property that is the subject of the arrangement
are transferred by the owner to the lessee or user. In general, where
an arrangement covered by Division 16D exists, relevant deductions will
be denied if the use of the property, or the effective control of its
use, is in the hands of either:
- a government or tax-exempt government authority and the arrangement
was entered into after 5 pm on 15 May 1984, or
- a person who uses the property outside Australia for the purpose of
producing income which is exempt from tax in Australia and the arrangement
was entered into after 5 pm on 16 December 1984.
Why are Sections 51AD and Division 16D
Considered to be Impediments to PPPs?
PPPs are basically partnerships between public authorities
and private sector companies. As sections 51AD and Division 16D disallow
certain deductions for tax purposes because of the involvement of tax-exempt
public authorities in the partnerships, these sections make it less attractive
for the use of assets owned by public authorities in partnership with
private sector companies. These provisions adversely impact on infrastructure
development where assets owned by public authorities are involved.
End-users in Partnerships
According to the explanatory memorandum to the Income
Tax Amendment Bill (No. 5) 1983, subsection 13 allows proportionate
deductions in cases where the end-user is a partnership 'and some but
not all of the partners are tax-exempt organisations or the partners are
not deriving wholly assessable income from the partnership's use of the
property'. The application of the subsection raises difficulties, especially
in relation to subparagraph (4)(a)(ii), and it is not clear that the explanation
is completely correct. It may be possible to rely on subsection (11) to
obtain a partial deduction where a partnership of lessees uses property
only partly for the purpose of producing assessable income.
In deciding, for the purposes of subsection (13), the
extent to which a taxpayer is to be regarded as having used the property
for business purposes, the Commissioner has regard to the respective interests
of the 'taxable' partners in the net partnership income or loss and the
extent to which any of the other partners have used the property in deriving
assessable income: subsection (14).
None of the foregoing applies, however, where there are
two or more lessees of property caught by subparagraph (4)(a)(ii) and
one is a company whose income is ordinarily exempt from tax, if that company
effectively controls the property and uses it in the company's tax-exempt
activities. In these circumstances, the property is treated as not being
used by the owner for the purpose of producing assessable income and no
deductions at all are allowable: subsection (15).
The Ralph Review in its report A
New Tax System Redesigned at page 392, referred to below, in recommending
the repeal of section 51AD emphasised the adverse impact on infrastructure
providers as the main reason for this recommendation. It stated:
Section 51AD has a severe impact where it applies because all deductions
are denied to the taxpayer but the associated income is still assessable.
It has been continually criticised by State Governments and infrastructure
providers for its severe impact where it applies and the uncertainty
it creates. Section 51AD has become even more problematical in recent
years because of increased levels of privatisation and outsourcing
of government services which were not contemplated when it was first
conceived.
The basis for this view was set out in Discussion Paper
2 Volume 1 titled A Platform
For Consultation issued by the Review of Business Taxation in February
1999. Chapters 8, 9 and 10 dealt with taxation of leases and rights. Paragraphs
8.29 to 8.37, which summarise the impact of sections 51AD and Division
16D on tax exempt leasing, are set out below.
Tax
exempt leasing
- 8.29 The ability of tax exempt entities to engage in leasing and similar
arrangements is restricted by section 51AD and Division 16D, which operate
to deny tax benefits to those who provide property to tax exempt entities,
such as public utilities.
- 8.30 These provisions were introduced to prevent tax exempt entities
from accessing tax preferences by entering into contracts with taxable
entities for the use of assets.
- 8.31 Section 51AD applies to property predominantly financed by non-recourse
debt which is leased to, or effectively controlled by, an end user
which:
- is a tax exempt entity;
- is a non-resident and uses the property outside Australia; or
- previously owned the asset (for example, sale and lease back).
- 8.32 In applying section 51AD, non-recourse debt is broadly defined
as debt where the creditors rights against the debtor in the event
of default are legally or effectively limited to the financed property.
- 8.33 Section 51AD is severe in its application, because it disallows
completely deductions relating to the property, while all the income
remains taxable. It applies to arrangements which have features of both
operating and finance leases.
- 8.34 While always criticised for its severe impact,
section 51AD has become more problematic because of privatisation and
outsourcing of government functions that were not contemplated when
it was first conceived.
- 8.35 Division 16D applies in respect of a qualifying arrangement
where section 51AD does not apply and where there is use or effective
control by an end user who is:
- a tax exempt public body; or
- a person who uses the property outside Australia to produce income
not subject to Australian tax.
- 8.36 Division 16D denies capital allowances to the owner of the
property and treats lease payments as repayments of principal and payments
of interest. Division 16D does not apply to other tax exempt entities,
such as certain clubs or businesses operated by charities. A Division
16D qualifying arrangement is broadly similar to a finance lease.
- 8.37 Both section 51AD and Division 16D are complex in their application,
in that the operation of the effective control test necessarily requires
a degree of judgment on the part of the tax authorities, especially
in relation to arrangements where the tax exempt remains involved to
a greater or lesser extent in decisions relating to the arrangement.
However, section 51AD is more controversial because the complexity is
exacerbated by the severity of its application.
Has the Repeal of Sections 51AD and Division
16D been Canvassed Previously?
The Ralph Review
The repeal of sections 51AD and Division 16D was urged
in submissions to the Review of Business Taxation (the Ralph Review) which
was chaired by Mr John Ralph in 199899. The Review in its report (July
1999) A
New Tax System Redesigned (the Ralph Review) made the following recommendations
that will impact on infrastructure investment.
- abolition of section 51 AD (Recommendation 10.9, page 392), and
- replacing Division 16D under recommended removal of accelerated depreciation
(Recommendation 10.10page 393).
Shaping Regional Australias
Future
The House of Representatives Standing Committee on Primary
Industries and Regional Affairs inquired into infrastructure and the development
of Australias regional areas and submitted its report Time
Running Out: Shaping Regional Australias Future in May 2001.
The Australian Council of Infrastructure Development
(AusCID) had urged the repeal of section 51AD as it unnecessarily delayed
projects, added significant costs and reduced community benefit from major
private sector investment in infrastructure. The comments in Chapter
4 of this report are set out below.
Sections 51 AD and Division 16D
Other taxation considerations closely bound up with the
accelerated depreciation provisions include Sections 51AD and Division
16D of the Income Tax Assessment Act 1936. These provisions were the subject
of much representation during the inquiry with the former, according to
AusCID, 'the most significant hurdle which is constraining increased private
investment in public infrastructure'.(71) Removal of Section
51AD was essential because it unnecessarily delayed projects, added significant
costs and reduced community benefit from major private sector investment
in infrastructure. Similar sentiments were expressed by other parties:
By private sector provision, the value of depreciation and other
concessions are potentially available to State Governments. In a new
environment of much greater cooperation on Federal State finances
the regulations prohibiting tax benefit transfer are an anachronism.
The abolition of section 51AD and the reform of Division 16D should
be priority outcomes from the review of business taxation.(72)
A comprehensive statement of the problems associated
with these provisions was set out in AusCIDs submission to the Ralph
review. In brief, Section 51AD was devised to prevent government control
of privately financed infrastructure in 'an era where there was no private
ownership and little private management of infrastructure in Australia'.
Furthermore, 'its application was too broad and the consequences of its
breach to severe'.
Government Response
On 14 May 2002 the Minister for Revenue and Assistant
Treasurer, Senator Helen Coonan, in announcing the Government's programme
for delivering the next stage of business tax reform measures foreshadowed
that legislation for replacing section 51AD and the associated Division
16D provisions will be introduced in the Autumn 2003 sittings.(73)
However, the Minister indicated that while there is broad agreement with
the States and private sector on a framework to replace the existing section
51AD and the associated Division 16D provisions, significant boundary
and implementation issues remain to be resolved. Further consultation
on these issues will be undertaken through the course of 2002-03.
- NSW Government, Working with Government. Private Financing of
Infrastructure and Certain Government Services in NSW, November
2000, at
- Bureau of Transport and Communications Economics, Benefits of
Private Sector Involvement in Road Provision: A Look at the Evidence,
Working Paper 33, June 1997, p. 1.
- In NSW, PPPs are called Privately Financed Projects (PFPs).
- For readers interested in a (generally positive) assessment of
PPPs in the UK, see PricewaterhouseCoopers at
- OECD, OECD Economic Surveys: United Kingdom, OECD, Paris
2002, pp. 120 and 121.
- See McCann
FitzGerald legal briefing.
- Australian Council for Infrastructure Development, What are
Public Private Partnerships?, at
- J. Pierce and I. Little, 'Taxpayers need value from partnerships',
Australian Financial Review, 8 April 2002.
- OECD, op. cit., pp. 117 and 119.
- E. S. Savas, Privatization and PublicPrivate Partnerships,
Seven Bridges Press, New York 2000, p. 241.
- Michael B. Gerrard, 'Public-Private Partnerships', Finance
and Development, vol. 38, no. 3, September 2001.
- Partnerships Victoria, Risk Allocation and Contractual Issues
at
, p. 7.
- See UK Treasury,
- Partnerships Victoria, op. cit., Overview, p. 7.
- Economic Planning Advisory Commission, Private Infrastructure
Task Force Report, AGPS, September 1995, p. xii.
- UK Treasury Private Finance Initiative Taskforce (web site no longer
available). The Taskforce became
Partnerships UK ,
which is now partly privately owned.
- Michael B. Gerrard, op. cit.
- ibid.
- Grahame Allen, The Private Finance Initiative (PFI), House
of Commons Library Research Paper 01/117, 18 December 2001, p. 22
at:
- NSW Government, op. cit.
- See UK Treasury at
.
- Australian Council for Infrastructure Development, personal communication.
- For a comprehensive discussion of procedures for determining whether
PPPs offer value for money, see UK National Audit Office, Examining
the value for money of deals under the Private Finance Initiative,
13 August 1999 at
- NSW Treasury, Private Provision of Public Infrastructure and
Services, Research and Information Paper, April 2002, p. 2 at
- Grahame Allen, op. cit., p. 25.
- ibid., pp. 25-6.
- J. Pierce and I. Little, op. cit.
- Industry Commission, Private Investment in Urban Roads,
IC Information Papers, October 1997, p. xi at
- Michael B. Gerrard, op. cit.
- For an analysis of the drivers of value for money, see Value
for Money Drivers in the Private Finance Initiative: A Report
by Arthur Andersen and Enterprise LSE, commissioned by the UK Treasury
Taskforce, London, 2000.
- For definitions of these and other terms, see for example, the
Victorian Government's Guidance Material on Risk Allocation and
Contractual Issues at
and the Tasmanian Department of Treasury and Finance, Guiding
Principles for Private Sector Participation in Public Infrastructure
Provision at
- UK Treasury Private Finance Initiative Taskforce, op. cit.
- Province of New Brunswick, 'Public-private Partnerships', at
- Michael B. Gerrard, op. cit.
- Bureau of Transport and Communications Economics, op. cit., p.
7.
- UK Treasury Private Finance Initiative Taskforce, op. cit.
- Commonwealth Policy Principles for the Use of Private Financing.
Paper issued by the Hon. John Fahey, Minister for Finance and Administration,
October 2001, p. 11 at
- For additional information, see
- NSW Treasury, op. cit., p. 2.
- Michael B. Gerrard, op. cit.
- EPAC, EPAC Private Infrastructure Task Force Final Report,
AGPS, September 1995, p. 42.
- Bureau of Transport and Communications Economics, op. cit., p.
9.
- NSW Treasury, op. cit., p. 4.
- J. Pierce and I. Little, op. cit.
- The debate about the relative merits of public and private finance
is complicated and unresolved. The following does not enter this debate
but merely seeks to set out the different viewpoints.
- NSW Treasury, op.cit., p. 4.
- Commonwealth Policy Principles for the Use of Private Financing.
Paper issued by the Hon. John Fahey, Minister for Finance and Administration,
October 2001, p. 5 at
Some argue that the ability of government to pool risks means that
there is no need for the public sector to be risk averse.
- J. Pierce and I. Little, op. cit.
- Jim Longley, Head of Government Finance, Commonwealth Bank of
Australia, speech given to the National Infrastructure Summit, Melbourne,
15 August 2002.
- Bureau of Transport and Communications Economics, op. cit., p.
10.
- Grahame Allen, op. cit., p. 22.
- Accounting Standards Board at
- Present value is the worth in today's dollars of a future stream
of returns or costs. To obtain present value, a discount rate is used
to discount these future returns and costs.
- NSW Treasury, op.cit., p. 9.
- Australian Council for Infrastructure Development, Australia
at a CrossroadsPublic/Private partnerships or Perish?, at:
- For example, adopting a standard definition of force majeure in
contracts involving hospitals.
- See PPP Forum at
- Grahame Allen, op. cit., p.30.
- Jens Lundsgaard, 'Competition and Efficiency in Publicly Funded
Services' OECD Economics Department Working Paper no. 331, 6 June
2002 at
- OECD op. cit., p. 121.
- See Department of Defence at
- See Minister for Defence, press release 316/2002, 28 June 2002,
at
- See Department of Finance and Administration at
- Department of Transport and Regional Services at
- The patrol boats proposal involved uninsurable risk that stemmed
from the fact that the boats could be used for defence purposes.
- L. Taylor and L. Allen, 'Minchin won't commit to PPPs', Australian
Financial Review, 11 July 2002, p. 3.
- Speech to the Australian Financial Review Infrastructure Summit,
15 August 2002, at
- J. Pierce and I. Little, op. cit.
- NSW Treasury, op. cit., p. 3.
- N Middleton,
, published in the PPP Global Directory by the International Project
Finance
- Australian Council for Infrastructure Development, Submission no.
215, p. 7.
- Tourism Task Force, Submission, no. 227, p. 5.
- Minister for Revenue and the Assistant Treasurer, 'Maintaining
the Momentum of Business Tax Reform',

|
 |