Skip to section navigationSkip to content Commonwealth of Australia Coat of Arms Parliament of Australia - Department of the Parliamentary Library
HomeSenateHouse of RepresentativesLive BroadcastingThis Week in Parliament FindFrequently asked questionsContact


Mandatory renewable energy target (MRET)

A mandatory renewable energy target (MRET) is a set percentage, or an amount of electricity (expressed as either a percentage of total electricity generated or as a set amount of electricity) that is required to be generated from renewable sources, such as solar, wind, biomass or hydro.

The Commonwealth Government's MRET commenced on 1 April 2001. The Renewable Energy (Electricity) Act 2000 (the Act) currently requires the generation of 9,500 gigawatt hours (GWh) of extra renewable electricity per year by 2010.

Interim annual targets have been set to ensure that there will be consistent progress towards achieving the 9,500 GWh target by 2010 and that all of the investment does not occur in the final years of the scheme. Annual targets set in Section 40 of the Act are enforceable on 'liable entities' and apply to calendar years up to and including 2020.

The aim of the renewable energy target is to increase the production of renewable energy. Under section 31 of the Act, all electricity retailers and wholesale buyers who make 'relevant acquisitions' have a legal liability to contribute towards the generation of additional renewable energy. They are called liable entities, and meet their legal obligation by acquiring renewable energy certificates. The liable parties then surrender renewable energy certificates (RECs) in proportion to their acquisitions of electricity. Each REC represents one megawatt hour (MWh) of eligible renewable electricity.

If a liable party does not discharge their liability by surrendering RECs, then the Renewable Energy Shortfall Charge of $40 per REC applies. Penalties can be redeemed if the appropriate number of RECs are surrendered within the next three years of the penalty being paid and there are sufficient RECs offered for surrender against the compliance year being assessed.

For liable parties to meet their proportion of the interim targets they need to know their total amount of relevant acquisitions. The total liable purchases are multiplied by the Renewable Power Percentage (RPP). The RPP is specified in the relevant regulations. The RPP for 2008 is 3.14 per cent. This figure reaches 10 per cent in 2010.

There are two different ways for renewable energy to be eligible under the Act:

  • renewable energy power stations, once accredited, can create RECs from generation in excess of the power station's 1997 generation baseline level, or
  • deemed output systems, which when installed in a given geographic area are deemed to be able to produce a defined amount of electricity for the purposes of the Act.
Deemed output systems include:
  • eligible solar water heaters (SWHs) as listed in the Regulations. The amount of eligible RECs for SWH models varies as individual SWH models are tested to determine the amount of electricity that they displace and are listed in the Regulations with a deemed REC value, and
  • small generation units (SGUs), such as photovoltaic systems, mini electric hydro systems and small wind systems. The amount of eligible RECs for SGUs varies depending on the size of the SGU and the amount of time that the SGU is deemed to generate electricity.
Owners of deemed systems are eligible for RECs by directly creating their RECs or assigning their right to create RECs to an agent once. Agents, who must be registered under the Act, can create RECs from individuals who have assigned their right to create RECs to the registered agent from their deemed output systems.

The Rudd Government has set a target of 20 per cent share for renewable energy in Australia's electricity supply by 2020. This requires the government to increase the current MRET from 9,500 GWh in 2010 to 45,000 GWh in 2020. The expanded measure is to be phased out between 2020 and 2030 as the proposed Australian emissions trading scheme matures and prices become sufficient (i.e. high enough) to ensure that an MRET is no longer required to drive deployment of renewable generation technologies.

At the Council of Australian Governments (COAG) meeting in December 2007, the Commonwealth and states agreed to work cooperatively to bring the existing MRET and the various state-based targets into a single, expanded national MRET scheme by early 2009. An implementation plan and interim report on progress was put to COAG at its March 2008 meeting. The final design is to be provided to COAG for consideration at its October 2008 meeting.

A review, titled Renewable opportunities—a review of the operation of the Renewable Energy (Electricity) Act 2000, was conducted in the third year of the MRET's operation by a panel independent of the government which assessed various issues associated with the MRET and its legislation. The review made some thirty recommendations.

Costs to the economy

The initial development of the Commonwealth’s MRET was informed by a number of studies, one of which directly focused on the effects of the MRET on the wider economy. The Econtech report found the long-run effect of the MRET on gross domestic product (GDP) would be slightly negative, at –0.03 per cent per annum. The Consumer Price Index (CPI) was predicted to grow slightly (0.05 per cent per annum), while employment was predicted to remain effectively stable, with initial decreases in employment offset by later employment growth. The report concluded there would be small and negative macroeconomic consequences from the measure, but also recognised the review was being concluded early in the MRET's lifecycle, making assessments of its economic impact diffucult.

Benefits

The review of the Commonwealth’s MRET scheme suggested that it had the following benefits:

  • increased employment in the renewable energy industry, especially in remote areas where wind farms were situated
  • the scheme was a stimulus to further regional development, as the relevant power generation projects were often sited well away from major urban areas
  • diverse environmental benefits, including improved waste and non-native weed management (through biomass power generation), forestry waste management and air quality management, and
  • obviously, further development of the renewable energy industry.


7 November, 2008 Comments to: web.library@aph.gov.au
Last reviewed 7 November, 2008 by the Parliamentary Library Web Manager
© Commonwealth of Australia
Parliament of Australia Web Site Privacy Statement
Images courtesy of AUSPIC
DNR08